Common use of Document Review Clause in Contracts

Document Review. (a) Project Co acknowledges having conducted a thorough review of the Contract Documents and has reported to the Consultant and Owner any Design Issue found by Project Co in the Contract Documents during its review. If Project Co does discover any Design Issue in the Contract Documents, Project Co shall not proceed with the Work affected until Project Co has first complied with the provisions of Section 11.18. Project Co acknowledges that it is responsible for the risks assumed by Project Co in Sections 11.17 and 11.18 and that any additional costs resulting from such risks will form part of the Project Co Design Contingency. It is intended that the review of the Contract Documents conducted by Project Co pursuant to this Section 5.2(a) be carried out by Project Co and the Project Co Parties using their own experiences and expertise in accordance with the standard of care set out in Section 11.2(a)(viii) and in accordance with the representations and warranties of Project Co set out in Section 7.1. (b) Except as may constitute a Design Issue properly characterized as a Project Co Design Issue under Section 11.17, and except in respect of those Contract Documents which, under the terms of this Project Agreement, Project Co is required to prepare or produce, Project Co shall not be responsible for verifying that the Contract Documents are in compliance with Applicable Law. (c) If the Contract Documents are at variance with Applicable Law, or if, subsequent to the Submission Date, changes are made to Applicable Law which require modification to the Contract Documents, Project Co shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming known. The Consultant will make the changes required to the Contract Documents as provided in Article 21 below and Schedule 11 – Change Procedure. (d) If Project Co fails to notify the Consultant in writing, fails to obtain direction as required in Section 5.2(c), and performs Work knowing it to be contrary to any Applicable Law, Project Co shall be responsible for and shall correct the violations thereof, and shall bear the costs, expenses and damages attributable to its failure to comply with the provisions of such Applicable Law.

Appears in 4 contracts

Samples: Project Agreement, Project Agreement, Project Agreement

AutoNDA by SimpleDocs

Document Review. (a) Project Co acknowledges having conducted a thorough review of the Contract Documents and has reported to the Consultant and Owner any Design Issue found by Project Co in the Contract Documents during its review. If Project Co does discover any Design Issue in the Contract Documents, Project Co shall not proceed with the Work affected until Project Co has first complied with the provisions of Section 11.18. Project Co acknowledges that it is responsible for the risks assumed by Project Co in Sections 11.17 and 11.18 and that any additional costs resulting from such risks will form part of the Project Co Design Contingency. It is intended that the review of the Contract Documents conducted by Project Co pursuant to this Section 5.2(a) be carried out by Project Co and the Project Co Parties using their own experiences and expertise in accordance with the standard of care set out in Section 11.2(a)(viii) and in accordance with the representations and warranties of Project Co set out in Section 7.1. (b) Except as may constitute a Design Issue properly characterized as a Project Co Design Issue under Section 11.17, and except in respect of those Contract Documents which, under the terms of this Project Agreement, Project Co is required to prepare or produce, Project Co shall not be responsible for verifying that the Contract Documents are in compliance with Applicable Law. (c) If the Contract Documents are at variance with Applicable Law, or if, subsequent to the Submission Date, changes are made to Applicable Law which require modification to the Contract Documents, Project Co shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming known. The Consultant will make the changes required to the Contract Documents as provided in Article 21 below and Schedule 11 - Change Procedure. (d) If Project Co fails to notify the Consultant in writing, fails to obtain direction as required in Section 5.2(c), and performs Work knowing it to be contrary to any Applicable Law, Project Co shall be responsible for and shall correct the violations thereof, and shall bear the costs, expenses and damages attributable to its failure to comply with the provisions of such Applicable Law.

Appears in 3 contracts

Samples: Project Agreement, Project Agreement, Project Agreement

Document Review. (a) Project Co acknowledges having conducted a thorough review of the Contract Documents and has reported to the Consultant and Owner THP any Design Issue found by Project Co in the Contract Documents during its review. If Project Co does discover any Design Issue in the Contract Documents, Project Co shall not proceed with the Work affected until Project Co has first complied with the provisions of Section 11.18. Project Co acknowledges that it is responsible for the risks assumed by Project Co in Sections 11.17 and 11.18 and that any additional costs resulting from such risks will form part of the Project Co Design Contingency. It is intended that the review of the Contract Documents conducted by Project Co pursuant to this Section 5.2(a) be carried out by Project Co and the Project Co Parties using their own experiences and expertise in accordance with the standard of care set out in Section 11.2(a)(viii) and in accordance with the representations and warranties of Project Co set out in Section 7.1.7.1.‌ (b) Except as may constitute a Design Issue properly characterized as a Project Co Design Issue under Section 11.17, and except in respect of those Contract Documents which, under the terms of this Project Agreement, Project Co is required to prepare or produce, Project Co shall not be responsible for verifying that the Contract Documents are in compliance with Applicable Law. (c) If the Contract Documents are at variance with Applicable Law, or if, subsequent to the Submission Date, changes are made to Applicable Law which require modification to the Contract Documents, Project Co shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming known. The Consultant will make the changes required to the Contract Documents as provided in Article 21 below and Schedule 11 – Change Procedure.Procedure.‌ (d) If Project Co fails to notify the Consultant in writing, fails to obtain direction as required in Section 5.2(c), and performs Work knowing it to be contrary to any Applicable Law, Project Co shall be responsible for and shall correct the violations thereof, and shall bear the costs, expenses and damages attributable to its failure to comply with the provisions of such Applicable Law.

Appears in 1 contract

Samples: Project Agreement

Document Review. (a) Project Co acknowledges having conducted a thorough review of the Contract Documents and has reported to the Consultant and Owner CMH any Design Issue found by Project Co in the Contract Documents during its review. If Project Co does discover any Design Issue in the Contract Documents, Project Co shall not proceed with the Work affected until Project Co has first complied with the provisions of Section 11.18. Project Co acknowledges that it is responsible for the risks assumed by Project Co in Sections 11.17 and 11.18 and that any additional costs resulting from such risks will form part of the Project Co Design Contingency. It is intended that the review of the Contract Documents conducted by Project Co pursuant to this Section 5.2(a) be carried out by Project Co and the Project Co Parties using their own experiences and expertise in accordance with the standard of care set out in Section 11.2(a)(viii) and in accordance with the representations and warranties of Project Co set out in Section 7.1. (b) Except as may constitute a Design Issue properly characterized as a Project Co Design Issue under Section 11.17, and except in respect of those Contract Documents which, under the terms of this Project Agreement, Project Co is required to prepare or produce, Project Co shall not be responsible for verifying that the Contract Documents are in compliance with Applicable Law. (c) If the Contract Documents are at variance with Applicable Law, or if, subsequent to the Submission Date, changes are made to Applicable Law which require modification to the Contract Documents, Project Co shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming known. The Consultant will make the changes required to the Contract Documents as provided in Article 21 below and Schedule 11 – Change Procedure. (d) If Project Co fails to notify the Consultant in writing, fails to obtain direction as required in Section 5.2(c), and performs Work knowing it to be contrary to any Applicable Law, Project Co shall be responsible for and shall correct the violations thereof, and shall bear the costs, expenses and damages attributable to its failure to comply with the provisions of such Applicable Law.

Appears in 1 contract

Samples: Project Agreement

Document Review. (a) Project Co acknowledges having conducted a thorough review of the Contract Documents and has reported to the Consultant and Owner any Design Issue found by Project Co in the Contract Documents during its review. If Project Co does discover any Design Issue in the Contract Documents, Project Co shall not proceed with the Work affected until Project Co has first complied with the provisions of Section 11.18. Project Co acknowledges that it is responsible for the risks assumed by Project Co in Sections 11.17 and 11.18 and that any additional costs resulting from such risks will form part of the Project Co Design Contingency. It is intended that the review of the Contract Documents conducted by Project Co pursuant to this Section 5.2(a) be carried out by Project Co and the Project Co Parties using their own experiences and expertise in accordance with the standard of care set out in Section 11.2(a)(viii) and in accordance with the representations and warranties of Project Co set out in Section 7.1.for (b) Except as may constitute a Design Issue properly characterized as a Project Co Design Issue under Section 11.17, and except in respect of those Contract Documents which, under the terms of this Project Agreement, Project Co is required to prepare or produce, Project Co shall not be responsible for verifying that the Contract Documents are in compliance with Applicable Law. (c) If the Contract Documents are at variance with Applicable Law, or if, subsequent to the Submission Date, changes are made to Applicable Law which require modification to the Contract Documents, Project Co shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming known. The Consultant will make the changes required to the Contract Documents as provided in Article 21 below and Schedule 11 – Change Procedure. (d) If Project Co fails to notify the Consultant in writing, fails to obtain direction as required in Section 5.2(c), and performs Work knowing it to be contrary to any Applicable Law, Project Co shall be responsible for and shall correct the violations thereof, and shall bear the costs, expenses and damages attributable to its failure to comply with the provisions of such Applicable Law.

Appears in 1 contract

Samples: Project Agreement

AutoNDA by SimpleDocs

Document Review. (a) Project Co acknowledges having conducted a thorough review of the Contract Documents and has reported to the Consultant and Owner HMQ any Design Issue found by Project Co in the Contract Documents during its review. If Project Co does discover any Design Issue in the Contract Documents, Project Co shall not proceed with the Work affected until Project Co has first complied with the provisions of Section 11.18. Project Co acknowledges that it is responsible for the risks assumed by Project Co in Sections 11.17 and 11.18 and that any additional costs resulting from such risks will form part of the Project Co Design Contingency. It is intended that the review of the Contract Documents conducted by Project Co pursuant to this Section 5.2(a) be carried out by Project Co and the Project Co Parties using their own experiences and expertise in accordance with the standard of care set out in Section 11.2(a)(viii) and in accordance with the representations and warranties of Project Co set out in Section 7.1. (b) Except as may constitute a Design Issue properly characterized as a Project Co Design Issue under Section 11.17, and except in respect of those Contract Documents which, under the terms of this Project Agreement, Project Co is required to prepare or produce, Project Co shall not be responsible for verifying that the Contract Documents are in compliance with Applicable Law. (c) If the Contract Documents are at variance with Applicable Law, or if, subsequent to the Submission Date, changes are made to Applicable Law which require modification to the Contract Documents, Project Co shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming known. The Consultant will make the changes required to the Contract Documents as provided in Article 21 below and Schedule 11 – Change Procedure. (d) If Project Co fails to notify the Consultant in writing, fails to obtain direction as required in Section 5.2(c), and performs Work knowing it to be contrary to any Applicable Law, Project Co shall be responsible for and shall correct the violations thereof, and shall bear the costs, expenses and damages attributable to its failure to comply with the provisions of such Applicable Law.

Appears in 1 contract

Samples: Project Agreement

Document Review. (a) Project Co acknowledges having conducted a thorough review of the Contract Documents and has reported to the Consultant and Owner CHH any Design Issue found by Project Co in the Contract Documents during its review. If Project Co does discover any Design Issue in the Contract Documents, Project Co shall not proceed with the Work affected until Project Co has first complied with the provisions of Section 11.18. Project Co acknowledges that it is responsible for the risks assumed by Project Co in Sections 11.17 and 11.18 and that any additional costs resulting from such risks will form part of the Project Co Design Contingency. It is intended that the review of the Contract Documents conducted by Project Co pursuant to this Section 5.2(a) be carried out by Project Co and the Project Co Parties using their own experiences and expertise in accordance with the standard of care set out in Section 11.2(a)(viii) and in accordance with the representations and warranties of Project Co set out in Section 7.1. (b) Except as may constitute a Design Issue properly characterized as a Project Co Design Issue under Section 11.17, and except in respect of those Contract Documents which, under the terms of this Project Agreement, Project Co is required to prepare or produce, Project Co shall not be responsible for verifying that the Contract Documents are in compliance with Applicable Law. (c) If the Contract Documents are at variance with Applicable Law, or if, subsequent to the Submission Date, changes are made to Applicable Law which require modification to the Contract Documents, Project Co shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming known. The Consultant will make the changes required to the Contract Documents as provided in Article 21 below and Schedule 11 – Change Procedure. (d) If Project Co fails to notify the Consultant in writing, fails to obtain direction as required in Section 5.2(c), and performs Work knowing it to be contrary to any Applicable Law, Project Co shall be responsible for and shall correct the violations thereof, and shall bear the costs, expenses and damages attributable to its failure to comply with the provisions of such Applicable Law.

Appears in 1 contract

Samples: Project Agreement