GOVERNANCE PROCEDURES. 7.3.1 The Implementation Agency shall document the agreed structures in a procedures manual. 7.3.2 The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- reading material, shall be distributed at least one week in advance of the relevant meeting. 7.3.3 All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed. 7.3.4 The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this. 7.3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter. 7.3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1 7.3.7 All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise). 7.3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementation:
Appears in 2 contracts
Samples: Master Services Agreement, Master Services Agreement
GOVERNANCE PROCEDURES. 7.3.1 3.1 The Implementation Agency shall document the agreed structures in a procedures manual.
7.3.2 3.2 The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- pre-reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3 All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4 The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1
7.3.7 3.7 All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementation:SCHEDULE – VI - TERMS OF PAYMENT SCHEDULE
Appears in 1 contract
Samples: Contract Agreement
GOVERNANCE PROCEDURES. 7.3.1 3.1. The Implementation Agency shall document the agreed structures in a procedures manual.
7.3.2 3.2. The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3. All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4. The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5. In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6. The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1.
7.3.7 3.7. All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8. If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours endeavors to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementation:.
Appears in 1 contract
Samples: Master Service Agreement
GOVERNANCE PROCEDURES. 7.3.1 (a) The Implementation Agency System Integrator shall document the agreed structures in a procedures manual.
7.3.2 (b) The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- reading prereading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 (c) All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 (d) The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 (e) In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 (f) The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1
7.3.7 (g) All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 (h) If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementation:.
Appears in 1 contract
Samples: Master Service Agreement
GOVERNANCE PROCEDURES. 7.3.1 3.1 The Implementation Agency System Integrator shall document the agreed structures in a procedures manual.
7.3.2 3.2 The agenda for each meeting of the PIU PMU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIUPMU, along with relevant pre- pre-reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3 All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4 The Parties shall ensure as far as reasonably practicable that the PIU PMU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1
7.3.7 3.7 All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementation:.
Appears in 1 contract
Samples: Master Service Agreement (Msa) and Service Level Agreement (Sla)
GOVERNANCE PROCEDURES. 7.3.1 3.1 The Implementation <<‘Portal Development and Management Agency (PDMA)’>> shall document the agreed structures in a procedures manual.
7.3.2 3.2 The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- pre-reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3 All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4 The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1
7.3.7 3.7 All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementationSchedule of CMS are presented as below:
A. Project Preparation and Business Blueprint Phase
B. Procurement and installation of Hardware, Network and System Software
Appears in 1 contract
Samples: Master Service Agreement
GOVERNANCE PROCEDURES. 7.3.1 3.1 The Implementation Agency System Integrator shall document the agreed structures in a procedures manual.
7.3.2 3.2 The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3 All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4 The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1
7.3.7 3.7 All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementation:
Appears in 1 contract
Samples: Contract Agreement for Selection of System Integrators
GOVERNANCE PROCEDURES. 7.3.1 3.1 The Implementation Agency <<‘Total Solution and Service Provider (TSSP)’>> shall document the agreed structures in a procedures manual.
7.3.2 3.2 The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3 All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4 The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1
7.3.7 3.7 All negotiations, statements and / or and/or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours endeavors to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following Title: Originator: Sponsor: Date of Initiation: (To include reason for change and appropriate details/specifications. Identify any attachments as A1, A2, and A3 etc.) Authorised by BSBCL Date: Name: Signature: Received by the SI Date: Name: (Identify any attachments as B1, B2, and B3 etc.) Changes to Services, charging structure, payment profile, documentation, training, service levels and component working arrangements and any other contractual issue. Charges for Implementation: (including a schedule would be followed for payment during the Project implementation:of payments) Other Relevant Information: (including value-added and acceptance criteria)
Appears in 1 contract
Samples: Master Services Agreement
GOVERNANCE PROCEDURES. 7.3.1 3.1 The Implementation Agency SI for Compute Infrastructure shall document the agreed structures in a procedures manual.
7.3.2 3.2 The agenda for each meeting of the PIU shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIU, along with relevant pre- reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3 All meetings and proceedings will be documented such documents to be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4 The Parties shall ensure as far as reasonably practicable that the PIU shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article 9.1
7.3.7 3.7 All negotiations, statements and / or documentation pursuant to these Articles shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementationexecution:
Appears in 1 contract
Samples: Contract Agreement for Selection of System Integrator for Compute Infrastructure
GOVERNANCE PROCEDURES. 7.3.1 3.1 The Implementation Agency Service Operator shall document the agreed structures in a procedures manual.
7.3.2 3.2 The agenda for each meeting of the PIU Project Steering Committee shall be set to reflect the discussion items referred to above and extraordinary items may be added either with the agreement of the Parties or at the request of either Party. Copies of the agenda for meetings of the PIUProject Steering Committee, along with relevant pre- pre-reading material, shall be distributed at least one week in advance of the relevant meeting.
7.3.3 3.3 All meetings and proceedings will be documented such documented. Such documents to shall be distributed to the Parties and copies shall be kept as a record. All actions, responsibilities and accountabilities arising out of any meeting shall be tracked and managed.
7.3.4 3.4 The Parties shall ensure as far as reasonably practicable that the PIU Project Steering Committee shall resolve the issues and resolve the objectives placed before them and that members representing that Party are empowered to make relevant decisions or have easy access to empowered individuals for decisions to be made to achieve this.
7.3.5 3.5 In order formally to submit a Disputed Matter to the aforesaid for a, one Party ("Claimant") shall give a written notice ("Dispute Notice") to the other Party. The Dispute Notice shall be accompanied by (a) a statement by the Claimant describing the Disputed Matter in reasonable detail and (b) documentation, if any, supporting the Claimant's position on the Disputed Matter.
7.3.6 3.6 The other Party ("Respondent") shall have the right to respond to the Dispute Notice within 7 30 days after receipt of the Dispute Notice. In the event that the parties are unable to resolve the Disputed Matter within a further period of 7 30 days, it shall refer the Disputed Matter to next level of the dispute resolution for action as per the process mentioned in article Clause 9.1
7.3.7 3.7 All negotiations, statements and / or documentation pursuant to these Articles Clause shall be without prejudice and confidential (unless mutually agreed otherwise).
7.3.8 3.8 If the Disputed Matter is having a material effect on the operation of the Services (or any of them or part of them) the Parties will use all their respective reasonable endeavours endeavors to reduce the elapsed time in reaching a resolution of the Disputed Matter. The following schedule would be followed for payment during the Project implementation:.
Appears in 1 contract
Samples: Master Service Agreement