Change Orders and Cost Overruns Sample Clauses

Change Orders and Cost Overruns. Landlord’s approval is required in advance of all changes to, and deviations from, the Approved Construction Documents (each, a “Change Order”), including any (i) omission, removal, alteration or other modification of any portion of the Landlord Work, (ii) additional architectural or engineering services, (iii) changes to materials, whether building standard materials, specially ordered materials, or specially fabricated materials, or (iv) cancellation or modification of supply or fabrication orders. Except as otherwise expressly provided in this Work Letter, all costs of the Landlord Work in excess of the Construction Allowance including Change Orders requested by Tenant and approved by Landlord which increase the cost of the Landlord Work (collectively, “Cost Overruns”) shall be paid by Tenant to Landlord within 10 days of receipt of Landlord’s invoice. In addition, at Landlord’s election, Landlord may require Tenant to prepay any projected Cost Overruns within 10 days of receipt of Landlord’s invoice for same. Landlord may stop or decline to commence all or any portion of the Landlord Work until such payment (or prepayment) of Cost Overruns is received. On or before the Commencement Date, and as a condition to Tenant’s right to take possession of the Expansion Space, Tenant shall pay Landlord the entire amount of all Cost Overruns, less any prepaid amounts. Tenant’s failure to pay, when due, any Cost Overruns or the cost of any Change Order shall constitute an event of default under the Lease.
AutoNDA by SimpleDocs
Change Orders and Cost Overruns. All change orders must be approved (which approval shall not be unreasonably withheld or delayed) in advance in writing by Landlord. Change orders requested by Tenant and approved by Landlord which delay or increase the cost of the Work shall be paid by Tenant within 15 days of receipt of Landlord's invoice therefor (which payment may be required by Landlord prior to commencing construction). Except as otherwise expressly provided in this Construction Agreement, all costs of the Work in excess of the Construction Allowance (collectively, "COST OVERRUNS") shall be paid by Tenant to Landlord within 10 days of Landlord's invoice. Landlord may stop or decline to commence all or any portion of the Work until such payment is received. On or before the Expansion Space Commencement Date, and as a condition to Tenant's right to take possession of the Expansion Space, Tenant shall pay Landlord the entire amount of all Cost Overruns, less any prepaid amounts.
Change Orders and Cost Overruns. MCSD agrees to notify the City in the event there are additional costs or change orders associated with the construction/replacement/renovation projects. The City shall be given a reasonable opportunity to review these matters and participate in any decision making, with the final decision being made by MCSD. The City shall not be responsible for any cost of the change orders.
Change Orders and Cost Overruns. All change orders must be approved in advance in writing by Landlord. Change orders requested by Tenant and approved by Landlord which delay or increase the cost of the Work shall be paid by Tenant within 15 days of receipt of Landlord's invoice therefor (which payment may be required by Landlord prior to commencing construction). Except as otherwise expressly provided in this Construction Agreement, all costs of the Work in excess of the Construction Allowance (collectively, "Cost Overruns") shall be paid by Tenant to Landlord within 10 days of Landlord's invoice. In addition, at Landlord's election, Landlord may require Tenant to prepay any projected Cost Overruns within 5 days of Landlord's invoice. Landlord may stop or decline to commence all or any portion of the Work until such payment (or prepayment) is received. On or before the Commencement Date, and as a condition to Tenants right to take possession of the Premises, Tenant shall pay Landlord the entire amount of all Cost Overruns, less any prepaid amounts.

Related to Change Orders and Cost Overruns

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Cost Overruns The Borrower shall ensure that all cost-overruns over the estimated construction costs of the Project as certified by a quantity surveyor or the Architect or as ascertained by the Lender as and when they occur shall be funded by the Borrower’s own equity;

  • Change Order (5) The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Construction Contract; Cost Budget Prior to execution of a construction contract, Tenant shal] submit a copy of the proposed contract with the Contractor for the construction of the Tenant Improvements, including the genera] conditions with Contractor (the “Contract”) to Landlord for its approval, which approval shall not be unreasonably withheld, conditioned or delayed. Following execution of the Contract and prior to commencement of construction, Tenant shall provide Landlord with a fully executed copy of the Contract for Landlord’s records. Prior to the commencement of the construction of the Tenant Improvements, and after Tenant has accepted all bids and proposals for the Tenant Improvements, Tenant shall provide Landlord with a detailed breakdown, by trade, for all of Tenant’s Agents, of the final estimated costs to be incurred or which have been incurred in connection with the design and construction of the Tenant Improvements to be performed by or at the direction of Tenant or the Contractor (the “Construction Budget”), which costs shall include, but not be limited to, the costs of the Architect’s and Engineers’ fees and the Landlord Coordination Fee. The amount, if any, by which the total costs set forth in the Construction Budget exceed the amount of the Tenant Improvement Allowance is referred to herein as the “Over Allowance Amount”. In the event that an Over-Allowance Amount exists, then prior to the commencement of construction of the Tenant Improvements, Tenant shall supply Landlord with cash in an amount equal to the Over- Allowance Amount. The Over-Allowance Amount shall be disbursed by Landlord prior to the disbursement of any of the then remaining portion of the Tenant Improvement Allowance, and such disbursement shall be pursuant to the same procedure as the Tenant Improvement Allowance. In the event that, after the total costs set forth in the Construction Budget have been delivered by Tenant to Landlord, the costs relating to the design and construction of the Tenant Improvements shall change, any additional costs for such design and construction in excess of the total costs set forth in the Construction Budget shall be added to the Over-Allowance Amount and the total costs set forth in the Construction Budget, and such additional costs shall be paid by Tenant to Landlord immediately as an addition to the Over-Allowance Amount or at Landlord’s option, Tenant shall make payments for such additional costs out of its own funds, but Tenant shall continue to provide Landlord with the documents described in items (1), (ii), (iii) and (iv) of Section 2.2.2.1 of this Tenant Work Letter, above, for Landlord’s approval, prior to Tenant paying such costs. All Tenant Improvements paid for by the Over-Allowance Amount shall be deemed Landlord’s property under the terms of the Lease. 4.2.2

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Construction Budget The total amount indicated by the District for the Project plus all other costs, including design, construction, administration, financing, and all other costs.

  • Project Budget A Project Budget shall be prepared and maintained by Grantee. The Project Budget shall detail all costs for which the Grant will be used during each calendar month of the Term. The Project Budget must be approved in writing by the Project Monitor. Grantee shall carry out the Project and shall incur costs and make disbursements of funds provided hereunder by the Sponsor only in conformity with the Project Budget. The current approved Project Budget is contained in Attachment B. Said Project Budget may be revised from time to time, but no Project Budget or revision thereof shall be effective unless and until the same is approved in writing by Project Monitor. The funds granted under this Grant Contract cannot be used to supplant (replace) other existing funds.

  • Project Plan Development of Project Plan Upon the Authorized User’s request, the Contractor must develop a Project Plan. This Project Plan may include Implementation personnel, installation timeframes, escalation procedures and an acceptance plan as appropriate for the Services requested. Specific requirements of the plan will be defined in the RFQ. In response to the RFQ, the Contractor must agree to furnish all labor and supervision necessary to successfully perform Services procured from this Lot. Project Plan Document The Contractor will provide to the Authorized User, a Project Plan that may contain the following items: • Name of the Project Manager, Contact Phone Numbers and E-Mail Address; • Names of the Project Team Members, Contact Phone Numbers and E-Mail Address; • A list of Implementation milestones based on the Authorized User’s desired installation date; • A list of responsibilities of the Authorized User during system Implementation; • A list of designated Contractor Authorized Personnel; • Escalation procedures including management personnel contact numbers; • Full and complete documentation of all Implementation work; • Samples of knowledge transfer documentation; and • When applicable, a list of all materials and supplies required to complete the Implementation described in the RFQ. Materials and Supplies Required to Complete Implementation In the event that there are items required to complete an Implementation, the Contractor may request the items be added to its Contract if the items meet the scope of the Contract. Negotiation of Final Project Plan If the Authorized User chooses to require a full Project Plan, the State further reserves the right for Authorized Users to negotiate the final Project Plan with the apparent RFQ awardee. Such negotiation must not substantively change the scope of the RFQ plan, but can alter timeframes or other incidental factors of the final Project Plan. The Authorized User will provide the Contractor a minimum of five (5) business days’ notice of the final negotiation date. The Authorized User reserves the right to move to the next responsible and responsive bidder if Contractor negotiations are unsuccessful.

  • Development Budget Attached hereto as Exhibit "B" and incorporated herein by this reference is the Development Budget in an amount equal to $_____________. Owner acknowledges and represents that the attached Development Budget includes the total costs and expenses to acquire, develop, renovate and construct the Real Property and the Apartment Housing.

  • Tenant Improvement Costs The Tenant Improvements’ cost (the “Tenant Improvement Costs”) shall mean and include any and all costs and expenses of the Work, including, without limitation, all of the following: