Works Programme Revisions. a. The Contractor shall immediately notify the Authority’s Engineer in writing of the need for any changes in the Works Programme, whether due to a change of intention or of circumstances or for any other reason. Where such proposed change affects timely completion of the Works or any Project Milestone Date. The proposed revised Works Programme shall show the sequence of operations of any and all works related to the change and the impact of changed work or changed conditions.
Appears in 47 contracts
Samples: Contract Agreement, Contract Agreement, Draft Contract Agreement
Works Programme Revisions. a. The Contractor shall immediately notify the Authority’s Engineer in writing of the need for any changes in the Works Programme, whether due to a change of intention or of circumstances or for any other reason. Where such proposed change proposedchange affects timely completion of the Works or any Project Milestone Date. The proposed revised Works Programme shall show the sequence of operations of any and all works related to the change and the impact of changed work or changed conditions.
Appears in 3 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Works Programme Revisions. a. The Contractor shall immediately notify the Authority’s Engineer in writing of the need for any changes in the Works ProgrammePro gramme, whether due to a change of intention or of circumstances or for any other reason. Where such proposed change affects timely completion of the Works or any Project Milestone Date. The proposed revised Works Programme Pro gramme shall show the sequence of operations of any and all works related to the change and the impact of changed work or changed conditions.
Appears in 2 contracts