Examples of Station Development Land in a sentence
Provided that it is clarified that the right of way and/ or access to the Redevelopment Land and the Station Development Land, shall be granted to the Developer solely for the purposes of undertaking the Redevelopment Project and/ or the Station Development Project, and the Developer shall have no ownership or leasehold rights in respect of such Redevelopment Land or the Station Development Land or improvements thereof.
Provided that Developer shall ensure that the Station Development Land and the Redevelopment Land is available for use by Authority and/ or Railway, their relevant personnel and end-users (including passengers), in accordance with the approved works programme for the Station Development Project and the Redevelopment Project.
Further, the Developer shall ensure that for the duration commencing from the time when the Station Development Land and the Redevelopment Land is handed over to the Developer by Authority (and/ or its nominee) for the purpose of the Project, and ending at the date on which same are handed back by the Developer to Authority (and/ or its nominee), the Station Development Land and the Redevelopment Land remains free of all encroachments.
In the event that there subsist any common areas, facilities, access points, structures, utilities, or other interfacing areas as between the Site and the Redevelopment Land, or the Site and the Station Development Land, the design, development, construction, operation and maintenance thereof, shall be undertaken by the Developer in accordance with the Interfacing Structures and Areas Plan.
If Developer performs any works in a manner contrary to such Specifications and approved Design & Drawings, the approved works programme for the Station Development Project, the Handover Plan– Station Development Land or any of them and without such reference to the Nodal Officer it shall bear all the costs arising or ensuing therefrom and shall be responsible for all loss to Authority or RLDA or the Railway.
The whole of the works in respect of the Station Development Project shall be executed in perfect conformity with the DPR, Specifications and approved Design & Drawings for the Station Development Project, and in accordance with the approved works programme for the Station Development Project and the Handover Plan – Station Development Land.
In the event the activities proposed to be undertaken during the Transition Phase including handover of Station Development Land have not been completed within the abovementioned period of 3 (three) months, then the Transition Phase shall be extended by a maximum additional period of 90 (ninety) days.
After fulfilment by the Developer of all the Conditions Precedent, IRSDC shall provide to the Developer right of way to the Station Development Land, for the exclusive purposes of undertaking the Station Development Land, in the following manner.
Such Handover Plan – Station Development Land shall be subject to the approval of IRSDC, which may be given subject to any modification or amendments that IRSDC may deem appropriate.
Location map and site plan of the proposed Habibganj Railway Station and allied areas i.e. Station Development Land for the purpose of Station Facility Management is as per Drawing No. ICT-CT-3-ARCH-631 Habibganj Railway Station Areas to be maintained by Facility Manager, read in conjunction with drawing No. ICT-CT-3-ARCH-901 R1 dated 24-09-2014).