CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue a Certificate for Payment to the State, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her reasons for withholding a Certificate as provided in Subparagraph 9.6.1
Appears in 187 contracts
Samples: Contract for Services, Contract for Services, Contract for Services
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding certification in whole or in part. The issuance of a Certificate as provided in Subparagraph 9.6.1of Payment will constitute a recommendation only by the Architect and not a legal, binding obligation on Owner.
Appears in 13 contracts
Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project
CERTIFICATES FOR PAYMENT. 9.4.1 15.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her and Owner of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 15.4.3.
Appears in 7 contracts
Samples: Standard Abbreviated Form of Agreement Between Owner and Contractor, Standard Abbreviated Form of Agreement Between Owner and Contractor, Standard Abbreviated Form of Agreement Between Owner and Contractor
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate as provided certification in Subparagraph 9.6.1whole or in part.
Appears in 3 contracts
Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
CERTIFICATES FOR PAYMENT. 9.4.1 4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Contractor, Roof Replacement Agreement
CERTIFICATES FOR PAYMENT. 9.4.1 15.2.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 15.2.3.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope, Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate as provided certification in Subparagraph 9.6.1whole or in part. men t in the manner payment from the nd contr
Appears in 1 contract
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.
Appears in 1 contract
Samples: Lease Agreement (Immunicon Corp)
CERTIFICATES FOR PAYMENT. 9.4.1 4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue a Certificate for Payment to the State, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her reasons for withholding a Certificate as provided in Subparagraph 9.6.1to
Appears in 1 contract
Samples: Construction Contract
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue Paym Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is Arc properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate as provided w in Subparagraph 9.6.1whole or in part. r of liens, claims,
Appears in 1 contract
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven (7) days after the receipt of the Contractor's completed Application for PaymentPayment and the Architect’s site visit, either either, issue to the Owner a Certificate for Payment to the State, with a copy to the Contractor, for such amount as the Architect determines is properly due, due or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.
9.4.2 The issuance of a Certificate for Payment will constitute a representation by the Architect
Appears in 1 contract
Samples: Architectural Services Agreement
CERTIFICATES FOR PAYMENT. 9.4.1 14.2.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 14.2.3.
Appears in 1 contract
CERTIFICATES FOR PAYMENT. 20 9.4.1 The Architect will, will within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines recommends is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.
Appears in 1 contract
Samples: General Conditions of the Contract for Construction
CERTIFICATES FOR PAYMENT. 9.4.1 4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.
Appears in 1 contract
Samples: Construction Contract
CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify notifY the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Contractor (STAMPS.COM Inc)