General Technical Requirements. a) The Concession Holder shall be responsible for selecting the route and path of the transmission line. The preliminary section selected for the transmission line contained in the preliminary engineering project shall be assessed by the Concession Holder, who will determine the final section. Measures shall be taken to prevent the line route from crossing archaeological zones, national parks and restricted zones. b) The Concession Holder shall be responsible for all aspects related to the construction and maintenance of the accesses to the substations, for which it shall adhere to the applicable existing standards. c) The Concession Holder shall be responsible for the following activities, among others: • Management of rights of way and payment of compensations to landowners or land occupants. The Grantor shall help with the awareness-raising activities for owners in order to have an expeditious management of the right of way. • Obtainment of Final Power Transmission Concession. • Coordinate with the concessionaires that are developing a project or have facilities within the route of the line, or where it is necessary to carry out works for the connection to the substations that are part of the scope of this project. • Obtainment of Certificate of Absence of Archaeological Remains - XXXX (certificate issued by the Ministry of Culture about the non-affectation of archaeological remains). • Preparation of the Environmental Impact Study and its monitoring plan, the same that shall be developed within the existing legal framework, besides the approval of the corresponding public entities. d) The Grantor shall be in charge of obtaining the favorable technical opinion for the referential section of the project issued by the Peruvian Service for Natural Protected Areas (SERNANP). e) The easement strip for 220 kV lines shall be of at least 25 m. In the areas with presence of trees or objects that due to their height and proximity to the line pose a potential hazard for the people moving in the area, or for the line itself (in case of dangerous proximity or in the event of a potential fall of these trees on the line), the corresponding measures shall be considered to eliminate or minimize these risks, such as the removal or cutting of these trees.
Appears in 2 contracts
Samples: Concession Contract, Concession Contract
General Technical Requirements. a) The Concession Holder shall be responsible for selecting the route and path of the transmission line. The preliminary section selected for the transmission line contained in the preliminary engineering project shall be assessed by the Concession Holder, who will determine the final section. Measures shall be taken to prevent the line route from crossing archaeological zones, national parks and restricted zones.
b) The Concession Holder shall be responsible for all aspects related to the construction and maintenance of the accesses to the substations, for which it shall adhere to the applicable existing standards.
c) The Concession Holder shall be responsible for the following activities, among others: • Management of rights of way and payment of compensations to landowners or land occupants. The Grantor shall help with the awareness-raising activities for owners in order to have an expeditious management of the right of way. • Obtainment of Final Power Transmission Concession. • Coordinate with the concessionaires that are developing a project or have facilities within the route of the line, or where it is necessary to carry out works for the connection to the substations that are part of the scope of this project. • Obtainment of Certificate of Absence of Archaeological Remains - XXXX (certificate issued by the Ministry of Culture about the non-affectation of archaeological remains). • Preparation of the Environmental Impact Study and its monitoring plan, the same that shall be developed within the existing legal framework, besides the approval of the corresponding public entities.
d) The Grantor shall be in charge of obtaining the favorable technical opinion for the referential section of the project issued by the Peruvian Service for Natural Protected Areas (SERNANP).
e) The easement strip for 220 kV lines shall be of at least 25 m. In the areas with presence of trees or objects that due to their height and proximity to the line pose a potential hazard for the people moving in the area, or for the line itself (in case of dangerous proximity or in the event of a potential fall of these trees on the line), the corresponding measures shall be considered to eliminate or minimize these risks, such as the removal or cutting of these trees.