Final Payment Submissions Sample Clauses

Final Payment Submissions. Final payment shall be due on Contractor's submission of the following to Owner: 19.5.4.1 An affidavit declaring any indebtedness connected with the Work, e.g. payrolls or invoices for materials or equipment, to have been paid, satisfied or to be paid with the proceeds of final payment, so as not to encumber Owner's property; 19.5.4.2 As-built drawings, manuals, copies of warranties and all other close-out documents required by the Contract Documents; 19.5.4.3 Release of any liens, conditioned on final payment being received; 19.5.4.4 Consent of any surety; and
AutoNDA by SimpleDocs
Final Payment Submissions. Final payment, constituting the entire unpaid balance of the contract sum, shall be paid by the Owner to the Demolition Contractor when the Contract Work has been completed, and the Contract fully performed. Final payment will be made only in conjunction with Wyo. Stat. § 16-6-116 and 117, as amended. 19.5.4.1 No final payment will be made until the Demolition Contractor files a sworn statement, stating that all claims for material and labor performed under the Contract have been made and paid. The sworn statement shall be filed with the appropriate entity, as designated in Wyo. Stat. § 16-6-117. A copy of the sworn statement shall be provided to the Agency and Surety. Failure of the Demolition Contractor to provide the sworn statement to the Surety will not relieve the Surety from liability under the bond. 19.5.4.2 If any claim for material and labor is disputed, the sworn statement shall so state and include a copy of any claim or lien and the amount claimed. The amount claimed shall be deducted from the final payment and retained by the Agency until the dispute is resolved, as provided in Wyo. Stat. § 16-6-117. The parties agree that the Agency may, at its discretion, place the disputed amount in an interest bearing account. In the event the funds are placed in an interest bearing account, any and all accrued interest shall belong to the Agency. 19.5.4.3 Final payment to the Demolition Contractor based on its sworn statement of no disputed claims for material or labor shall not relieve the Surety from liability on any bond if outstanding material or labor claims or liens exist, and if material men and/or laborers properly followed the procedures described in Wyo. Stat. § 16-6-121.

Related to Final Payment Submissions

  • Payment Scheduling The earliest possible Scheduled Payment Date for each Xxxxxx will be designated within the portion of the Site through which the Service is offered when you are scheduling the payment. Therefore, the Service will not permit you to select a Scheduled Payment Date less than the earliest possible Scheduled Payment Date designated for each Xxxxxx. When scheduling payments you must select a Scheduled Payment Date that is no later than the actual Due Date reflected on your Xxxxxx statement unless the Due Date falls on a non-Business Day. If the actual Due Date falls on a non-Business Day, you must select a Scheduled Payment Date that is at least one (1) Business Day before the actual Due Date. Scheduled Payment Dates must be prior to any late date or grace period. Depending on the method of payment, your Eligible Transaction Account may be debited prior to the Scheduled Payment Date. For example, if the selected method of payment is a draft, the draft arrives earlier than the Scheduled Payment Date due to expedited delivery by the postal service, and the Xxxxxx immediately deposits the draft, your Eligible Transaction Account may be debited earlier than the Scheduled Payment Date.

  • Final Payment All items or Automated Clearing House (ACH) transfers credited to your account are provisional until we receive final payment. If final payment is not received, we may charge your account for the amount of such items or ACH transfers and impose a return item charge on your account. Any collection fees we incur may be charged to your account. We reserve the right to refuse or return any item or funds transfer.

  • Additional Payment In addition to any Spousal Support, in the event of Divorce: (check one)

  • Additional Payment Terms All payments must be made in U.S. dollars and delivered to us at any one of our branch offices or to the address shown on the monthly statement. If we receive your payment before 5:00 p.m. (Mountain Standard Time) on a business day, at the address shown on the front of your monthly statement or at any of our branch offices, we will credit your payment as of the date of receipt. All other payments will be credited to your Account on the next business day following receipt. We may accept late or partial payments as well as payments marked “PAID IN FULL” or other restrictive endorsements, without losing any of our rights under this Agreement and without such payments constituting full accord and satisfaction of the debt. If you make payments using personal checks, and your financial institution refuses to pay the check and returns it to us, you agree to pay a Return Payment Fee. If your loan Account balance is less than the minimum payment amount you must pay the entire balance. You may repay all or part of what you owe at any time. However, so long as you owe any amount you must continue to make your periodic minimum payment. Your minimum monthly payment will be allocated to your account in accordance with all applicable laws and regulations. Personal Identification Number. We will issue you a Personal Identification Number (“PIN”) to be used with your Card. You agree not to write this PIN on your Card, and not to carry your PIN with you at the same time as you carry your Card. We will treat any charge made by you using your Card and PIN as having been authorized by you. If you keep your PIN with the Card, we can refuse to reissue your Card. Change of Terms. We can change the terms of this Agreement, including all fees, other charges and Annual Percentage Rate, at any time, subject to applicable laws and regulations. Events of Default. You are in default if you fail to pay the minimum payment listed on each billing statement on time, file for bankruptcy, exceed your credit limit without our permission, or default on this or any other Nusenda Federal Credit Union Card Agreement you have with us. If you are in default, we may close your Account and require a shorter amortization of your account balance, subject to applicable laws and regulations. No notice is required. We may also declare the whole balance due if you die, if you make false or misleading statements on your application, or if other creditors attach or garnish your property. If you have given us a security interest in a share Account, share draft Account, or certificate of deposit, we may use the deposit amount to pay any amount you owe us. Collection Costs. If we have to refer collection of your Account to a lawyer (who is not our salaried employee), to the extent permitted by law, you will have to pay our attorney’s fee plus court costs and any other fees.

  • Payment Schedule The purchase price for timber sold under this contract shall be paid in advance as follows: The first payment shall be paid within 30 days of the notification of high bid or before operating, whichever occurs first. The first payment shall be 10 percent of the total estimated bid value. The total estimated bid value shall be the sum obtained by multiplying the estimated timber volumes by the prices given in Section 44 less the amount of the project work. Cash bid deposits shall be applied to the initial payment. Subsequent payments shall be made in advance of timber removal when log hauling begins. Each payment shall be made before the value of timber removed equals one-half an advance payment or within the time period stated on the billing if PURCHASER is more than one-half of a payment in advance. The amount of each advance payment shall be calculated by dividing the total estimated bid value less the initial payment by 9; with the total estimated bid value being the sum obtained by multiplying the estimated timber volumes by the prices given in Section 44 less the amount of the project work. STATE may accept partial payment, upon written request, if logging is inactive. However, the full amount of advance payment is paid before logging resumes. Partial payment must be sufficient to maintain a payment deposit equal to one-half of a regular advance payment. The total purchase price shall be calculated after all log scale is reported by multiplying prices in Section 44 by the scaled volume. STATE shall refund any advance payment in excess of the total price, or PURCHASER shall pay any deficit within 30 days of notice. PURCHASER's deposit account shall not accrue interest payable to PURCHASER.

  • DISTRIBUTION OF CONTRACTOR PRICE LIST AND CONTRACT APPENDICES Contractor shall provide Authorized Users with electronic copies of the Contract, including price lists and Appendices, upon request. Contract Updates will be handled as provided in Appendix C – Contract Modification Procedures.

  • FINAL COMPLETION AND FINAL PAYMENT 9.9.1 Upon receipt of written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such 9.9.2 Neither the final payment nor the remaining retained percentage shall become due until the Contractor submits to the Architect (1) an affidavit that all payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the State or its property might in any way be responsible, have been paid or otherwise satisfied; (2) consent of surety, if any, to final payment; (3) Other data establishing payment or satisfaction of all such obligations, including, but not limited to, receipts, releases, or other supporting documentation. and (4) final waivers of liens arising out of the Contract, to the extent and in such form as may be designated by the State. If any Subcontractor refuses to furnish a release or waiver required by the State, the Contractor may furnish a bond satisfactory to the State to indemnify him against any such lien. If any such lien remains unsatisfied after all payments are made, the Contractor shall refund to the State all moneys that the latter may be compelled to pay in discharging such lien, including all costs and reasonable attorneys' fees. 9.9.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by the issuance of Change Orders affecting final completion, and the Architect so confirms, the State shall, upon application by the Contractor and certification by the Architect, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipulated in the Contract Documents, and if bonds have been furnished as required by the Contract Documents, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Architect prior to certification of such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims. 9.9.4 The making of final payment shall constitute a waiver of all claims by the State except those arising from: (a) unsettled liens, (b) faulty or defective Work appearing after Substantial Completion, (c) failure of the Work to comply with the requirements of the Contract Documents, or (d) terms of any special warranties required by the Contract Documents. 9.9.5 The acceptance of final payment shall constitute a waiver of all claims by the Contractor except those previously made in writing and identified by the Contractor as unsettled at the time of the final Application for Payment.

  • Supplemental Payments Applicant shall make annual Supplemental Payments in an amount equal to, but not to exceed, the limit of the annual Supplemental Payment as set out Section 6.2 below, starting with the first complete or partial year of the Qualifying Time Period and accruing on January 1 of each year thereafter, and continuing through the third year following the end of the Tax Limitation Period.

  • FEES AND PAYMENT SCHEDULE The fees and payment schedule for furnishing services under this Contract shall be based on the rate schedule which is attached hereto as Exhibit B and by this reference incorporated herein. Said fees shall remain in effect for the entire term of the Contract. Contractor shall provide County with his/her/its Federal Tax I.D. number prior to submitting the first invoice.

  • Additional Payments If, for any taxable year, Executive shall be liable for the payment of an excise tax under Section 4999 and/or Section 409A or other substitute or similar tax assessment (the “Excise Tax”) of the Internal Revenue Code of 1986, as amended (the “Code”), including the corresponding provisions of any succeeding law, with respect to any payments or benefits under Section 9 of this Agreement or Sections 7 or 8 or any other provision of this Agreement, including but not limited to this Section 12 or under any benefit plan of the Company applicable to Executive individually or generally to executives or employees of the Company, then, notwithstanding any other provisions of this Agreement, the Company shall pay to the Executive an additional amount (the “Gross-Up Payment”) such that the net amount retained by the Executive, after deduction of the Excise Tax imposed on all such payments and benefits and of the federal, state and local income tax and Excise Tax imposed upon payments provided for in this Section 12, shall be equal to the payments and benefits due to the Executive hereunder and the payments and/or benefits due to the Executive under any benefit plan of the Company. Each Gross-Up Payment shall be made to Executive or as provided in Section 16 hereof, upon the later of (i) five (5) days after the date the Executive notifies the Company of its need to make such Gross-Up Payment, or (ii) the date of any payment causing the liability for such Excise Tax. The amount of any Gross-Up Payment under this section shall be computed by a nationally recognized certified public accounting firm designated jointly by the Company and the Executive. The cost of such services by the accounting firm shall be paid by the Company. If the Company and the Executive are unable to designate jointly the accounting firm, then the firm shall be the accounting firm used by the Company immediately prior to the Change in Control.