Examples of Record Schedule in a sentence
Disposal and destruction of per- sonnel records shall be in accordance with the General Record Schedule issued by the General Services Admin- istration for the records or, alter- natively, with Office or agency records control schedules approved by the Na- tional Archives and Records Service of the General Services Administration.
The Record Schedule, once approved, serves as the final update of the Project Schedule.
Record Schedule: A CPM schedule that shows the actual start and finish date of each activity, durations, and all changes.
Record As-Built Schedule: A Record Schedule accurately reflecting actual progress of Work shall be submitted, as part of this Contract's Record Documents.
Neither the Contract Time nor Contract Amount shall be changed due to a delay in Contractor’s early completion date until all the corresponding Contract Float available in the Record Schedule at the start of the delay is used and performance of the specified Work extends necessarily beyond that Contract Time.
The contractor shall prepare a Record Schedule that includes actual start and actual finish dates for all activities.
The records of the Board and its subcommittees shall be managed in accordance with General Record Schedule 6.2, Federal Advisory Committee Records, or other approved agency records disposition schedule, and the appropriate DoD policies and procedures.
Division 01 Section “Construction Progress Documentation" for construction schedules as basis for Record Schedule.
In accordance with Section 119.0701, Florida Statutes, the Professional or Contractor (referred hereinafter in all of the “Project Records” section collectively as “Professional”), when acting on behalf of the County, as provided under 119.011(2), F.S., shall keep and maintain public records as required by law and retain them as provided by the General Record Schedule established by the Department of State.
The Contractor shall not recover from the County (a) acceleration costs incurred to overcome delays which warrant extensions in Contract Time but exclude changes in Contract Amount, (b) escalation costs for any part of the Work having Contract Float or not delayed beyond the late dates in the Record Schedule, or (c) delay costs not expressly allowed herein, as supplemented.