Critical Path Activities Sample Clauses

Critical Path Activities. To the extent the Construction Manager completes activities on the Critical Path earlier than scheduled, the savings in time on account thereof shall belong solely to the Construction Manager.
AutoNDA by SimpleDocs
Critical Path Activities. To the extent the Job Order Contractor completes activities on the Critical Path earlier than scheduled, the savings in time on account thereof shall belong solely to the Job Order Contractor.
Critical Path Activities. Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Critical path cycle activities include, but are not limited to, submittals, acceptance, purchasing, fabrication, and delivery.
Critical Path Activities. To the extent the Contractor completes activities on the Critical Path earlier than scheduled, the savings in time on account thereof shall belong solely to the Contractor.
Critical Path Activities. To the extent the Design-Builder completes activities on the critical path earlier than scheduled, the savings in time on account thereof shall belong solely to the Project.

Related to Critical Path Activities

  • Specific Activities Please give detailed information about the specific activities of the Project promoter and the Partner(s), with budget allocations 7.1 The main tasks of [name of the Project Promoter], referred to as the ‘Project Promoter’, are summarized as follows: Name Project activities Project budget 1 .... [mention the budget allocated to Project Promoter for the respective activity] EUR.... Activity 2 .... EUR... 7.2 The main input/responsibilities of [name of the Project Partner(s)], referred to as Partner 1, 2, etc., are summarized as follows: Name Project activities Project budget Partner 1... [briefly present the project activity implemented by Partner]. Activity 1 .... [mention the budget allocated to Partner 1 for the respective activity] EUR.... Activity 2 .... EUR... Name Project activities Project budget

  • Extracurricular Activities Effective July 1, 2009, stipends for participation in extracurricular activities which are authorized by the appointing authority shall be: Inland $950/year Sailing $400/year Art Club Advisor $300/year Drama Club Advisor $300/year Cross Country Skiing $150/year Boys’ Basketball $1000/year Girls’ Basketball (if class D) $1000/year Asst. Boys’ Basketball $750/year Asst. Girls’ Basketball (if class D) $750/year Scorekeeper/Timekeeper $10/game Soccer $400/year Track $400/year Cross County Running $400/year Girls’ Basketball (if not class D) $400/year Sports Activity Director $400/year Athletic Director $200/year

  • EXTRA-CURRICULAR ACTIVITIES 1. In this Agreement, extra-curricular programs and activities include all those that are beyond the provincially prescribed and locally determined curricula of the school district. 2. The Board and the Association consider it desirable that teachers participate in extra-curricular activities, and recognize that participation in extra-curricular activities by the individual teacher is on a voluntary basis.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!