ACCEPTANCE AND REJECTION a. Buyer shall accept the Services or give Seller notice of rejection within a reasonable time after the date of delivery. No payment, prior test, inspection, passage of title, any failure or delay in performing any of the foregoing, or failure to discover any defect or other nonconformance shall relieve Seller of any obligations under this Contract or impair any rights or remedies of Buyer.
INSPECTION, ACCEPTANCE AND REJECTION a. All Goods will be subject to Mercy Corps' inspection and testing (which may be done by a third party authorized by Mercy Corps), at any time and place, including the period of manufacture/production/creation and before final acceptance. If Mercy Corps inspects or tests at Supplier's premises, Supplier, without additional charge, will provide all reasonable facilities and assistance for the safety and convenience of Mercy Corps' inspectors. No inspection or testing done or not done before final inspection and acceptance will relieve Supplier from responsibility for defects or for other failure to meet the requirements of this Agreement. Notwithstanding any prior inspections or payments made, all Goods will be subject to final inspection and acceptance at the Delivery Location within a reasonable time after delivery (but in no event, less than three days after the date of delivery).
Inspection and Rejection of Nonconforming Goods (a) Buyer shall inspect the goods within five days of receipt (“Inspection Period”). Xxxxx will be deemed to have accepted the goods unless it notifies Seller in writing of any Nonconforming Goods during the Inspection Period and furnishes documentation reasonably required by Seller. “
Rejection of Deliverables The Department reserves the right to reject deliverables, as outlined in the Grant Work Plan, as incomplete, inadequate, or unacceptable due, in whole or in part, to Xxxxxxx’s lack of satisfactory performance under the terms of this Agreement. The Grantee’s efforts to correct the rejected deliverables will be at Xxxxxxx’s sole expense. Failure to fulfill the applicable technical requirements or complete all tasks or activities in accordance with the Grant Work Plan will result in rejection of the deliverable and the associated invoice. Payment for the rejected deliverable will not be issued unless the rejected deliverable is made acceptable to Department in accordance with the Agreement requirements. The Department, at its option, may allow additional time within which Grantee may remedy the objections noted by Department. The Grantee’s failure to make adequate or acceptable deliverables after a reasonable opportunity to do so shall constitute an event of default.
361 Acceptance of Specified Roads Specified Road work may be accepted subject to completion of clearing work that does not affect the road structure when completion is delayed for reasons beyond control of Purchaser, such as adverse weather. Specified Road work may be accepted subject to completion of planting and seeding for soil stabilization when completion is delayed for reasons beyond control of Purchaser, such as seasonal limitations. Purchaser shall complete planting or seeding on such road during the next suitable planting season. Specified Road work may be conditionally accepted prior to the application of dust palliatives when application is not necessary to prevent dusting of the road surface due to climatic conditions. Purchaser shall apply dust palliative on such roads prior to use during periods when dusting may occur. Prior to request for final inspection, Specified Road work, roadways, borrow pits, and quarries, occupied and no longer needed by Purchaser in connection with Purchaser’s Operations, shall be cleared of all rubbish, excess materials, and temporary structures.
Acceptance of Deliverables The State’s Project Manager shall be responsible for the sign-off acceptance of all Deliverables required and performed/submitted pursuant to this Agreement. Upon successful completion of a Deliverable, Contractor shall provide the State’s Project Manager with a completed Acceptance and Signoff Form (Exhibit E). The State’s Project Manager will apply the standards established in Exhibit D and the acceptance criteria set forth in subparagraph B of this article, as appropriate, to determine the acceptability of the Deliverable provided by Contractor. If the State’s Project Manager rejects the Deliverable, the parties agree to any dispute(s) resulting from such rejection(s) will be resolved as set forth in this article. Acceptance Criteria for Deliverables (“Criteria”) provided by Contractor pursuant to this Agreement include: Timeliness: The Work was provided on time; according to schedule; Completeness: The Deliverable contained all of the, Data, Materials, and features required by the Agreement; and Technical accuracy: The Deliverable complied with the standards of this Agreement, or, if this Agreement lacks a standard for provision of the Work, the currently generally accepted industry standard. Contractor shall provide the Deliverable to the State, in accordance with direction from the Project Manager and as provided for in Exhibit D. The State shall accept the Deliverable, provided that Contractor has delivered the Deliverable in accordance with the Criteria. The State’s Project Manager shall assign the Acceptance and Signoff Form to notify Contractor of the Deliverable’s acceptability. If the State rejects the Deliverable provided, the State’s Project Manager shall submit to Contractor’s Project Manager a written rejection describing in detail the failure of the Deliverable as measured against the Criteria. If the State rejects the Deliverable, then Contractor shall have a period of ten (10) Business Days from receipt of the Notice of rejection to correct the stated failure(s) to conform to the Criteria.
ACCEPTANCE STANDARDS Inspection and acceptance/rejection of products shall be made within thirty (30) days of receipt or upon completion of installation should that installation period extend beyond thirty
ACCEPTANCE TESTS 11.1 If the Contract provides acceptance tests for Goods and/or the result of Services after their completion and/or delivery to the Purchaser, the acceptance shall only be considered as definitive when such tests have demonstrated the compliance of the Goods and/or the result of the Services to the requirements in the Contract.
Acceptance of the Terms of Use These terms of use are entered into by and between You and InterPayments Inc ("Company," "we," or "us"). The following terms and conditions, together with any documents they expressly incorporate by reference (collectively, "Terms of Use"), govern your access to and use of xxx.xxxxxxxxxxxxx.xxx, including any content, functionality, and services offered on or through xxx.xxxxxxxxxxxxx.xxx (the "Website"), whether as a guest or a registered user. Please read the Terms of Use carefully before you start to use the Website. By using the Website or by clicking to accept or agree to the Terms of Use when this option is made available to you, you accept and agree to be bound and abide by these Terms of Use and our Privacy Policy, found at Privacy Policy, incorporated herein by reference. If you do not want to agree to these Terms of Use or the Privacy Policy, you must not access or use the Website. This Website is offered and available to users who are 18 years of age or older. By using this Website, you represent and warrant that you are of legal age to form a binding contract with the Company and meet all of the foregoing eligibility requirements. If you do not meet all of these requirements, you must not access or use the Website.
Rejection of Work Using the Notice of Non-Conforming Work procedures outlined in the General Conditions, the Design Professional shall reject work that does not comply with the requirements of the Contract Documents or that does not comply with the applicable laws and codes. The Design Professional shall have authority to order testing of the Work, as is provided in the Contract Documents or as otherwise required in its judgment, whether such work is fabricated, installed, or completed.