Claim Submission. Within 30 days of the Notice of Claim, the Contractor shall provide the School District in writing with a Claim, which shall include a clear description of the Claim, any and all changes in cost and in time to which the Contractor and its Subcontractors of any tier may be entitled under this Agreement for the Claim, and data supporting the Claim. The Claim of a Subcontractor may be brought only through the Contractor and only after the Contractor notifies the School District in writing that the Contractor has reviewed and agrees with the Claim. No act, omission, or knowledge, actual or constructive, of the School District shall in any way be deemed to be a waiver of the requirement for a timely written Claim unless the School District provides the Contractor with an explicit, unequivocal written waiver.
Claim Submission. All Claims must be submitted on or before the date of the Final Payment and shall include all documents necessary to substantiate the Claim. Contractor acknowledges and agrees that any untimely Claim shall be deemed waived. This limitation shall not apply to Claims which first arise after the Final Payment, including Claims asserted by third parties.
Claim Submission. In addition to the information required for other Claims, a Differing Site Condition Claim shall include the following information:
Claim Submission. When submitting a Death Claim for payment, the Ceding Company will provide Generali USA with proper claim documentation, including a copy of the proof of payment by the Ceding Company, information on the beneficiary and a copy of the insured's death certificate. In addition, for contestable claims, the Ceding Company will send to Generali USA a copy of all non-privileged claim related documents, information or underwriting papers.
Claim Submission. Within 21 days of the Notice of Claim, the Contractor shall provide both KCDA and the Client in writing with a Claim, which shall include a clear description of the Claim, all changes in cost and in time (direct, indirect, impact, and otherwise) to which the Contractor and Subcontractors of any tier are entitled, and data supporting the Claim. The claim of a Subcontractor may be brought only through the Contractor and only after the Contractor notifies KCDA and the Client in writing that the Contractor has reviewed and agrees with the Claim.
Claim Submission. It is the intention of the Parties that any Claim or potential Claim of Developer arising under and by virtue of the Contract Documents be brought to the attention of the Department at the earliest possible time in order that the matter may be resolved expeditiously, if possible, or other appropriate action promptly taken. If Developer believes it is entitled to Extra Work Costs, Delay Costs, Completion Deadline extensions, relief under Section 9.2, or relief under any other provision of the Contract Documents, then Developer shall comply with the Claim submission procedure described in Section 9.1.1.1.
Claim Submission. Within 21 days of the Notice of Claim, the Contractor shall provide both KCDA and the Client in writing with a Claim, which shall include a clear description of the Claim, any and all changes in cost and in time to which the Contractor and its Subcontractors of any tier may be entitled under this Agreement for the Claim, and data supporting the Claim. The claim of a Subcontractor may be brought only through the Contractor and only after the Contractor notifies KCDA and the Client in writing that the Contractor has reviewed and agrees with the Claim. No act, omission, or knowledge, actual or constructive, of the Client shall in any way be deemed to be a waiver of the requirement for a timely written Claim unless the Client provides the Contractor with an explicit, unequivocal written waiver. Failure to comply with these requirements shall constitute waiver of the Claim.
Claim Submission. Company may submit a Claim through the Obligo Platform Service. The Claim submission shall include sufficient detail describing the basis for the Claim so that a reasonable Tenant will be able understand the reason for the Claim. Claims may only be submitted at the end of the Lease Term or upon the Tenant’s vacancy. Claims may not be submitted after the Billing Authorization Term, and may not exceed the applicable Billing Authorization Value.
Claim Submission. If Developer believes that it is entitled to Extra Work Costs, Delay Costs, time extension or other relief under the Contract Documents, Developer shall submit a Claim and comply with the claims procedures and requirements as set forth in [Section of Division ].
Claim Submission. If a Claim arises, our goal is to learn about and address your concerns and, if we are unable to do so to your satisfaction, to provide you with a neutral and cost-effective means of resolving the dispute quickly. You agree that before filing any claim in arbitration, you must submit Claims by sending an email to xxxxxxxxxxxxxxxx@xxxxxxxxxxx.xxx at any time, or by calling (000) 000-0000 from Monday - Friday 7:00 AM to 5:00 PM PT.