DAMAGES AND DELAYS Sample Clauses

DAMAGES AND DELAYS. The CONSULTANT agrees that no charges or claim for damages shall be made by them for any delays or hindrances from any cause whatsoever during the progress of any portion of the services specified in this AGREEMENT. Such delays or hindrances, if any, shall be compensated for by an extension of time for such reasonable period as the STATE may decide, it being understood however, that the permitting of the CONSULTANT to proceed to complete any services or any part of them after the date of completion or after the date to which the time of completion may have been extended, shall in no way operate as a waiver on the part of the STATE of any of its rights herein. Nothing in this ARTICLE will prevent the CONSULTANT from exercising its rights under ARTICLE 9 of this AGREEMENT.
AutoNDA by SimpleDocs
DAMAGES AND DELAYS. The Consultant agrees that no charges or claim for damages shall be made by the Consultant for any delays or hindrances from any cause whatsoever during the progress of any portion of the work required by this Agreement. Such delays or hindrances, if any, shall be compensated for by an amendment to the Project Schedule and, as applicable, the Budget, subject to the procedures otherwise applicable herein for changes to the Project Schedule and Budget.
DAMAGES AND DELAYS. The CONSULTANT agrees that no charges or claim for damages shall be made by him for any delays or hindrances from any cause whatsoever during the progress of any portion of the services specified in this Contract. Such delays or hindrances, if any, shall be compensated for by an extension of time for such reasonable period as the Sponsor may decide, it being understood however, that the permitting of the CONSULTANT to proceed to complete any services or any part of them after the date of completion or after the date to which the time of completion may have been extended, shall in no way operate as a waiver on the part of the Sponsor of any of its rights herein. Nothing in this ARTICLE will prevent the CONSULTANT from exercising his rights under ARTICLE 7 of this contract.
DAMAGES AND DELAYS. Xxxxxxxx-Xxxxxxxx will not be responsible for damage done to Contractor’s work by others. Any repairing of the same by Xxxxxxxx-Xxxxxxxx will be charged at regular scheduled rates over and above the amount of this proposal. Xxxxxxxx- Xxxxxxxx shall not be responsible for loss, damage or delay caused by circumstances beyond its reasonable control, including buy not limited to acts of God, weather, accidents, fire, vandalism, strikes, jurisdictional disputes, failure or delay of transportation, shortage of or inability to obtain materials, equipment or labor; changes in the work and delays caused by others. In the event of these occurrences, Contractor’s time for performance under this proposal shall be extended for a time sufficient of permit completion of the Work.
DAMAGES AND DELAYS. The CONSULTANT agrees that no
DAMAGES AND DELAYS. Performer agrees that no charges or claim for damages shall be made by Performer against AFMSP and MAC, members of its Board, and its officers, agents, employees, volunteers and commissioners for any damages or hindrances from any cause whatsoever other than contribution or indemnity claims for bodily injury during any performance under this Agreement. Delays or hindrances, if any, shall be compensated for by an extension of time for such reasonable period as the AFMSP may determine to be equitable in the circumstances, and the opportunity for renegotiation of compensation.
DAMAGES AND DELAYS. The CONSULTANT agrees that no charges or claim for damages shall be made by him for any delays or hindrances from any cause whatsoever during the progress of any portion of the services specified in this Contract. Such delays or hindrances, if any, shall be compensated for by an extension of time for such reasonable period as the Sponsor may decide, it being understood however, that the permitting of the CONSULTANT to proceed to complete any services or any part of them after the date of completion or after the date to which the time of completion may have been extended, shall in no way operate as a waiver on the part of the Sponsor of any of its rights herein. Nothing in this ARTICLE will prevent the CONSULTANT from exercising his rights under ARTICLE 7 of this contract. Notwithstanding any other provisions of this Contract, CONSULTANT shall not be relieved of liability for damages sustained by Sponsor by virtue of CONSULTANT’s breach of this Contract and Sponsor may withhold or offset payments to CONSULTANT until such time as the actual extent of damages due Sponsor from CONSULTANT is determined.
AutoNDA by SimpleDocs
DAMAGES AND DELAYS. The CONSULTANT agrees that no charges or claim for damages shall be made by him for any delays or hindrances from any cause whatsoever during the progress of any portion of the services specified in this Agreement. Such delays or hindrances, if any, shall be compensated for by an extension of time for such reasonable period as the Municipality may decide, it being understood however, that the permitting of the CONSULTANT to proceed to complete any services or any part of them after the date of completion or after the date to which the time of completion may have been extended, shall in no way operate as a waiver on the part of the Municipality of any of its rights herein. Nothing in this ARTICLE will prevent the CONSULTANT from exercising his rights under ARTICLE 7 of this agreement.
DAMAGES AND DELAYS. FRR will not be responsible for damage done to FRR’s work by others, including damage to temporary tie-ins. Any repairing of the same by FRR will be charged as an extra. FRR shall not be liable for liquidated or delay damages due to a delay in completion of the Project unless the delay was caused by FRR. FRR shall not be responsible for loss, damage or delay caused by circumstances beyond its reasonable control, including but not limited to acts of God, accidents, snow, fire, weather, vandalism, regulation, strikes, jurisdictional disputes, failure or delay of transportation, shortage of or inability to obtain materials, equipment or labor. In the event of these occurrences, FRR’s time for performance under this proposal shall be extended for a time sufficient to permit completion of the Work.

Related to DAMAGES AND DELAYS

  • Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Damages; Relief Termination of this Agreement shall not preclude either Party from claiming any other damages, compensation or relief that it may be entitled to upon such termination.

  • Force Majeure, Notice of Delay, and No Damages for Delay The Contractor will not be responsible for delay resulting from its failure to perform if neither the fault nor the negligence of the Contractor or its employees or agents contributed to the delay and the delay is due directly to acts of God, wars, acts of public enemies, strikes, fires, floods, or other similar cause wholly beyond the Contractor’s control, or for any of the foregoing that affect subcontractors or suppliers if no alternate source of supply is available to the Contractor. In case of any delay the Contractor believes is excusable, the Contractor will notify the Department or Customer in writing of the delay or potential delay and describe the cause of the delay either (1) within 10 days after the cause that creates or will create the delay first arose, if the Contractor could reasonably foresee that a delay could occur as a result, or (2) if delay is not reasonably foreseeable, within five days after the date the Contractor first had reason to believe that a delay could result. The foregoing will constitute the Contractor’s sole remedy or excuse with respect to delay. Providing notice in strict accordance with this paragraph is a condition precedent to such remedy. No claim for damages will be asserted by the Contractor. The Contractor will not be entitled to an increase in the Contract price or payment of any kind from the Department or Customer for direct, indirect, consequential, impact or other costs, expenses or damages, including but not limited to costs of acceleration or inefficiency, arising because of delay, disruption, interference, or hindrance from any cause whatsoever. If performance is suspended or delayed, in whole or in part, due to any of the causes described in this paragraph, after the causes have ceased to exist the Contractor will perform at no increased cost, unless the Department or Customer determines, in its sole discretion, that the delay will significantly impair the value of the Contract to the State of Florida or to Customers, in which case the Department or Customer may (1) accept allocated performance or deliveries from the Contractor, provided that the Contractor grants preferential treatment to Customers with respect to commodities or contractual services subjected to allocation, or (2) purchase from other sources (without recourse to and by the Contractor for the related costs and expenses) to replace all or part of the commodity or contractual services that are the subject of the delay, which purchases may be deducted from the Contract quantity, or (3) terminate the Contract in whole or in part.

  • Liquidated Damages for Delay In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.

  • Delay Damages If the Commercial Operation Date is not achieved by the date set forth therefor in Section 3.1(a) (as extended pursuant to Section 3.1(c)), Seller shall pay to Buyer damages for each month from and after such date until the Commercial Operation Date at the rate of $1.50 per kwh of Contract Maximum Amount up to a maximum of twelve (12) months of delay, pro rated for partial months (“Delay Damages”). Delay Damages shall be due under this Section 3.2(a) without regard to whether Buyer exercises its right to terminate this Agreement pursuant to Section 9.3; provided, however, that if Buyer exercises its right to terminate this Agreement under Section 9.3, Delay Damages shall be due and owing to the extent that such Delay Damages were due and owing at the date of such termination. If the Facility has not achieved the Commercial Operation by the date set forth therefor in Section 3.1(a) (as the same may be extended in accordance with Section 3.1(c)), for any reason, Seller shall have the right to terminate this Agreement at any time after that deadline date (as so extended) until either the Facility achieves the Commercial Operation Date or Buyer terminates this Agreement under Section 9.3 (regardless of whether or not Seller elected to continue to construct the Project). In the event Seller so terminates this Agreement, Seller shall be liable to Buyer on the date of such termination for (x) the entire amount of Delay Damages that would otherwise accrue (or have accrued) by such date plus (y) the undrawn amount of any Development Period Security provided to Buyer by Seller; provided, however, that if Seller terminates this Agreement on the deadline set forth for the Commercial Operation Date in Section 3.1(a) (as the same may be extended in accordance with Section 3.1(c)), Seller shall not be required to pay any Delay Damages hereunder but shall forfeit the Development Period Security. Subject to the foregoing sentence, neither Party shall have any liability to the other Party with respect to a termination of this Agreement by Seller under this Section 3.2(b). Each Party agrees and acknowledges that (i) the damages that Buyer would incur due to Seller’s delay in achieving the Commercial Operation Date would be difficult or impossible to predict with certainty, and (ii) it is impractical and difficult to assess actual damages in the circumstances stated, and therefore the Delay Damages and other damages as agreed to by the Parties and set forth herein are a fair and reasonable calculation of such damages. Notwithstanding the foregoing, this Article shall not limit the amount of damages payable to Buyer if this Agreement is terminated by Buyer as a result of Seller’s failure to achieve the Commercial Operation Date. Any such termination damages shall be determined in accordance with Article 9. By the tenth (10th) day following the end of the calendar month in which Delay Damages first become due and continuing by the tenth (10th) day of each calendar month during the period in which Delay Damages accrue (and the following months if applicable), Buyer shall deliver to Seller an invoice showing Buyer’s computation of such damages and any amount due Buyer in respect thereof for the preceding calendar month. No later than ten (10) days after receiving such an invoice, Seller shall pay to Buyer, by wire transfer of immediately available funds to an account specified in writing by Buyer or by any other means agreed to by the Parties in writing from time to time, the amount set forth as due in such invoice. If Seller fails to pay such amounts when due, Buyer may draw upon the Development Period Security for payment of such Delay Damages, and Buyer may exercise any other remedies available for Seller’s default hereunder.

  • Consequential Damages Waiver NEITHER PARTY SHALL HAVE ANY LIABILITY ARISING OUT OF OR RELATED TO THIS AGREEMENT FOR ANY LOSS OF USE, LOST DATA, LOST PROFITS, FAILURE OF SECURITY MECHANISMS, INTERRUPTION OF BUSINESS, LOSS CAUSED BY THE INTERRUPTION, TERMINATION OR DELAYED OPERATION OF THE INTERNET, THIRD-PARTY TELECOMMUNICATION SERVICES OR THIRD-PARTY SECURITY FEATURES OR SYSTEMS, EXCEPT AS REQUIRED BY LAW. EXCEPT FOR CUSTOMER’S BREACH OF SECTION 1.4 (USE RESTRICTIONS) OR EITHER PARTY’S UNLAWFUL OR WILLFUL MISCONDUCT OR GROSS NEGLIGENCE, NEITHER PARTY SHALL BE LIABLE FOR ANY INDIRECT, SPECIAL, INCIDENTAL, EXEMPLARY, PUNITIVE, RELIANCE, OR CONSEQUENTIAL DAMAGES OF ANY KIND, EVEN IF INFORMED OF THE POSSIBILITY IN ADVANCE, SUFFERED BY ANY PARTY OR ANY PARTY CLAIMING ON BEHALF OF OR THROUGH THE OTHER PARTY, OR ANY OTHER THIRD PARTY RESULTING FROM OR ARISING OUT OF OR RELATED TO THIS AGREEMENT OR THE PERFORMANCE OR BREACH THEREOF.

  • Indemnity Consequential Damages and Insurance 18.1 Indemnity 18.1.1 Indemnified Party 18.1.2 Indemnifying Party 18.1.3 Indemnity Procedures 18.2 Consequential Damages 18.3 Insurance 18.3.1 18.3.2 18.3.3 18.3.4 18.3.5 18.3.6 18.3.7 18.3.8 18.3.9 18.3.10 18.3.11

  • Outages and Interruptions Outages.

  • Waiver of Consequential Damages, Etc To the fullest extent permitted by applicable law, the Borrower shall not assert, and hereby waives, any claim against any Indemnitee, on any theory of liability, for special, indirect, consequential or punitive damages (as opposed to direct or actual damages) arising out of, in connection with, or as a result of, this Agreement, any other Loan Document or any agreement or instrument contemplated hereby, the transactions contemplated hereby or thereby, any Loan or Letter of Credit or the use of the proceeds thereof. No Indemnitee referred to in subsection (b) above shall be liable for any damages arising from the use by unintended recipients of any information or other materials distributed to such unintended recipients by such Indemnitee through telecommunications, electronic or other information transmission systems in connection with this Agreement or the other Loan Documents or the transactions contemplated hereby or thereby other than for direct or actual damages resulting from the gross negligence or willful misconduct of such Indemnitee as determined by a final and nonappealable judgment of a court of competent jurisdiction.