Connecting Transmission Owner’s Attachment Facilities Construction The Connecting Transmission Owner’s Attachment Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Connecting Transmission Owner and Developer agree on another mutually acceptable deadline, the Connecting Transmission Owner shall deliver to the Developer “as-built” drawings, relay diagrams, information and documents for the Connecting Transmission Owner’s Attachment Facilities set forth in Appendix A. The Connecting Transmission Owner [shall/shall not] transfer operational control of the Connecting Transmission Owner’s Attachment Facilities and Stand Alone System Upgrade Facilities to the NYISO upon completion of such facilities.
Connecting Transmission Owner’s Attachment Facilities Connecting Transmission Owner shall design, procure, construct, install, own and/or control the Connecting Transmission Owner’s Attachment Facilities described in Appendix A hereto, at the sole expense of the Developer.
DISCONNECTION OF SUPPLY 14.1 When can we arrange for disconnection? (a) you do not pay your bill by the pay-by date and, if you are a residential customer, you: (i) fail to comply with the terms of an agreed payment plan; or (ii) do not agree to an offer to pay the bill by instalments, or having agreed, you fail to comply with the instalment arrangement; (b) you do not provide a security deposit we are entitled to require from you; or (c) you do not give access to your premises to read a meter (where relevant) for 3 consecutive meter reads; or (d) you fail to give us safe and unhindered access to the premises as required by clause 11 or any requirements under the energy laws; or (e) there has been illegal or fraudulent use of energy at your premises in breach of clause 16 of this contract; or (f) we are otherwise entitled or required to do so under the Rules or by law.
Transfer or Deletion of Student Data The Provider shall review, on an annual basis, whether the Student Data it has received pursuant to the DPA continues to be needed for the purpose(s) of the Service Agreement and this DPA. If any of the Student Data is no longer needed for purposes of the Service Agreement and this DPA, the Provider will provide written notice to the LEA as to what Student Data is no longer needed. The Provider will delete or transfer Student Data in readable form to the LEA, as directed by the LEA (which may be effectuated through Exhibit D of the DPA), within 30 calendar days if the LEA requests deletion or transfer of the Student Data and shall provide written confirmation to the LEA of such deletion or transfer. Upon termination of the Service Agreement between the Provider and LEA, Provider shall conduct a final review of Student Data within 60 calendar days. If the LEA receives a request from a parent, as that term is defined in 105 ILCS 10/2(g), that Student Data being held by the Provider be deleted, the LEA shall determine whether the requested deletion would violate State and/or federal records laws. In the event such deletion would not violate State or federal records laws, the LEA shall forward the request for deletion to the Provider. The Provider shall comply with the request and delete the Student Data within a reasonable time period after receiving the request. Any provision of Student Data to the LEA from the Provider shall be transmitted in a format readable by the LEA.
System Upgrade Facilities and System Deliverability Upgrades Connecting Transmission Owner shall design, procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Appendix A hereto. The responsibility of the Developer for costs related to System Upgrade Facilities and System Deliverability Upgrades shall be determined in accordance with the provisions of Attachment S to the NYISO OATT.
Participating TO’s Interconnection Facilities The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendix A at the sole expense of the Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Interconnection Customer.
Interconnection Facilities Engineering Procurement and Construction Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO and the CAISO from the Interconnection Customer associated with interconnecting the Large Generating Facility.
Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.
Early Construction of Base Case Facilities Developer may request Connecting Transmission Owner to construct, and Connecting Transmission Owner shall construct, subject to a binding cost allocation agreement reached in accordance with Attachment S to the ISO OATT, including Section 25.8.7 thereof, using Reasonable Efforts to accommodate Developer’s In-Service Date, all or any portion of any System Upgrade Facilities or System Deliverability Upgrades required for Developer to be interconnected to the New York State Transmission System which are included in the Base Case of the Class Year Study for the Developer, and which also are required to be constructed for another Developer, but where such construction is not scheduled to be completed in time to achieve Developer’s In-Service Date.
Access Toll Connecting Trunk Group Architecture 9.2.1 If CSTC chooses to subtend a Verizon access Tandem, CSTC’s NPA/NXX must be assigned by CSTC to subtend the same Verizon access Tandem that a Verizon NPA/NXX serving the same Rate Center Area subtends as identified in the LERG. 9.2.2 CSTC shall establish Access Toll Connecting Trunks pursuant to applicable access Tariffs by which it will provide Switched Exchange Access Services to Interexchange Carriers to enable such Interexchange Carriers to originate and terminate traffic to and from CSTC’s Customers. 9.2.3 The Access Toll Connecting Trunks shall be two-way trunks. Such trunks shall connect the End Office CSTC utilizes to provide Telephone Exchange Service and Switched Exchange Access to its Customers in a given LATA to the access Tandem(s) Verizon utilizes to provide Exchange Access in such LATA. 9.2.4 Access Toll Connecting Trunks shall be used solely for the transmission and routing of Exchange Access to allow CSTC’s Customers to connect to or be connected to the interexchange trunks of any Interexchange Carrier which is connected to a Verizon access Tandem.