Examples of Concessionaire Change in a sentence
For the avoidance of doubt the Concessionaire shall not amend or change the Concessionaire's Proposals except by way of a Concessionaire Change.
Where the Concessionaire Change is necessary for the Concessionaire to comply with Section 14.3, HPTE shall not be entitled to unreasonably withhold its consent to such a Concessionaire Change provided the implementation, rectification and consequential impact, is at the Concessionaire's expense.
A Concessionaire Change pursuant to this Section 11.4.1 will not, unless it is consented to by the Province’s Representative as provided in Section 11.4.3, in any way qualify or relieve the Concessionaire of its primary responsibility to comply with, satisfy and perform the Construction Output Specifications notwithstanding any review of or failure to object to the proposed Concessionaire Change by the Province's Representative.
The Concessionaire will not proceed to implement a proposed Concessionaire Change unless and until there has been no objection in accordance with the Review Procedure (on the grounds set out in paragraph 3.2 of Part 2 of Schedule 8 [Review Procedure]) and the relevant Concessionaire Change Certificate has been issued by the Concessionaire’s Representative and duly countersigned by the Province's Representative in accordance with paragraph 7 of Part 2 of Schedule 8 [Review Procedure].
For greater certainty, except to the extent provided in Part 3 of Schedule 13 [Concessionaire Changes] or in paragraph (r) of the definition of "Compensation Event" in Section 1 of Schedule 1 [Definitions and Interpretation], no additional payment to the Concessionaire or adjustment to the Total Performance Payment will be made as a consequence of implementation of a Concessionaire Change.
For greater certainty, except to the extent provided in Part 3 of Schedule 13 [Concessionaire Changes], no additional payment to the Concessionaire or adjustment to the Performance Payment will be made as a consequence of implementation of a Concessionaire Change.
The Concessionaire will not proceed to implement a proposed Concessionaire Change unless and until there has been no objection in accordance with the Review Procedure (on the grounds set out in paragraph 3.2 of Part 2 of Schedule 8 [Review Procedure]) and the relevant Concessionaire Change Certificate has been issued by the Concessionaire’s Representative and duly countersigned by the Province’s Representative in accordance with paragraph 7 of Part 2 of Schedule 8 [Review Procedure].
A Concessionaire Change pursuant to this Section 11.4.1 will not in any way qualify or relieve the Concessionaire of its primary responsibility to comply with and satisfy the Construction Output Specifications notwithstanding any review of or failure to object to the proposed Concessionaire Change by the Province’s Representative.
All costs arising out of any Concessionaire Change of Scope requested by Concessionaire under this Clause 16.1.2 during the Construction Period shall be borne by the Concessionaire.
In case the Authority does not respond to the Concessionaire’s proposal for Concessionaire Change of Scope within thirty (30) days from the date of receipt of the proposal, it shall be deemed that the change of scope of work have not been accepted by the Authority.