Continuity of Construction Sample Clauses

Continuity of Construction. Construction, once undertaken, shall proceed in a continuous and reasonably expeditious manner until Physical Completion is achieved.
AutoNDA by SimpleDocs
Continuity of Construction. Borrower shall prosecute with diligence and continuity the construction of the work and improvements and will not suspend or cease construction for a period longer than thirty (30) days. Borrower’s obligation under this provision shall be subject to exception due to events of Force Majeure Delay. "Force Majeure Delay" shall mean a delay in progress of construction due to weather, act of God, unavailability or shortage of labor or materials, national emergency, fire or other casualty, natural disaster, war, delays or actions of governmental authorities or utilities, riots, acts of violence, labor strike, injunctions in connection with litigation, or other cause which is not within the reasonable control of Borrower. Force Majeure Delay does not include the failure to order and obtain materials in a timely fashion for the continuous development of the Development and does not include financial difficulties of the Borrower.
Continuity of Construction. Construction, once undertaken, shall proceed in a continuous and reasonably expeditious manner until Physical Completion, as such term is defined in Section 2.10, is achieved, which shall not occur later than 18 months after the completion of the foundation for the Project. Any delay caused by acts of God, fire, accident, casualty, cessation of activity due to refusal to work by labor, or any other caused not attributable to the failure of Developer to use reasonable care and due diligence, however, shall be excused by Owner, provided that Developer shall use its best efforts to minimize any such delays and shall resume construction at the earliest possible time.
Continuity of Construction. Construction, once undertaken, shall proceed in a continuous and reasonably expeditious manner until Physical Completion (as such term is defined in Section 2.10) is achieved, which shall not occur later than sixteen (16) months after the date the Project Loan Documents are executed and delivered.
Continuity of Construction. (a) Works on the Allotment, once commenced, shall not be left incomplete or without substantial work being carried out for a period longer than one (1) month.
Continuity of Construction. Construction, once undertaken, shall proceed in a continuous and expeditious manner until Physical Completion, as such term is defined in Section 2.9, is achieved. Physical Completion shall take place no later than fourteen (14) months from the Start Date (the "Completion Date"). Any delays caused by acts of God, fire, accident, casualty, labor strikes or job actions, or any other cause not attributable to the failure of the Contractor to use reasonable care and due diligence ("Force Majeure"), however, shall be excused by the Owner, provided that Contractor shall use its best efforts to minimize any such delays and shall resume construction at the earliest possible time. Notwithstanding the foregoing, in the event of any delay caused by a Force Majeure which extends the date of Physical Completion beyond the Completion Date, the Contractor shall be obligated to pay to the Lender any additional interest, attorneys, inspection and consulting fees and all other expenses under the Lender Loan payable as a direct and proximate result of any such delay (the "Lender Direct Costs") beyond the Completion Date which shall be the Owner's sole and exclusive remedy as a result of such delay. In the event that any delay as a result of a Force Majeure extends the date of Physical Completion beyond the Completion Date by a period of twelve (12 months or more, the Owner shall within three (3) days after receipt of notice from the Contractor, deliver to the Contractor a completed and signed application to transfer the ownership of the DON to the Contractor or its designee. In such event, the Owner agrees to use its reasonable best efforts to obtain DPH approval for such transfer which shall include, without limitation, timely and accurate responses to questions or requests for information from DPH whether such questions or requests shall be written or oral, the timely completion and submission of any applications requested by DPH and attendance at any hearings held by DPH at which the Owner's attendance is requested, mandated or otherwise necessary. Upon the approval by DPH of a transfer of the DON back to the Contractor or its designee, the Owner shall within thirty (30) days of the date of Owner's receipt of the Contractor's notice thereof, reconvey all right, title and interest in and to the Premises and the Facility and all rights related thereto and the Contractor shall assume all of the obligations of the Owner under the Lender Loan, subject to the consent of Lender,...
Continuity of Construction. Construction, once undertaken, shall proceed in a continuous and reasonably expeditious manner until Physical Completion, as such term is defined in Section 2.9, is achieved, which shall not occur later that eighteen (18) months after the commencement of the construction for the Facility. For purposes hereof the phrase "Commencement of Construction" shall be defined as the later of the date of the issuance of a building permit for the Facility or the date of the purchase of the Premises by the Purchaser. To the extent that such date is beyond the time period required by the DON, the Purchaser shall use its reasonable best efforts to obtain an extension of same, and Seller shall assist it in such efforts. Any delays caused by acts of God, or fire, accident, casualty, cessation of activity due to refusal to work by labor, but only, in the case of the foregoing, if not principally attributable to the Seller's negligence or willful misconduct, or any other cause not attributable to the failure of the Seller to use reasonable care and due diligence, however, shall be excused by the Purchaser, provided that Seller shall use its reasonable best efforts to minimize any such delays and shall resume construction at the earliest possible time. In the event that the Seller does not Physically Complete the Facility within eighteen (18) months from the Commencement of Construction and such delay is not attributable to a force majeure as set forth above, the Seller shall pay to the Purchaser liquidated damages of $3200 per day for each day of such delay.
AutoNDA by SimpleDocs
Continuity of Construction. All structures commenced in the Park shall be prosecuted diligently to completion and shall be completed within twelve (12) months of commencement unless exception is granted in writing by FIPCO.
Continuity of Construction. ​ The construction of every dwelling on a Lot shall be completed within 12 months after the commencement of such construction. No improvement that has been partially or totally destroyed by fire or other casualty shall be allowed to remain in such condition for more than three months from the time of such destruction or damage.

Related to Continuity of Construction

  • Commencement of Construction Construction of the Project will start within thirty (30) days after notification to the Developer by the Owner, or as soon thereafter as weather and ground conditions permit.

  • ICIF Construction The ICIF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Parties agree on another mutually acceptable deadline, Interconnection Customer shall deliver to Transmission Provider and Transmission Owner “as-built” drawings, information and documents for the ICIF, such as: a one-line diagram, a site plan showing the Generating Facility and the ICIF, plan and elevation drawings showing the layout of the ICIF, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Interconnection Customer’s step-up transformers, the facilities connecting the Generating Facility to the step-up transformers and the ICIF, and the impedances (determined by factory tests) for the associated step-up transformers and the Generating Facility. Interconnection Customer shall provide Transmission Provider and Transmission Owner with Interconnection Customer’s specifications for the excitation system, automatic voltage regulator, Generating Facility control and protection settings, transformer tap settings, and communications, if applicable.

  • Completion of Construction Within 60 days of the completion of construction of the Project, Project Owner shall deliver to DoD copies of the FAA form 7460-2 for each ASN, including the final coordinates for each turbine erected.

  • DAF Construction The DAF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Developer and Connecting Transmission Owner agree on another mutually acceptable deadline, the Developer shall deliver to the Connecting Transmission Owner and NYISO “as- built” drawings, information and documents for the DAF, such as: a one-line diagram, a site plan showing the Large Generating Facility and the DAF, plan and elevation drawings showing the layout of the DAF, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Developer’s step-up transformers, the facilities connecting the Large Generating Facility to the step-up transformers and the DAF, and the impedances (determined by factory tests) for the associated step-up transformers and the Large Generating Facility. The Developer shall provide to, and coordinate with, Connecting Transmission Owner and NYISO with respect to proposed specifications for the excitation system, automatic voltage regulator, Large Generating Facility control and protection settings, transformer tap settings, and communications, if applicable.

  • Commencement and Completion of Construction Subject to Unavoidable Delays, Developer shall cause construction of the Minimum Improvements to be undertaken and completed: (i) by no later than June 1, 2020; or (ii) by such other date as the parties shall mutually agree upon in writing. Time lost as a result of Unavoidable Delays shall be added to extend this date by a number of days equal to the number of days lost as a result of Unavoidable Delays. All work with respect to the Minimum Improvements shall be in conformity with the Construction Plans approved by the building official or any amendments thereto as may be approved by the building official. Developer agrees that it shall permit designated representatives of the City, upon reasonable notice (which does not have to be written), to enter upon the Development Property during the construction of the Minimum Improvements to inspect such construction and the progress thereof.

  • Law; Construction This Agreement and any claim, counterclaim or dispute of any kind or nature whatsoever arising out of or in any way relating to this Agreement (“Claim”), directly or indirectly, shall be governed by, and construed in accordance with, the internal laws of the State of New York.

  • Principles of Construction All references to sections and schedules are to sections and schedules in or to this Agreement unless otherwise specified. All uses of the word “including” shall mean “including, without limitation” unless the context shall indicate otherwise. Unless otherwise specified, the words “hereof,” “herein” and “hereunder” and words of similar import when used in this Agreement shall refer to this Agreement as a whole and not to any particular provision of this Agreement. Unless otherwise specified, all meanings attributed to defined terms herein shall be equally applicable to both the singular and plural forms of the terms so defined.

  • Certain Matters of Construction The terms “herein,” “hereof,” “hereunder” and other words of similar import refer to this Agreement as a whole and not to any particular section, paragraph or subdivision. Any pronoun used shall be deemed to cover all genders. In the computation of periods of time from a specified date to a later specified date, “from” means “from and including,” and “to” and “until” each mean “to but excluding.” The terms “including” and “include” shall mean “including, without limitation” and, for purposes of each Loan Document, the parties agree that the rule of ejusdem generis shall not be applicable to limit any provision. Section titles appear as a matter of convenience only and shall not affect the interpretation of any Loan Document. All references to (a) laws or statutes include all related rules, regulations, interpretations, amendments and successor provisions; (b) any document, instrument or agreement include any amendments, waivers and other modifications, extensions or renewals (to the extent permitted by the Loan Documents); (c) any section mean, unless the context otherwise requires, a section of this Agreement; (d) any exhibits or schedules mean, unless the context otherwise requires, exhibits and schedules attached hereto, which are hereby incorporated by reference; (e) any Person include successors and assigns; (f) time of day mean time of day at Lenders’ notice addresses under Section 13.3.1; or (g) discretion of any Lender mean the sole and absolute discretion of such Person. All calculations of fundings of the Loans, and payments of Obligations shall be in Dollars and, unless the context otherwise requires, all determinations made from time to time under the Loan Documents shall be made in light of the circumstances existing at such time. Borrowers shall have the burden of establishing any alleged negligence, misconduct or lack of good faith by any Lender under any Loan Documents. No provision of any Loan Documents shall be construed against any party by reason of such party having, or being deemed to have, drafted the provision.

  • Strict Construction The parties to this Agreement have participated jointly in the negotiation and drafting of this Agreement. In the event an ambiguity or question of intent or interpretation arises, this Agreement will be construed as if drafted jointly by the parties, and no presumption or burden of proof will arise favoring or disfavoring any party by virtue of the authorship of any of the provisions of this Agreement.

  • General Construction 20.2.1. Binding Nature.............................................. 20.2.2. Entire Agreement............................................ 20.2.3. Governing Law............................................... 20.2.4. Indulgences Not Waivers..................................... 20.2.5. Titles Not to Affect Interpretation......................... 20.2.6.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!