Common use of Clustering Clause in Contracts

Clustering. At Transmission Provider's option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 14 contracts

Samples: Standard Large Generator Interconnection Procedures, Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

AutoNDA by SimpleDocs

Clustering. At Transmission Provider's the ISO’s option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Reliability Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider the ISO elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Servicetogether. The deadline Deadlines for completing all Interconnection System Reliability Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster WindowWindow shall be in accordance with Section 30.7.4. Transmission Provider The ISO may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Reliability Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the New York State Transmission System's System capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's the ISO’s OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 5 contracts

Samples: Service Agreement for Firm Point to Point Transmission Service, Transmission Wheeling Agreements, Service Agreement for Firm Point to Point Transmission Service

Clustering. At Transmission Provider's IPA’s option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider IPA elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Dayscalendar days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Servicetogether. The deadline for completing all Interconnection System Impact Studies for which an Interconnection a System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.47.3, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider IPA may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's IPA’s capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS IPA’s list maintained pursuant to Section 3.3 beginning at least one hundred and eighty (180) Calendar Days calendar days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 3 contracts

Samples: Generator Interconnection Procedures, Generator Interconnection Procedures, Generator Interconnection Procedures

Clustering. At Transmission Provider's option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.46.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement

Clustering. At Transmission Provider's IPA’s option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider IPA elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Dayscalendar days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Servicetogether. The deadline for completing all Interconnection System Impact Studies for which an Interconnection a System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.47.3, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider IPA may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's IPA’s capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS IPA’s list maintained pursuant to Section 3.3 beginning at least one hundred and eighty (180) Calendar Days calendar days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 2 contracts

Samples: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)

Clustering. At Transmission Provider's ’s option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's ’s capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's ’s OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 2 contracts

Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Clustering. At Transmission Provider's option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Clustering. At Transmission Provider's option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Positionusing Clustering. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" ", shall be studied together without regard to together. Transmission Provider, may at its option, establish Queue Cluster Windows for any one or more Operating Regions, in which case only those Generating Facilities with Points of Interconnection within such Operating Region(s) received within the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Windowstudied together using Clustering. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Transmission Provider may, at its option, limit the number of Interconnection Requests Interconnection Customers may submit during a Queue Cluster Window for the same Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's ’s capabilities at the time of each studytime. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified. Transmission Provider may allocate the costs of Interconnection Studies carried out pursuant to Clustering, and the costs of Network Upgrades and Interconnection Facilities identified as required by those Interconnection Studies, between or among the Interconnection Customers having filed the Interconnection Requests that are the subject of the Clustering pro rata, based on the maximum MW electrical output of the Generating Facility (if the Interconnection Request is for a new Generating Facility) or the increase in MW electrical output of the Generating Facility (if the Interconnection Request is for an increase in the generating capacity of an existing Generating Facility) from each Interconnection Request, notwithstanding their Queue Positions. Notwithstanding Section 11, within fifteen (15) Calendar Days of the date on which the Transmission Provider delivers the draft Interconnection Facilities Study report to Interconnection Customers whose Interconnection Requests have been studied pursuant to Clustering, each Interconnection Customer shall indicate on OASIS whether it is willing to pay and provide security for its applicable share of the good faith estimate of costs contained in the Facilities Study in accordance with Attachment O of the Tariff. Within thirty (30) Calendar Days after comments on the draft Interconnection Facilities Study report are submitted by the Interconnection Customers to the Transmission Provider, Transmission Provider shall tender a draft SGIA, together with draft appendices completed to the extent practicable, to each Interconnection Customer that has indicated that it is willing to pay and provide security for its applicable share of the costs. Each tendered SGIA shall be contingent on execution by each other Interconnection Customer receiving an SGIA. The remaining provisions of Section 11 with respect to the tender, negotiation and execution of SGIAs apply, except that if any one or more SGIAs so tendered is not executed by the applicable Interconnection Customer(s) and returned with evidence that milestones have been achieved pursuant to Section 11.3 by the deadline for execution of the SGIA by the Interconnection Customer, the Transmission Provider shall, within fifteen (15) Calendar Days thereafter, reissue SGIAs to those Interconnection Customers that executed the previous SGIA reapportioning the costs contained in the Interconnection Facilities Study among those remaining Interconnection Customers. Each of those remaining Interconnection Customers shall have fifteen (15) Calendar Days to execute its SGIA and return it with evidence that milestones have been achieved pursuant to Section 11.3. If any one or more of those SGIAs are not executed and returned as provided, then the Transmission Provider shall continue to reissue SGIAs as provided for above until all issued SGIAs are executed and returned as provided, or until the last SGIA tendered was tendered to a single Interconnection Customer.

Appears in 1 contract

Samples: Standard Generator Interconnection Agreement (Sgia)

AutoNDA by SimpleDocs

Clustering. At Transmission Provider's ’s option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 1 contract

Samples: Service Agreement for Firm Point to Point Transmission Service

Clustering. At Transmission Provider's option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether as Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (Lgia)

Clustering. At Transmission Provider's option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue PositionPositionPriority. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Procedures (Lgip)

Clustering. At Transmission Provider's ’s option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study. Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource ER Interconnection Service or Network Resource NR Interconnection Service. The deadline Deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility. Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study. The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on the Transmission Provider's OASIS beginning at least one hundred and eighty (180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)