Commissioning. Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 13 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Interconnection Agreement
Commissioning. Commissioning tests of the Interconnection Customer’s 's installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least five ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 8 contracts
Samples: Generator Interconnection Agreement, Interconnection Procedures, Interconnection Procedures
Commissioning. Commissioning tests of the Interconnection CustomerMember’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner Cooperative must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 7 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Procedures
Commissioning. Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner Utility must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 5 contracts
Samples: Interconnection Procedures, Interconnection Procedures, Interconnection Procedures
Commissioning. 6.5.1 Commissioning tests of the Interconnection Customer’s 's installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least five ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 4 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Procedures, Generator Interconnection Procedures
Commissioning. Commissioning tests of the Interconnection Customer’s 's installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner Provider must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 3 contracts
Samples: Standard Small Generator Interconnection Agreement, Small Generator Interconnection Agreement, Standard Small Generator Interconnection Agreement (Sgia)
Commissioning. Commissioning tests of the Interconnection Customer’s 's installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner Provider must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 2 contracts
Samples: Standard Small Generator Interconnection Agreement (Sgia), Standard Small Generator Interconnection Agreement (Sgia)
Commissioning. Commissioning tests of the an Interconnection Customer’s installed equipment shall will be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner Interconnection Provider must be given at least five Business Days 5 business days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 2 contracts
Samples: Model Interconnection Procedures and Agreement for Small Distributed Generation Resources, Model Interconnection Procedures and Agreement for Small Distributed Generation Resources
Commissioning. Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner Provider must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 1 contract
Samples: Standard Small Generator Interconnection Agreement (Sgia)
Commissioning. Commissioning tests of the Interconnection Customer’s 's installed equipment shall will be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner If the Interconnection Customer is proceeding under Section 2.3.1, the Cooperative must be given at least five ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 1 contract
Samples: Interconnection Procedures
Commissioning. Commissioning tests of the Interconnection Customer’s 's installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner Provider must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 1 contract
Samples: Standard Small Generator Interconnection Agreement (Sgia)
Commissioning. Commissioning tests of the Interconnection Customer’s 's installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner If the Interconnection Customer is not proceeding under Section 2.3.2, the Authority must be given at least five ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Appears in 1 contract
Samples: Generator Interconnection Procedures