CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
Appears in 3 contracts
Samples: campussuite-storage.s3.amazonaws.com, Item Description Unit Unit Cost Subtotal, app.lincoln.ne.gov
CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Contractor's Construction Schedule Updating: At monthly weekly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
Appears in 1 contract
Samples: www.nassaucountyny.gov
CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Contractor's Construction Schedule Updating: At monthly bi-weekly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
Appears in 1 contract
Samples: www.bidnet.com
CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Contractor's Construction Schedule Updating: At monthly weekly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week two (2) days before each regularly scheduled progress meeting.
Appears in 1 contract
Samples: Construction Contract
CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Contractor's Construction Schedule Updating: At monthly two week intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before at each regularly scheduled progress meeting.
Appears in 1 contract
Samples: gssdocs.deldot.delaware.gov