Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Change Orders and Contract Amendments a) The Purchaser may at any time order the supplier/ selected bidder through Notice in accordance with clause “Notices” above, to make changes within the general scope of the Contract in any one or more of the following: -
i. drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Purchaser;
ii. the method of shipment or packing;
iii. the place of delivery; and
iv. the related services to be provided by the supplier/ selected bidder.
b) If any such change causes an increase or decrease in the cost of, or the time required for, the supplier’s/ selected bidder’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery and Completion Schedule, or both, and the Contract shall accordingly should be amended. Any claims by the supplier/ selected bidder for adjustment under this clause must be asserted within thirty (30) days from the date of the supplier’s/ selected bidder’s receipt of the Purchaser’s change order.
c) Prices to be charged by the supplier/ selected bidder for any related services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the supplier/ selected bidder for similar services.
Change Orders and Contract Amendments. The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
Change Orders and Contract Amendments a) The Purchaser may at any time order the supplier/ selected bidder through Notice in accordance with clause “Notices” above, to make changes within the general scope of the Contract in any one or more of the following: -
i. drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Purchaser;
ii. the method of shipment or packing;
iii. the place of delivery; and
iv. the related services to be provided by the supplier/ selected bidder.
b) If any such change causes an increase or decrease in the cost of, or the time required for, the supplier’s/ selected bidder’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery and Completion Schedule, or both, and the Contract shall accordingly should be amended. Any claims by the supplier/ selected bidder for adjustment under this clause must be asserted within thirty
Change Orders and Contract Amendments a) The Purchaser may at any time order the supplier/ selected bidder through Notice in accordance with clause “Notices” above, to make changes within the general scope of the Contract in any one or more of the following: -
i. the related services to be provided by the supplier/ selected bidder. RISL Rate Contract for Security Audit of Website(s) / Web Application(s) / portal(s)
b) If any such change causes an increase or decrease in the cost of, or the time required for, the supplier’s/ selected bidder’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery and Completion Schedule, or both, and the Contract shall accordingly should be amended. Any claims by the supplier/ selected bidder for adjustment under this clause must be asserted within thirty (30) days from the date of the supplier’s/ selected bidder’s receipt of the Purchaser’s change order.
c) Prices to be charged by the supplier/ selected bidder for any related services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the supplier/ selected bidder for similar services.
Change Orders and Contract Amendments. 2.10.1 No variation or modification in the terms of the contract shall be made except by written amendment signed by the parties.
2.10.2 Contracting Institute will reserve the right at the time of award of contract to increase or decrease the quantity of services specified in the Chapter 3 without any change in charges of the offered quantity or other terms and condition.
Change Orders and Contract Amendments. 14.1.1. APDCL may at any time direct the AMISP through a written notice to change the number of meters proposed to be installed (“Change Order”). No Change Order that has the effect of varying the number of meters to be installed beyond +/- 20% of the original number of meters shall be issued by the Utility without prior consent of AMISP. Provided however that upon expiry of time period specified in 3.3.2(o) of this AMISP Contract if the Utility has not been able to provide clearance/ approval/ permits for installation of the meters, the Utility shall issue a Change Order no later than 7 days of expiry of such time period confirming the actual number of meters for which clearance/ approval/ permits is available.
14.1.2. In the event a Change Order causes an increase or decrease in the time required for, the AMISP’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Project Implementation Schedule as provided in Schedule A of this AMISP Contract and the Contract shall accordingly be amended. Any claims by the AMISP or the Utility for adjustment under this Article must be asserted within 28 (twenty-eight) days from the date of the AMISP’s receipt of the Change Order. The Parties agree that any change in the delivery and Project Implementation Schedule shall result in an proportional change in the Term of the Contract.
14.1.3. In the event a Change Order, issued up to 24 months after the date of execution of this AMISP Contract, modifies the total number of Smart Meters to be installed then such revised quantity shall be deemed to be the basis for determination of Work Completion.
14.1.4. The Total meter-months of operating the AMI System after Operational Go-Live shall be computed taking into account all Change Orders issued by the Utility.
14.1.5. No Change Order for reduction of quantity shall be issued after Work Completion. In the event of loss of a consumer after Work Completion the Utility may request the AMISP to relocate a Smart Meter at a different location, however AMISP shall continue to receive the AMISP Service Charge qua all the Smart Meters installed.
Change Orders and Contract Amendments a) The Purchaser may at any time order the supplier/ selected bidder through Notice in accordance with clause “Notices” above, to make changes within the general scope of the Contract in any one or more of the following: -
i. drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Purchaser;
ii. the method of shipment or packing;
iii. the place of delivery; and
iv. the related services to be provided by the supplier/ selected bidder.
b) If any such change causes an increase or decrease in the cost of, or the time required for, the supplier’s/ selected bidder’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery and Completion Schedule, or both, and the Contract shall accordingly should be amended. Any claims by the supplier/ selected bidder for adjustment under this clause must be asserted within thirty (30) days from the date of the supplier’s/ selected bidder’s receipt of the Purchaser’s change order.
c) Prices to be charged by the supplier/ selected bidder for any related services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the supplier/ selected bidder for similar services. Rate Contract for Various Surveillance items to be deployed in the State of Rajasthan
Change Orders and Contract Amendments. 14.1.1. [Utility] may at any time direct the AMISP through a written notice to change the number of meters proposed to be installed (“Change Order”). No Change Order that has the effect of varying the number of meters to be installed beyond +/- 20% of the original number of meters shall be issued by the Utility without prior consent of AMISP. Provided however that upon expiry of time period specified in 3.3.2(o) of this AMISP Contract if the Utility has not been able to provide clearance/ approval/ permits for installation of the meters, the Utility shall issue a Change Order no later than 7 days of expiry of such time period confirming the actual number of meters for which clearance/ approval/ permits is available.
14.1.2. In the event a Change Order causes an increase or decrease in the time required for, the AMISP’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Project Implementation Schedule as provided in Schedule A of this AMISP Contract and the Contract shall accordingly be amended. Any claims by the AMISP or the Utility for adjustment under this Article must be asserted within 28 (twenty-eight) days from the date of the AMISP’s receipt of the Change Order. The Parties agree that any change in the delivery and Project Implementation Schedule shall result in an proportional change in the Term of the Contract.
Change Orders and Contract Amendments. The Purchaser may at any time order the selected bidder through Notice, to make changes within the general scope of the Contract and in the related services to be provided by the selected bidder.