CM Review of Time Extension Requests Sample Clauses

CM Review of Time Extension Requests. The CM shall, prior to the issuance of a change order, determine the effect on the CONSTRUCTION AND Master Schedules of time extensions requested by the Contractor.
AutoNDA by SimpleDocs

Related to CM Review of Time Extension Requests

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv); (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13); (c) occurrence of a Force Majeure Event; (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and (e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement. (ii) The Contractor shall, no later than 15 (fifteen) business days from the occurrence of an event or circumstance specified in Clause 10.5 (i), inform the Authority’s Engineer by notice in writing, with a copy to the Authority, stating in reasonable detail with supporting particulars, the event or circumstances giving rise to the claim for Time Extension in accordance with the provisions of this Agreement. Provided that the period of 15 (fifteen) business days shall be calculated from the date on which the Contractor became aware, or should have become aware, of the occurrence of such an event or circumstance. Provided further that notwithstanding anything to the contrary contained in this Agreement, Time Extension shall be due and applicable only for the Works which are affected by the aforesaid events or circumstances and shall not in any manner affect the Project Completion Schedule for and in respect of the Works which are not affected hereunder. (iii) On the failure of the Contractor to issue to the Authority’s Engineer a notice in accordance with the provisions of Clause 10.5 (ii) within the time specified therein, the Contractor shall not be entitled to any Time Extension and shall forfeit its right for any such claims in future. For the avoidance of doubt, in the event of failure of the Contractor to issue notice as specified in this clause 10.5 (iii), the Authority shall be discharged from all liability in connection with the claim. (iv) The Authority’s Engineer shall, on receipt of the claim in accordance with the provisions of Clause 10.5 (ii), examine the claim expeditiously within the time frame specified herein. In the event the Authority’s Engineer requires any clarifications to examine the claim, the Authority’s Engineer shall seek the same within 15 (fifteen) days from the date of receiving the claim. The Contractor shall, on receipt of the communication of the Authority’s Engineer requesting for clarification, furnish the same to the Authority’s Engineer within 10 (ten) days thereof. The Authority’s Engineer shall, within a period of 30 (thirty) days from the date of receipt of such clarifications, forward in writing to the Contractor its determination of Time Extension. Provided that when determining each extension of time under this Clause 10.5, the Authority’s Engineer shall review previous determinations and may increase, but shall not decrease, the total Time Extension. (v) If the event or circumstance giving rise to the notice has a continuing effect: (a) a fully detailed claim shall be considered as interim; (b) the Contractor shall, no later than 10 (ten) days after the close of each month, send further interim claims specifying the accumulated delay, the extension of time claimed, and such further particulars as the Authority’s Engineer may reasonably require; and (c) the Contractor shall send a final claim within 30 (thirty) days after the effect of the event or the circumstance ceases. Upon receipt of the claim hereunder, the Authority’s Engineer shall examine the same in accordance with the provisions of Clause 10.5 (iv) within a period of 30 (thirty) days of the receipt thereof

  • Extension of Time Periods The parties may extend any period of time provided in this Article 7 by mutual agreement.

  • Extension Request The Borrower shall provide the applicable Extension Request at least three (3) Business Days prior to the date on which Lenders under the Existing Term Loan Tranche or Existing Revolver Tranche, as applicable, are requested to respond, and shall agree to such procedures, if any, as may be established by, or acceptable to, the Administrative Agent, in each case acting reasonably to accomplish the purposes of this Section 2.16. No Lender shall have any obligation to agree to have any of its Term Loans of any Existing Term Loan Tranche amended into Extended Term Loans or any of its Revolving Credit Commitments amended into Extended Revolving Credit Commitments, as applicable, pursuant to any Extension Request. Any Lender holding a Loan under an Existing Term Loan Tranche (each, an “Extending Term Lender”) wishing to have all or a portion of its Term Loans under the Existing Term Loan Tranche subject to such Extension Request amended into Extended Term Loans and any Revolving Credit Lender (each, an “Extending Revolving Credit Lender”) wishing to have all or a portion of its Revolving Credit Commitments under the Existing Revolver Tranche subject to such Extension Request amended into Extended Revolving Credit Commitments, as applicable, shall notify the Administrative Agent (each, an “Extension Election”) on or prior to the date specified in such Extension Request of the amount of its Term Loans under the Existing Term Loan Tranche or Revolving Credit Commitments under the Existing Revolver Tranche, as applicable, which it has elected to request be amended into Extended Term Loans or Extended Revolving Credit Commitments, as applicable (subject to any minimum denomination requirements imposed by the Administrative Agent). In the event that the aggregate principal amount of Term Loans under the Existing Term Loan Tranche or Revolving Credit Commitments under the Existing Revolver Tranche, as applicable, in respect of which applicable Term Lenders or Revolving Credit Lenders, as the case may be, shall have accepted the relevant Extension Request exceeds the amount of Extended Term Loans or Extended Revolving Credit Commitments, as applicable, requested to be extended pursuant to the Extension Request, Term Loans or Revolving Credit Commitments, as applicable, subject to Extension Elections shall be amended to Extended Term Loans or Revolving Credit Commitments, as applicable, on a pro rata basis (subject to rounding by the Administrative Agent, which shall be conclusive) based on the aggregate principal amount of Term Loans or Revolving Credit Commitments, as applicable, included in each such Extension Election.

  • Extension of Time Limits The time limits referred to in this Article may be extended by mutual agreement of the parties in writing.

  • Time Extension CONTRACTOR shall provide a time extension request on completion of Task Order for delays caused by others (Permitting Agencies, COUNTY or Contract Cities, or unforeseen conditions such as inclement weather, etc.) and at no fault by CONTRACTOR, subject to approval by COUNTY. COUNTY will review the request and determine in its sole discretion whether the situation warrant a time extension at no-cost or with costs. If CONTRACTOR completes the Task Order beyond the stipulated completion date without COUNTY’s specific written approval for time extension, CONTRACTOR will be subject to liquidated damages and may be construed as non-responsive, which may affect CONTRACTOR for considerations for future Task Orders or projects.

  • Time Extensions 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

  • Contract Extension The City may, in its sole discretion, unilaterally exercise an option to extend the Contract as described in the Contract Documents. In addition, the City may, in its sole discretion, unilaterally extend the Contract on a month-to-month basis following contract expiration if authorized under Charter section 99 and the Contract Documents. Contractor shall not increase its pricing in excess of the percentage increase described in the Contract.

  • Notice of Extension (a) If the Property Trustee is the only registered holder of the Debentures at the time the Company selects an Extended Interest Payment Period, the Company shall give written notice to the Administrative Trustees, the Property Trustee and the Trustee of its selection of such Extended Interest Payment Period two Business Days before the earlier of (i) the next succeeding date on which Distributions on the Trust Securities issued by the Trust are payable; or (ii) the date the Trust is required to give notice of the record date, or the date such Distributions are payable, to The Nasdaq National Market or other applicable self-regulatory organization or to holders of the Preferred Securities issued by the Trust, but in any event at least one Business Day before such record date. (b) If the Property Trustee is not the only holder of the Debentures at the time the Company selects an Extended Interest Payment Period, the Company shall give the holders of the Debentures and the Trustee written notice of its selection of such Extended Interest Payment Period at least two Business Days before the earlier of (i) the next succeeding Interest Payment Date; or (ii) the date the Company is required to give notice of the record or payment date of such interest payment to The Nasdaq National Market or other applicable self-regulatory organization or to holders of the Debentures. (c) The quarter in which any notice is given pursuant to paragraphs (a) or (b) of this Section 4.2 shall be counted as one of the 20 quarters permitted in the maximum Extended Interest Payment Period permitted under Section 4.1.

  • Listing Period Extension The Commission shall be due if the Property is sold, conveyed, exchanged, optioned, or otherwise transferred within _ _ days (“Extension Period”) after the expiration of the Listing Period to anyone with whom the Broker or Agency has negotiated unless the Property is listed, in good faith, with another real estate agency. The term “negotiation” shall include providing information about the Property, showing the Property, or presenting an offer on the Property. All rights under this Section shall terminate upon the expiration of the Extension Period.

  • Term of Contract; Contract Extension The Contract will be in effect from the Effective Date (15 December 2016) through 31 December 2018. DAS, in its sole discretion, may extend this Contract for additional terms beyond the original term, prior to Termination or expiration, one or more times for a combined total period not to exceed the complete length of the original term.