Examples of Required Final Completion Date in a sentence
An equitable adjustment by Agreed Change shall be made for increases in the Contract Sum, Required Substantial Completion Date and Required Final Completion Date on account of any such suspension, delay or interruption.
If no such agreement is reached, Contractor shall give notice to Architect and Owner of its objection to the change, if any, in the Contract Sum, Required Substantial Completion Date and/or Required Final Completion Date proposed in the Change Directive within five (5) business days after receipt of the Change Directive.
Such agreement shall be effective immediately and shall be an “Agreed Change,” which term, as used herein, shall mean any change in the Work as to which Contractor and Owner have agreed as any changes in the Contract Sum, the Required Substantial Completion Date and the Required Final Completion Date.
The Required Final Completion Date will be unchanged by ( ) Days The Required Final Completion Date as of the date of this Change Order therefore is Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary) N/A Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order.
Time is of the essence with respect to the Required Substantial Completion Date and the Required Final Completion Date stated in the Contract Documents.
The date specified as the Required Final Completion Date in the Milestone Schedule.
Time is of the essence with respect to the EPC Contractor’s obligations hereunder, including without limitation the EPC Contractor’s obligation to achieve Substantial Completion prior to the Required Substantial Completion Date and Final Completion prior to the Required Final Completion Date.
The Required Final Completion Date shall only be adjusted by Change Order as provided under this Agreement.
The Required Substantial Completion Date or the Required Final Completion Date shall not be extended unless agreed to by written Project Change Order signed by the Client and the EPC Contractor.
The Parties agree that only significant differences in subsurface conditions that would cause a major change in the manner, means or methods of constructing the foundations would require an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, but mere changes in the number or type of piles would not entitle Contractor to such an extension.