Examples of Change Order Proposal in a sentence
Any Change Order Proposal or request for an adjustment in the Contract Time shall demonstrate the impact on the critical path of the schedule.
Contractor shall include any request for a change in the Contract Sum in its Change Order Proposal.
If the clarification results in a change in the scope of the Work and causes a change in the Contract Sum and/or Contract Time, then Contractor shall submit a Change Order Proposal Evaluation (CPE) to the A/E with a copy to the ODR.
Contractor shall include any request for a change in the Contract Time in its Change Order Proposal.
Contractor’s Change Order Proposal, or request for adjustment in the Contract Sum, shall be accompanied by a complete itemization of the costs, including labor, material, subcontractor costs, and overhead and profit.