Pilot Completion Date definition

Pilot Completion Date means the date set forth on Schedule A.
Pilot Completion Date means the date set forth in Exhibit A.

Examples of Pilot Completion Date in a sentence

  • The Parties intend to complete the Pilot no later than the Pilot Completion Date.

  • The term of the Pilot Phase Financing shall commence on NTP and end on the earlier of (a) Conditional Approval of the Pilot Completion Date or (b) three (3) years following NTP.

Related to Pilot Completion Date

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Construction Completion Date means the date by which the overall development of the Project is completed in accordance with the provisions of this Agreement and when the Construction Completion Certificate is issued by the Independent Engineer as per Article 14.1.

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Final Completion Date means the date on which Final Completion occurs.

  • Substantial Completion Date means the date on which Substantial Completion occurs.

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • Project Completion means completion of the Redevelopment in accordance with this Agreement to the state where the whole of the Morley Shopping Centre, as so redeveloped, is capable of occupation for its intended purpose;

  • Scheduled Completion Date shall be the date set forth in Clause 10.3;

  • Construction Completion means physical construction of a cleanup action component is complete.

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Outside Completion Date shall have the meaning assigned to such term in Section 6.3(d).

  • COMPLETION TIME means the period by ‘date/month’ specified in the ‘Letter of Intent/Award’ or date mutually agreed upon for handing over of the intended scope of work, the erected equipment/plant which are found acceptable by the Engineer, being of required standard and conforming to the specifications of the Contract.

  • Construction Commencement Date means the date set out in the Addendum, if applicable, by which you must commence construction of the Hotel. For the Hotel to be considered under construction, youmust have begun to pour concrete foundations for the Hotel or otherwise satisfied any site-specific criteria for “under construction” set out in the Addendum.

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Improvement completion assurance means a surety bond, letter of credit,

  • Project Start Date means the first Milestone Start Date specified in Schedule B;

  • Billing Commencement Date means the earlier of:

  • Construction Period means the period commencing from the Appointed Date and ending on the date of the Completion Certificate;

  • Testson Completion means the tests which are specified in the Contractor agreed by both Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on Completion] before the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Completion Rate means the percentage of an apprenticeship cohort who receives a certificate of apprenticeship completion within 1 year of the projected completion date. An apprenticeship cohort is the group of individual apprentices registered to a specific program during a 1 year time frame, except that a cohort does not include the apprentices whose apprenticeship agreement has been cancelled during the probationary period or who have transferred.

  • Commercial Operation Date means the date on which a Material Project is substantially complete and commercially operable.

  • Commissioning Date means that date when construction of the contemplated Project is complete, and the Maintenance Term commences;

  • Framework Commencement Date means [insert date dd/mm/yyyy];