RA Start Date definition

RA Start Date shall be the later of the Initial Energy Delivery Date or the Expected PCDS Date or FCDS Date according to the deliverability type selected in Section A of the Cover Sheet.
RA Start Date means [insert MONTH, DAY, YEAR], which is the later of the Initial Energy Delivery Date and the [Expected FCDS Date][Expected PCDS Date].

Examples of RA Start Date in a sentence

  • Seller’s interconnection, distribution and/or transmission arrangements shall provide for the deliverability type selected in Section A of the Cover Sheet as of the RA Start Date and throughout the Delivery Term.

  • Seller covenants that it shall comply with all CAISO Tariff requirements and/or Participating TO tariff requirements, as applicable, that are applicable to an Interconnection Customer (as defined in the CAISO Tariff or Participating TO’s tariff, as applicable) and shall take any other necessary action, including payment of fees and submission of requests, applications or other documentation, to promote the completion of the Electric System Upgrades prior to the RA Start Date.

  • Seller covenants that it shall comply with all CAISO Tariff requirements and/or Participating TO tariff requirements, as applicable, that are applicable to an InterconnectionCustomer (as defined in the CAISO Tariff or Participating TO’s tariff, as applicable) and shall take any other necessary action, including payment of fees and submission of requests, applications or other documentation, to promote the completion of the Electric System Upgrades prior to the RA Start Date.

Related to RA Start Date

  • Start Date for Term Calculation Purposes Only: Regardless of actual award/effective date of Contract, for Agreement “term” calculation purposes only, the Agreement “start date” is the last day of the month that Award Notifications are anticipated as published in the Solicitation. Example: If the anticipated award date published in the Solicitation is August 27, 2020 but extended negotiations delay award until September 24, 2020 the end date of the resulting initial “two-year” term Agreement, (which is subject to an extension(s)) will still be August 31, 2022 in this example

  • Term Start Date has the meaning set forth in Section 1.01.

  • Project Start Date means the first Milestone Start Date specified in Schedule B;

  • Contract Start Date means the date specified in your Contract for Signature asthe date this Contract starts;

  • Service Start Date means the date on which services were first supplied under this Agreement.

  • Index Start Date means 19 January 2015.

  • Investment Start Date : means 22 July 2022 or if such day is not a Scheduled Trading Day, the following day which is a Scheduled Trading Day.

  • Supply Start Date means the date(s) specified in clause 2.8;

  • Start-up Period means up to 7 Academy Financial Years and covers the period up to and including the first Academy Financial Year in which all age groups are present at the Academy (that is, all the pupil cohorts relevant to the age range of the Academy will have some pupils present).

  • Commencement Date means the date of this Agreement.

  • Commercial Operation Date means the date on which a Material Project is substantially complete and commercially operable.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Initial Operation means the first integral operation of the complete equipment covered under the Contract with the sub-system and supporting equipment in service or available for service.

  • Benchmark Transition Start Date means, in the case of a Benchmark Transition Event, the earlier of (a) the applicable Benchmark Replacement Date and (b) if such Benchmark Transition Event is a public statement or publication of information of a prospective event, the 90th day prior to the expected date of such event as of such public statement or publication of information (or if the expected date of such prospective event is fewer than 90 days after such statement or publication, the date of such statement or publication).

  • Billing Commencement Date means the earlier of:

  • Lease Commencement Date has the meaning specified in Section 3.2 of the Master Lease.

  • Services Start Date means the date as set out in the Specification (Schedule 1);

  • Delivery Period Termination Date Has the meaning specified in the Related Pass Through Trust Supplement.

  • Hire Date has the meaning given to it in Section 2.6(a).

  • Framework Commencement Date means [insert date dd/mm/yyyy];

  • Service Commencement Date in respect of a Service or a particular instance of a Service means the date on which that particular Service or particular instance of a Service is first provided to the Customer, or as otherwise explicitly set out in this Agreement;

  • Construction Start Date means the later to occur of the date on which Seller delivers to Buyer (a) a copy of the Notice to Proceed that Seller has delivered to the EPC Contractor for the Project, and (b) a written Certification substantially in the form attached hereto as Appendix IV-1.

  • Project Commencement Date means the commencement date notified to the Minister pursuant to clause 4(1);

  • Commercial Operations Date or "COD": The date on which Facility first achieves Commercial Operations.

  • Start means the relevant Compounded Index value on the day falling the Relevant Number of Index Days prior to the first day of the relevant Interest Period.

  • Purchase Termination Date means the date upon which the Transferor shall cease, for any reason whatsoever, to make purchases of Receivables from the Seller under the Receivables Purchase Agreement or the Receivables Purchase Agreement shall terminate for any reason whatsoever.