Examples of Preliminary Change Instruction in a sentence
A Preliminary Change Instruction will include sufficient description of the contemplated Change, including any requirements under Section 2.12(b) of this Schedule to permit Project Co to prepare a Change Report.
The Preliminary Change Instruction may indicate whether the Authority considers that the subject matter of the Change and the Change Report should contemplate a Conditional Change Certificate in advance of a Change Certificate, and any matters referred to in Section 2.13(b) of this Schedule that the Authority considers Project Co should address in respect of a possible Conditional Change Certificate.
A Preliminary Change Instruction will include sufficient description of the contemplated Change, including any requirements under Section 1.13(b) of this Schedule, to permit Project Co to prepare a Change Report.
Subject to Section 2.3 of this Schedule, as soon as practicable and in any event, to the extent possible, within 15 Business Days after receipt of a Preliminary Change Instruction, or such longer period as the parties agree acting reasonably, Project Co will at its cost prepare and deliver to the Authority a Change Report for the contemplated Change described in the Preliminary Change Instruction.
A Preliminary Change Instruction will include sufficient description of the contemplated Change, including any requirements under Section 3.8(b) of this Schedule 12 [Changes], to permit the Contractor to prepare a Change Report.
C ConstructionApply pigmented cure and seal compound to the inside and top faces of concrete parapets after the required surface finish has been applied per standard spec 502.3.7. Apply before opening to traffic and before suspending work for the winter.
Subject to Section 2.2 of this Schedule 12 [Changes], as soon as practicable and in any event, to the extent reasonably possible, within 15 Business Days after receipt of a Preliminary Change Instruction, or such other period as the parties may agree in writing acting reasonably, the Contractor will, at its cost, prepare and deliver to BC Hydro a Change Report, signed by the Contractor’s Representative, for the contemplated Change described in the Preliminary Change Instruction.
BC Hydro may in writing modify a Preliminary Change Instruction at any time prior to the parties reaching an agreement on the Change Report in which case Project Co will, as soon as practicable and in any event not more than 10 Business Days after receipt of such modification (or such longer period as the parties acting reasonably may agree in writing), notify BC Hydro of any consequential changes to the Change Report.
A Preliminary Change Instruction will include sufficient description of the contemplated Change, including any requirements under Section 2.13(b) of this Schedule, to permit Project Co to prepare a Change Report.
A Preliminary Change Instruction will include sufficient description of the contemplated Change, including any requirements under Section 2.10(b) of this Schedule to permit Project Co to prepare a Change Report.