Commissioning and Testing. Section 12.1Commissioning . Seller shall perform its commissioning activities in accordance with Exhibit I.
Commissioning and Testing. Only if the Contractor removes or replaces any plant components, will commissioning and testing will be required. The Contractor is responsible for the successful commissioning and testing of each section of plant worked on. The Contractor prepares and submits a detailed commissioning plan for each section of plant prior to the completion of that section of the work and submits it to the Employer for approval. Upon completion of refurbishment of a plant section and before de-isolation of the plant, the Contractor confirms that the plant is fit for use and verifies that all re-assembled and newly installed components are correctly installed, including the directions checks, directions of flows, alignments, bolt tightness/torqueing etc. and that they match the existing plant configurations with the necessary plant labels installed, The plant is also cleaned of waste, scrap and debris and equipment removed. Scaffolding which does not affect the operation of the plant may be left until the plant commissioning is completed. An erection check/plant walk is arranged between all the relevant parties and a snag list generated for immediate rectifications to be done by the Contractor. The Contractor requests the RP to provide a Sanction for Test (SFT) so that isolations may be removed. All commissioning activities may be performed under the SFT. The Contractor verifies the signals from all electrical and Control & Instrumentation (C&I) components to the control desk with the Employer’s C&I maintenance department. The Contractor conducts both cold and hot commissioning together with the Employer’s personnel. The Contractor ensures that proper housekeeping is done again before re-instating the plant by means of the RP clearing the PTW. The plant is considered “in operation” once the RP clears the PTW and the Contractor may not perform any more activities on that plant unless a new PTW is applied for and accepted.
Commissioning and Testing. The Company shall, at its own expense, carry out the testing and Commissioning of the Complex and the connecting transmission infrastructure in accordance with the following provisions of this Schedule 4, the codes and standards set out in Schedule 2, and Prudent Utility Practice. The Company may conduct any and all system testing prior to initial energization described herein below at the manufacturer’s facility prior to the arrival of the [GENERATOR/PLANT] at the site. JPS shall be given five (5) days prior written notice of any testing or Commissioning procedure and JPS shall be entitled to have representatives present for purposes of observing any such procedures. If JPS representatives are unable to attend for any reason, the testing may proceed without them.
Commissioning and Testing. Seller shall commission and test the Facility in accordance with the requirements set forth in Appendix IX.
Commissioning and Testing. The contractor shall include for fully commissioning of the generating set including all control equipment and for the purpose of the required tests and shall provide all necessary instrument, tools, fuel and lubricating oil.
Commissioning and Testing. 1 The Seller’s Obligations The Seller shall carry out commissioning in accordance with Prudent Operating Practice and any procedure agreed on by the Parties.
Commissioning and Testing. (a) Each Processor will co-operate in good faith with ASM in the testing and commissioning of the ASM Plant and ASM will co-operate in good faith with each Processor in the testing and commissioning of each Finishing Plant.
Commissioning and Testing. Contractor shall submit commissioning procedures for Owner review per Exhibit 2.5.5. Owner shall provide comments on these procedures within ten (10) days after receipt of such procedures. In the event Owner fails to timely provide comments to Contractor as provided by this Section 2.13, the commissioning procedures shall be deemed approved by Owner as of the date of delivery thereof by Contractor. Contractor shall, in good faith, include Owner’s timely reasonable comments into the final commissioning procedures. Contractor shall perform the commissioning and testing of the Infrastructure Facilities in accordance with the Commissioning, Test and Inspection Procedures.
Commissioning and Testing. Contractor shall provide CUC with advance notice of at least ten (10) Days before Plant Completion Testing and shall allow CUC to observe such testing. Contractor shall perform all tests as are reasonably required to ensure the adequate completion and commissioning of and the safe and orderly start-up of the Plant.
Commissioning and Testing. 16 7.01. RA Capacity Qualification Testing. 16