Common use of Electrical Interconnection Facilities Clause in Contracts

Electrical Interconnection Facilities. The Electrical Interconnection Facilities shall be designed, procured, and constructed by Project Company. Upon achieving the Phase 1 Commercial Operation Date and GPA’s written acceptance thereof, the ownership, custody and control of the Electrical Interconnection Facilities shall be transferred by Project Company to GPA, after which the latter will operate and maintain the facilities in accordance with Prudent Utility Practices and the applicable system grid code at no cost to the Project Company. The transfer of the Electrical Interconnection Facilities shall be at no cost to GPA.

Appears in 5 contracts

Samples: Energy Conversion Agreement, Energy Conversion Agreement, Energy Conversion Agreement