Duty to Comply. 8.3.2.1 Subject to Section 8.3.1, Developer shall implement all Safety Compliance as expeditiously as reasonably possible following issuance of the Safety Compliance Order. Developer shall diligently prosecute the work necessary to achieve such Safety Compliance until completion. 8.3.2.2 Developer shall be entitled to submit a Claim for Extra Work Costs, Delay Costs or time extensions relating to compliance with a Safety Compliance Order as provided in Article 9. Notwithstanding the provisions in this Section 8.3.2.2, Developer shall not be entitled to any compensation, extension of time or other claim against the Department to the extent that the Safety Compliance Order is the result of the negligence, willful misconduct, or breach of applicable Law or contract by Developer or any Developer-Related Entity.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Duty to Comply. β
8.3.2.1 Subject to Section 8.3.1, Developer shall implement all Safety Compliance as expeditiously as reasonably possible following issuance of the Safety Compliance Order. Developer shall diligently prosecute the work necessary to achieve such Safety Compliance until completion.
8.3.2.2 Developer shall be entitled to submit a Claim for Extra Work Costs, Delay Costs or time extensions relating to compliance with a A Safety Compliance Order is a Relief Event which may entitle Developer to compensation, Completion Deadline extension, performance relief and other relief as provided in Article 9. Notwithstanding the provisions in this Section 8.3.2.2, Developer shall not be entitled to any compensation, extension of time or Completion Deadline extension, performance relief or other claim against the Department to the extent that the Safety Compliance Order is the result of the negligence, willful misconduct, or breach of applicable Law or contract by Developer or any Developer-Related Entity.
Appears in 2 contracts
Samples: Public Private Partnership Agreement, Public Private Partnership Agreement
Duty to Comply. 8.3.2.1 Subject to Section 8.3.1, Developer shall implement all Safety Compliance as expeditiously as reasonably possible following issuance of the Safety Compliance Order. Developer shall diligently prosecute the work necessary to achieve such Safety Compliance until completion.
8.3.2.2 Developer shall be entitled to submit a Claim for Extra Work Costs, Delay Costs or time extensions relating to compliance with a A Safety Compliance Order is a Relief Event which may entitle Developer to compensation, Completion Deadline extension, performance relief and other relief as provided in Article 9. Notwithstanding the provisions in this Section 8.3.2.2, Developer shall not be entitled to any compensation, extension of time or Completion Deadline extension, performance relief or other claim against the Department to the extent that the Safety Compliance Order is the result of the negligence, willful misconduct, or breach of applicable Law or contract by Developer or any Developer-Related Entity.
Appears in 1 contract
Samples: Public Private Partnership Agreement