Time(s) for Completion definition

Time(s) for Completion means the time(s) stated in Schedule E by which the Supply or any particular Supply or part thereof must be completed, as such time(s) may be adjusted (including in relation to a particular instance of Supply), strictly in accordance with this Agreement;
Time(s) for Completion means the time(s) stated in Schedule D by which the Supply or any particular Supply or part thereof must be completed, as such time(s) may be adjusted (including in relation to a particular instance of Supply), strictly in accordance with this Agreement;
Time(s) for Completion means the time(s) stated in Schedule E by which the Supply or any part thereof must be completed, as such time(s) may be adjusted, strictly in accordance with this Agreement;

Examples of Time(s) for Completion in a sentence

  • Time is of the essence of this Agreement, including without limitation in relation to the Time(s) for Completion.

  • The City shall provide its acceptance or rejection of such recommendation within a reasonable period so as not to delay the Time(s) for Completion.

  • On all matters properly referred to it in writing by the Supplier, the City shall (wherever practicable) give its decision in writing within a reasonable time having regard to the Time(s) for Completion and the Supplier’s obligations with regard to the Supply.

  • The Contractor shall update and revise the program as and when appropriate or when required by the Project Manager, but without modification in the Times for Completion specified in the SCC pursuant to Sub-Clause 8.2 and any extension granted in accordance with GCC Clause 40, and shall submit all such revisions to the Project Manager.

  • The Contractor shall update and revise the program as and when appropriate or when required by the Project Manager, but without modification in the Times for Completion specified in the PCC pursuant to Sub-Clause 8.2 and any extension granted in accordance with GCC Clause 40, and shall submit all such revisions to the Project Manager.

  • Adjustment of Contract Times for Completion In addition to the provisions in the Contract General Conditions, the Trustees will adjust the Contract Time for completion of the Work in accordance with these procedures.

  • The Contractor shall update and revise the program as and when appropriate or when required by the Project Manager, but without modification in the Times for Completion specified in the PC pursuant to Sub-Clause 8.2 and any extension granted in accordance with GC Clause 40, and shall submit all such revisions to the Project Manager.

  • The Contractor shall update and revise the program as and when appropriate or when required by the Project Manager, but without modification in the Times for Completion under GCC Sub-Clause 4.2 and any extension granted in accordance with GCC Clause 34, and shall submit all such revisions to the Project Manager.

  • Alternative Times for Completion [insert “are” or “are not”] permitted.

  • The Contractor shall update and revise the program as and when appropriate or when required by the Project Manager, but without modification in the Times for Completion given in the CC and any extension granted in accordance with CC Clause 40, and shall submit all such revisions to the Project Manager.


More Definitions of Time(s) for Completion

Time(s) for Completion means the time(s) stated in a Request for Supply by which a particular Supply or any part thereof must be completed, as such time(s) may be adjusted, strictly in accordance with this Agreement;
Time(s) for Completion means the date and/or time(s) by which the performance of the Services as required by any Request for Services must be completed;
Time(s) for Completion means the time(s) stated in Schedule E by which the Services or any particular Services or part thereof must be completed, as such time(s) may be adjusted (including in relation to a particular instance of Services), strictly in accordance with this Agreement;
Time(s) for Completion means the time(s) stated in Schedule E by which the Supply or any particular Supply or part thereof must be completed, as such
Time(s) for Completion means the time(s) stated in a Terms Agreement by which a particular article of Property must have been delivered by the Supplier to a Site or Sites;

Related to Time(s) for Completion

  • Time for Completion means the time for completing the Works as stated in the Contract Data (or as extended under Sub-Clause 7.3), calculated from the Commencement Date.

  • Date for Completion means the date for Completion specified in the Contract Specifics.

  • Time of Completion means the time for completing the execution of and passing the Tests on Completion of the Works of any section or part thereof as stated in the Contract (or as extended under Clause...) calculated from the Commencement Date

  • Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.

  • Commissioning Tests means all of the procedures and tests which, in accordance with the Reasonable and Prudent Standard, and in compliance with industry guidelines, practices and standards, are:

  • Study Completion means the database for the Study has been locked and all Essential Documents have been provided to the Sponsor, including a copy of the letter from the Reviewing HREC acknowledging receipt of the final report and/or closure letter from the Principal Investigator.

  • Construction Completion means physical construction of a cleanup action component is complete.

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Commissioning means the process for determining the need for and for obtaining the supply of healthcare and related services by the Trust within available resources.

  • Tests after Completion means the tests (if any) which are specified in the Contract and which are carried out in accordance with the Specification after the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Tests on Completion means the tests which are specified in the Contract or agreed by both Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on Completion] before the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Testson Completion means the tests which are specified in the Contractor agreed by both Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on Completion] before the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Date of Completion with respect to a Project shall mean: (i) the date upon which such Project and all components thereof have been acquired or constructed and are capable of performing the functions for which they were intended, as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; or (ii) the date on which the Issuer determines, upon the recommendation of or in consultation with the Consulting Engineer, that it cannot complete such Project in a sound and economical manner within a reasonable period of time as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; provided that in each case such certificate of the Consulting Engineer shall set forth the amount of all Costs of such Project which have theretofore been incurred, but which on the Date of Completion is or will be unpaid or unreimbursed.

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • service delivery and budget implementation plan means a detailed plan approved by the executive mayor of a municipality in terms of section 53(l)(c)(ii) of the MFMA for implementing the municipality's delivery of municipal services and its annual budget, and which must indicate

  • Phase 1 means the phase of the ATP comprised of: (1) improvements to the State Street Substation; (2) construction of the Proposed Line; (3) the rebuilding of NYSEG’s existing Lines 971 and 000 xxxxx xx Xxxxxxxx Xxxx xx the NYSEG ROW to allow for construction of the Proposed Line as intended; (4) improvements to the Elbridge Substation to accept the Proposed Line; and (5) National Grid’s conveyance to NYSEG of the NYSEG Acquired ROW and such other land interests as contemplated by the Purchase and Sale Agreement.

  • Delivery Schedule means the schedule for the delivery of Services as set forth in attached Annex 3.

  • Completion means the fulfilment of the Related Services by the Supplier in accordance with the terms and conditions set forth in the Contract.

  • Service Complaints For service problems or complaints, you should contact your local utility by calling: AEP Ohio at 000.000.0000. IN THE EVENT OF AN ENERGY-RELATED EMERGENCY, SUCH AS A POWER OUTAGE OR DOWNED POWER LINE, PLEASE VACATE THE AREA BY A SAFE DISTANCE AND CALL YOUR LOCAL UTILITY or 911. Authorization/Representation/Letter of Agency:By entering into this Agreement, you authorize XOOM to act on your behalf under your local utility’s tariffs in accordance with the rules and regulations of the PUCO. You acknowledge that you are your local utility account holder, or a person legally authorized to execute this Agreement on behalf of the account holder for electricity service and are at least eighteen (18) years of age. You agree to authorize XOOM to obtain your credit information and you agree to authorize your local utility to release all information relating to your historical and current electricity usage, billing and payment history to XOOM or its authorized representatives. You acknowledge that XOOM has full authority to make all rates and tariff selections necessary to meet its obligations under this Agreement. You may rescind this authorization at any time by contacting XOOM. Neither your social security number, customer account number nor any other customer financial information will be released by XOOM, except where such release is required by court order or by Commission Order or Rule, without your affirmative written consent. Execution of this Agreement shall constitute authorization for the release of this information to XOOM.

  • Notice to Proceed means notice issued by the OPWC pursuant to Section IV of this Agreement. "OPWC" means the Ohio Public Works Commission created pursuant to Revised Code Section 164.02.