Examples of Permitted Extensions in a sentence
If the Commercial Operation Date occurs after the Guaranteed Commercial Operation Date after giving effect to Permitted Extensions or Force Majeure, then Buyer shall be entitled to declare an Event of Default and collect a Termination Payment pursuant to Article Five.
If the Commercial Operation Date occurs after the Guaranteed Commercial Operation Date after giving effect to Permitted Extensions, then Buyer shall be entitled to declare an Event of Default and collect the Damage Payment pursuant to Article Five.
For sake of certainty, Buyer shall retain all Daily Delay Damages drawn (or which Buyer is entitled to draw) as a result of Seller’s failure to meet the Guaranteed Commercial Operation Date and the Guaranteed Construction Start Date (both as may be extended by Permitted Extensions), if Seller fails to meet the Guaranteed Commercial Operation Date (as may be extended by Permitted Extensions).
Seller shall be entitled to the return of all Daily Delay Damages collected by Buyer as a result of Seller’s failure to meet the Guaranteed Construction Start Date only if Seller meets the Guaranteed Commercial Operation Date (as may be extended by Permitted Extensions) as provided further in Section 8.4(c) of this Agreement.
Permitted Extensions shall become effective only with respect to the Commitments of the Lenders of the Specified Class that accept the applicable Extension Offer (such Lenders, the “Extending Lenders”) and, in the case of any Extending Lender, only with respect to such Lender’s Loans and Commitments of such Specified Class as to which such Lender’s acceptance has been made.