Full Commercial Operation Date definition

Full Commercial Operation Date means the date on which Seller confirms in writing to Buyer that the Production Facility is fully operational and prepared to commence production of the blades at the Planned Capacity. [...***...]
Full Commercial Operation Date. The date notified by the Seller in accordance with Clause 5.7;
Full Commercial Operation Date. Means the date agreed on by the Parties on which the Plant is ready for regular daily operation and capable of providing electricity to the Delivery Point on a sustained basis as contemplated under the Agreement.

Examples of Full Commercial Operation Date in a sentence

  • If the Full Commercial Operating Date is not achieved by the Long Stop Full Commercial Operation Date, other than in the circumstances described in Clause 11.1.1 of this Agreement, the Buyer shall be entitled to terminate the Agreement.

  • Project Investment Obligation Seller shall achieve Full Commercial Operation prior to the Guaranteed Full Commercial Operation Date or make cash expenditures of at least of Qualified Capital for the Project Seller Employment Obligation During each Contract Year during the Term of this Agreement, Seller shall employ no less than full time equivalent workers, .

  • Period of Cover:The actual construction, testing and Commissioning of the Plant for mobilisation of Seller’s contractors until the day following Full Commercial Operation Date.

  • Seller shall obtain a CEC Certification for the Facility by the date that is six (6) months following the Full Commercial Operation Date.

  • The Parties acknowledge and agree that Seller intends to undertake activities to expand the Initial Contract Capacity of the Project from 10 MW as of the Execution Date to the Full Contract Capacity as of the Guaranteed Full Commercial Operation Date.


More Definitions of Full Commercial Operation Date

Full Commercial Operation Date for a Plant, the date specified as such by the Seller with respect to such Plant ((including pursuant to an Initial Notice of Fourth Plant Exercise or a Subsequent Notice of Fourth Plant Exercise, according to the case) in accordance with Clause 7.10;
Full Commercial Operation Date is defined in the Power Purchase Agreement.
Full Commercial Operation Date means the date on which Full Commercial Operation shall have occurred.
Full Commercial Operation Date means the date on which Seller has (a) notified Buyer that Full Commercial Operation has occurred, and (b) provided to Buyer a certification of a Licensed Professional Engineer, substantially in the form attached hereto as Appendix VI-C, demonstrating satisfactory completion of the Commercial Operation Certification Procedure as provided in Appendix V hereto in respect of Full Commercial Operation.
Full Commercial Operation Date means the date on which the Commercial Operation Date of the last Generating Facility occurs.
Full Commercial Operation Date means the date when the full MW capacity of the Project is commercially available, but not later than January 1, 2002.
Full Commercial Operation Date the date specified as such by the Seller in accordance with Clause 7.10;