Transmission Interconnection Request definition
Examples of Transmission Interconnection Request in a sentence
A Generation Interconnection Request, a Transmission Interconnection Request and/or an IDR Transfer Agreement.
A Facilities Study related to a Transmission Interconnection Request.
NorthWestern Energy, as the designated operator, shall review the application for Transmission Interconnection Request for completeness.
A Transmission Interconnection Request will not be considered complete until all information in the application form is received and each Owner has received both a Transmission Interconnection Request that is considered to be a valid request and the required application deposit.
Transmission Interconnection Requests shall be studied in order based on the date, by which the last Owner has received a Transmission Interconnection Request that is considered to be a valid request, and the customer has consented to the sharing of information related to the request with the other Owners, to the extent such consent is necessary.
If the customer fails to cure all deficiencies within fifteen (15) business days after delivery of the notice of deficiency, the application for a Transmission Interconnection Request will be deemed by each Owner to be withdrawn.
If the New Service Upgrade Customer fails to provide Security in the amount, in the time or in the form required by Section 2.1, then this Upgrade CSA shall terminate immediately and the New Service Upgrade Customer’s Completed Application, Transmission Interconnection Request, or Upgrade Request, as applicable, shall be deemed terminated and withdrawn.
If the New Service Customer fails to provide Security in the amount, in the time or in the form required by Section 2.1, then this Upgrade CSA shall terminate immediately and the New Service Customer’s Completed Application, Transmission Interconnection Request, or Upgrade Request, as applicable, shall be deemed terminated and withdrawn.
If Project Developer fails to maintain its queue position(s) with such adjacent Control Area(s) throughout the entire PJM Transmission Interconnection Request process for the relevant PJM Transmission Interconnection Request, the relevant PJM Transmission Interconnection Request shall be deemed to be terminated and withdrawn.
For a Project Developer that has submitted a Transmission Interconnection Request, Project Developer shall provide evidence acceptable to the Transmission Provider that Project Developer has submitted and maintained a valid interconnection request with the adjacent Control Area(s) in which it is interconnecting.