Failure to Meet the Proposed Service Date Sample Clauses

Failure to Meet the Proposed Service Date. If the first Service Date fails to occur within sixty (60) calendar days of the first Proposed Service Date, the ISO, in its sole discretion, may terminate this Agreement by providing five (5) business days notice to Supplier declaring the ISO’s intention to terminate this Agreement; provided, however, that the ISO shall not have the right to terminate this Agreement for an additional sixty (60) calendar days if such failure is due to a Force Majeure Event. Notwithstanding anything to the contrary contained in this Section or this Agreement (including, without limitation, a Force Majeure Event), the ISO, in its sole discretion, may terminate this Agreement if the Service Date fails to occur within one hundred twenty (120) calendar days of the applicable Proposed Service Date by providing five (5) business days notice to Supplier declaring the ISO’s intention to terminate this Agreement. In the event that the ISO terminates this Agreement pursuant to this Section, Supplier shall pay the ISO the Credit Amount, as liquidated damages.
AutoNDA by SimpleDocs
Failure to Meet the Proposed Service Date. If the Service Date fails to occur within sixty (60) calendar days of the Proposed Service Date, the ISO, in its sole discretion, may terminate the LRP Resource by providing five (5) business days notice to Supplier declaring the ISO's intention to terminate such LRP Resource; provided, however, that the ISO shall not have the right to terminate such LRP Resource for an additional sixty (60) calendar days if such failure is due to a Force Majeure Event. Notwithstanding anything to the contrary contained in this Section or this Agreement (including, without limitation, a Force Majeure Event), the ISO, in its sole discretion, may terminate such LRP Resource if the Service Date fails to occur within one hundred twenty (120) calendar days of the Proposed Service Date by providing five (5) business days notice to Supplier declaring the ISO's intention to terminate such LRP Resource. In the event the ISO terminates the LRP Resource, Supplier shall pay the ISO that portion of the Credit Amount attributable to the terminated LRP Resource, as liquidated damages, and the ISO will adjust Schedule IV to reflect such termination. Notwithstanding the foregoing, in the event the Proposed DEP Regulations are either denied or not approved by June 1, 2005, the ISO, in its sole discretion, may terminate the affected LRP Resources (as indicated on Schedule IV) by providing five (5) business days notice to Supplier declaring the ISO's intention to terminate such LRP Resources, provided, however, Supplier shall not be obligated to pay the ISO liquidated damages attributable to the termination of such LRP Resources. After any such termination, the ISO will adjust Schedule IV to reflect such termination and reduce the amount of the letter or letters of credit or cash held in escrow provided pursuant to Section 2.4 by the remaining amount of the letter or letters of credit or cash held in escrow associated with such terminated LRP Resources.

Related to Failure to Meet the Proposed Service Date

  • Independence from Material Breach Determination Except as set forth in Section X.D.1.c, these provisions for payment of Stipulated Penalties shall not affect or otherwise set a standard for OIG’s decision that Xxxxx has materially breached this IA, which decision shall be made at OIG’s discretion and shall be governed by the provisions in Section X.D, below.

  • JOC - PRICING OF After Hours Coefficient What is your after hours coefficient for the RS Means Price Book for work performed after normal working hours? (FAILURE TO RESPOND PROHIBITS PART 2 JOC EVALUATION)

  • PRICING OF After Hours Coefficient What is your after hours coefficient for the RS Means Price Book for work performed after normal working hours?

  • Loop Testing/Trouble Reporting 2.1.6.1 Telepak Networks will be responsible for testing and isolating troubles on the Loops. Telepak Networks must test and isolate trouble to the BellSouth portion of a designed/non-designed unbundled Loop (e.g., UVL-SL2, UCL-D, UVL-SL1, UCL-ND, etc.) before reporting repair to the UNE Customer Wholesale Interconnection Network Services (CWINS) Center. Upon request from BellSouth at the time of the trouble report, Telepak Networks will be required to provide the results of the Telepak Networks test which indicate a problem on the BellSouth provided Loop. 2.1.6.2 Once Telepak Networks has isolated a trouble to the BellSouth provided Loop, and had issued a trouble report to BellSouth on the Loop, BellSouth will take the actions necessary to repair the Loop if a trouble actually exists. BellSouth will repair these Loops in the same time frames that BellSouth repairs similarly situated Loops to its End Users. 2.1.6.3 If Telepak Networks reports a trouble on a non-designed or designed Loop and no trouble actually exists, BellSouth will charge Telepak Networks for any dispatching and testing (both inside and outside the CO) required by BellSouth in order to confirm the Loop’s working status. 2.1.6.4 In the event BellSouth must dispatch to the end-user’s location more than once due to incorrect or incomplete information provided by Telepak Networks (e.g., incomplete address, incorrect contact name/number, etc.), BellSouth will xxxx Xxxxxxx Networks for each additional dispatch required to repair the circuit due to the incorrect/incomplete information provided. BellSouth will assess the applicable Trouble Determination rates from BellSouth’s FCC or state tariffs.

  • Solicitation Exceptions/Deviations Explanation If the bidder intends to deviate from the General Conditions Standard Terms and Conditions or Item Specifications listed in this proposal invitation, all such deviations must be listed on this attribute, with complete and detailed conditions and information included or attached. TIPS will consider any deviations in its proposal award decisions, and TIPS reserves the right to accept or reject any bid based upon any deviations indicated below or in any attachments or inclusions. In the absence of any deviation entry on this attribute, the proposer assures TIPS of their full compliance with the Standard Terms and Conditions, Item Specifications, and all other information contained in this Solicitation.

  • Payment for Material Completion The Contractor may request payment of the remaining contract balance, including retainage, less amounts credited the Owner or incurred as liquidated damages, and less amounts withheld for the Punchlist by reason of Minor Items or Permitted Incomplete Work (See Paragraph 6.5.3.2). Payment for Material Completion shall be made by a check payable jointly to the Contractor and Surety and shall be mailed to the Surety.

  • Failure to Meet Timelines Failure by the Union to comply with the timelines will result in the automatic withdrawal of the grievance. Failure by the Employer to comply with the timelines will entitle the Union to move the grievance to the next step of the procedure.

  • SUBMISSION OF THE MONTHLY MI REPORT 4.1 The completed MI Report shall be completed electronically and returned to the Authority by uploading the electronic MI Report computer file to MISO in accordance with the instructions provided in MISO. 4.2 The Authority reserves the right (acting reasonably) to specify that the MI Report be submitted by the Supplier using an alternative communication to that specified in paragraph 4.1 above such as email. The Supplier agrees to comply with any such instructions provided they do not materially increase the burden on the Supplier.

  • Solicitation Deviation/Compliance Does the vendor agree with the General Conditions Standard Terms and Conditions or Item Specifications listed in this proposal invitation? Yes

  • Response/Compliance with Audit or Inspection Findings A. Grantee must act to ensure its and its Subcontractors’ compliance with all corrections necessary to address any finding of noncompliance with any law, regulation, audit requirement, or generally accepted accounting principle, or any other deficiency identified in any audit, review, inspection or investigation of the Grant Agreement and the services and Deliverables provided. Any such correction will be at Grantee’s or its Subcontractor's sole expense. Whether Xxxxxxx's action corrects the noncompliance shall be solely the decision of the System Agency. B. As part of the services, Grantee must provide to HHS upon request a copy of those portions of Grantee's and its Subcontractors' internal audit reports relating to the services and Deliverables provided to the State under the Grant Agreement. C. Grantee shall include the requirement to provide to System Agency (and any of its duly authorized federal, state, or local authorities) internal audit reports related to this Grant Agreement in any Subcontract it awards. Upon request by System Agency, Grantee shall enforce this requirement against its Subcontractor. Further, Grantee shall include in any Subcontract it awards a requirement that all Subcontractor Subcontracts must also include these provisions.