Notice to Proceed Effective Date definition

Notice to Proceed Effective Date or “Full Notice to Proceed Effective Date” shall have the meaning set forth in Section 5.1.2.
Notice to Proceed Effective Date shall have the meaning set forth in Section 5.1.3.

Examples of Notice to Proceed Effective Date in a sentence

  • The Contract Price is not subject to escalation unless (i) the Full Notice to Proceed Effective Date is after the date set forth in Exhibit A, or (ii) there is an increase in the price resulting from a adverse major national or international Force Majeure event of any Equipment or materials, such as rental equipment, structural steel, rebar or concrete, or Subcontractor prices, after the Contract Price has been determined.

  • In the event the Full Notice to Proceed Effective Date is after such date, or in the event of any price change due to such national or international Force Majeure event, then the Contract Price, Project Schedule and Guaranteed Completion Date shall be subject to adjustment as determined by Contractor.

  • The Services to be provided by Service Provider under this Agreement shall commence on the date of the Notice to Proceed (Effective Date), and be completed in twelve (12) calendar months.

  • The Services to be provided by CONSULTANT under this Agreement shall commence on the date of the Notice to Proceed (Effective Date), and be completed no later than October 2014.

  • Provide back feed power for start up, commissioning and testing by not later than 11 months after the Notice to Proceed Effective Date.

  • Within ninety (90) days following the Full Notice to Proceed Effective Date, Contractor shall prepare and submit to GEC a Critical Path Schedule (the “Project Schedule”), consistent with the Project Schedule Summary, which shall be designed to have the Work completed on a timely basis by the Guaranteed Completion Date.

  • Within ninety (90) days following the Full Notice to Proceed Effective Date, GEC shall prepare, or have prepared, and submit to Owner a Critical Path Schedule (the “Project Schedule”), consistent with the Project Schedule Summary, which shall be designed to have the Work completed on a timely basis by the Guaranteed Completion Date.

  • The Services to be provided by ALS under this Agreement shall commence on the date of the Notice to Proceed (Effective Date), and be completed in accordance with Exhibit “A”.

  • The Services to be provided by Service Provider under this Agreement shall commence on the date of the Notice to Proceed (Effective Date), and be completed in accordance with [ ].

  • Subtracting these two contributions and the two-phonon cross section, leads to the value 1485 ±100 mb shown in the Table.

Related to Notice to Proceed Effective Date