Concessioning Authority Event of Default Sample Clauses

Concessioning Authority Event of Default. Failure of Concessioning Authority to provide Right of Way to the Project Site within 6 0 (Sixty) days of execution of the Agreement for any reason other than Concessionaire Event of Default shall constitute an event of default by Concessioning Authority ("Concessioning Authority Event of Default”).
AutoNDA by SimpleDocs
Concessioning Authority Event of Default c. Compliance with the directions of any Government Agency, other than instructions issued as a consequence of a breach by the Concessionaire of any of its obligations hereunder; and
Concessioning Authority Event of Default. (a) Each of the following events or circumstances, to the extent not caused by a default of the Concessionaire or Force Majeure, shall be considered for the purposes of this Agreement as events of default of the Concessioning Authority (“the Concessioning Authority Event of Default”) which, if not cured within the time period permitted, if any, shall provide the Concessionaire with the right to terminate this Agreement in accordance with Article 17 hereof
Concessioning Authority Event of Default i. any defect in the CONCESSIONING AUTHORITY’s title, ownership and possession of the Project Site.
Concessioning Authority Event of Default. Each of the following events or circumstances, to the extent not caused by a default of the Concessionaire or Force Majeure, and if not cured within the Cure Period, which shall be 60 (sixty) days (unless provided otherwise in this Concession Agreement), from the date of notice of default (the “Default Notice”) from the Concessionaire, shall be considered for the purpose of this Agreement as events of default of the Concessioning Authority (“Concessioning Authority Event of Default”):
Concessioning Authority Event of Default. (i) The Concessioning Authority’s repudiation or failure to perform or discharge any of its obligations in accordance with the provisions of this Agreement that has a Material Adverse Effect unless such failure has occurred as a consequence of an Concessionaire Event of Default or a Force Majeure Event;
Concessioning Authority Event of Default. Each of the following events or circumstances, to the extent not caused by a default of the Concessionaire or Force Majeure, and if not cured within the Cure Period, which shall be 60 (sixty) days (unless provided otherwise in this Concession Agreement), from the date of notice of default (the “Default Notice”) from the Concessionaire, shall be considered for the purpose of this Agreement as events of default of the Concessioning Authority (“Concessioning Authority Event of Default”): Any defect in the title, ownership and possession of the Concessioning Authority with respect to the Project Site; GoMP or any Competent Authority have by an act of commission or omission created circumstance that has a Material Adverse Effect on the Concessionaire, and the Concessioning Authority has failed to compensate the Concessionaire for the same through an adjustment to the Concession Period. The Concessioning Authority is in breach of its obligations under this Concession Agreement, which has a Material Adverse Effect upon the Concessionaire or the Project and this breach is not cured within a cure period of 90 days from the date of Default Notice. The Concessioning Authority is in breach of any representation or warranty made under this Agreement, or it repudiates this Concession Agreement.
AutoNDA by SimpleDocs

Related to Concessioning Authority Event of Default

  • Authority Event of Default Any of the following events shall constitute an event of default by the Authority ("Authority Event of Default”), when not caused by a Developer Event of Default:

  • Developer Event of Default Any of the following events shall constitute an event of default by the Developer ("Developer Event of Default") unless such event has occurred as a result of a Force Majeure Event or the Authority Event of Default or any governmental action for reasons other than any breach, default or lapse on the part of the Developer:

  • Train Operator Events of Default The following are Train Operator Events of Default:

  • Notice of Event of Default If the Mortgagee shall have Actual Knowledge of an Event of Default or of a Default arising from a failure to pay Rent, the Mortgagee shall give prompt written notice thereof to the Owner Trustee, the Owner Participant, Lessee, and each Note Holder. Subject to the terms of Sections 2.13, 4.03, 4.04, 4.08, 5.02 and 5.03 hereof, the Mortgagee shall take such action, or refrain from taking such action, with respect to such Event of Default or Default (including with respect to the exercise of any rights or remedies hereunder) as the Mortgagee shall be instructed in writing by a Majority in Interest of Note Holders. Subject to the provisions of Section 5.03, if the Mortgagee shall not have received instructions as above provided within 20 days after mailing notice of such Event of Default to the Note Holders, the Mortgagee may, subject to instructions thereafter received pursuant to the preceding provisions of this Section 5.01, take such action, or refrain from taking such action, but shall be under no duty to take or refrain from taking any action, with respect to such Event of Default or Default as it shall determine advisable in the best interests of the Note Holders; PROVIDED, HOWEVER, that the Mortgagee may not sell the Aircraft or any Engine without the consent of a Majority in Interest of Note Holders. For all purposes of this Trust Indenture, in the absence of Actual Knowledge on the part of the Mortgagee, the Owner Trustee or the Owner Participant, the Mortgagee, the Owner Trustee or the Owner Participant, as the case may be, shall not be deemed to have knowledge of a Default or an Event of Default (except, in the case of the Mortgagee, the failure of Lessee to pay any installment of Basic Rent within one Business Day after the same shall become due, if any portion of such installment was then required to be paid to the Mortgagee, which failure shall constitute knowledge of a Default) unless notified in writing by Lessee, the Owner Trustee, the Owner Participant or one or more Note Holders.

  • No Default for Force Majeure Neither Party will be in default in the performance of any of its obligations set forth in this Agreement, except for obligations to pay money, when and to the extent failure of performance is caused by Force Majeure.

  • Notice to Proceed - Site Improvements The Recipient shall not commence, or cause to be commenced, any site improvements or other work on the Land until the Director has issued a Notice to Proceed to the Recipient. Such Notice to Proceed will not be issued until the Director is assured that the Recipient has complied with all requirements for the approval of a grant under Revised Code Sections 164.20 through 164.27 and has completed any land acquisition required by the Project. A Notice to Proceed shall be required for all Project prime contractors or direct procurement initiated by the Recipient following execution of this Agreement.

  • Regulatory Event New Taxes If, after the Effective Date, a Regulatory Event occurs or New Taxes are imposed, and such event or taxes have a direct, material and adverse effect on the economic benefits to a Party of this ESA, the affected Party shall send written notice to the other Party, setting forth the Regulatory Event or New Taxes and reasonably demonstrating the effect of the same on the affected Party. Upon delivery of such notice, the Parties shall use reasonable efforts to negotiate an amendment to this ESA to mitigate such effect. Alternatively, if as a direct result of such a Regulatory Event or New Taxes, the Competitive Supplier incurs additional, material costs, the Competitive Supplier shall provide a written notice to the Town that documents: a) the effective date of the Regulatory Event or New Taxes; b) a detailed explanation and reasonable demonstration of the material costs incurred as a result of the Regulatory Event or New Taxes; c) the timing of the cost impact to be incurred by the Competitive Supplier; d) the proposed price increase per kWh to be passed on to Participating Consumers; and e) a proposed plan for coordinating with the Local Distributor for an increase in the price per kWh that is billed by the Local Distributor, designed to reimburse the Competitive Supplier for such cost impact. If the Town and the Competitive supplier cannot agree on the amendment to this ESA or reimbursement contemplated by this section, the matter may be subject to dispute resolution in accordance with section 12.2. In no event shall a price change become effective without providing Participating Consumers with a 30-day advance notice of the price change.

  • Consequences of Events of Default and Corrective Action If an Event of Default occurs, the Province may, at any time, take one or more of the following actions:

  • No Event of Default No Default or Event of Default has occurred and is continuing.

  • Event of Default Any of the following shall constitute an “Event of Default”: