Guaranteed Substantial Completion Dates Clause Samples
The Guaranteed Substantial Completion Dates clause establishes firm deadlines by which a contractor must achieve substantial completion of a project or specific project milestones. In practice, this clause sets out exact dates that are contractually binding, often linked to project schedules and may include provisions for penalties or incentives if the dates are missed or met. Its core function is to provide certainty and accountability regarding project timelines, helping to manage expectations and reduce the risk of delays.
POPULAR SAMPLE Copied 1 times
Guaranteed Substantial Completion Dates. Contractor shall achieve Substantial Completion of Subproject 1 no later than the date specified in Attachment E (“Guaranteed Substantial Completion Date for Subproject 1”) and Substantial Completion of Subproject 2 no later than the date specified in Attachment E (“Guaranteed Substantial Completion Date for Subproject 2”), (each a “Guaranteed Substantial Completion Date” and collectively, the “Guaranteed Substantial Completion Dates”). The Guaranteed Substantial Completion Dates shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Substantial Completion Dates. The Work to be performed for each SGF under this Agreement shall commence on the date of delivery of the Notice to Proceed for such SGF, and subject to the extensions provided for in this Agreement, Contractor shall perform the Work such that Substantial Completion of each SGF shall occur not later than the Guaranteed Substantial Completion Date for such SGF. In the event that Contractor does not achieve Substantial Completion of a SGF by its Guaranteed Substantial Completion Date as set forth in Attachment VIII, Contractor shall be liable for damages for failure to reach Substantial Completion of each SGF by the Guaranteed Substantial Completion Date for the SGF pursuant to Section 7.3.
Guaranteed Substantial Completion Dates. Contractor shall achieve:
1. Substantial Completion of Train 1 no later than [***] ([***]) Days following Contractor’s receipt of NTP (“Guaranteed Train 1 Substantial Completion Date”); and
2. Substantial Completion of Train 2 no later than [***] ([***]) Days following Contractor’s receipt of NTP (“Guaranteed Train 2 Substantial Completion Date”), each a “Guaranteed Substantial Completion Date” and collectively, the “Guaranteed Substantial Completion Dates.” The Guaranteed Substantial Completion Dates shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Substantial Completion Dates. Contractor shall achieve:
1. Substantial Completion of Train 1 no later than [***] ([***]) Days following Contractor’s receipt of NTP (“Guaranteed Train 1 Substantial Completion Date”); and
2. Substantial Completion of Train 2 no later than [***] ([***]) Days following Contractor’s receipt of NTP (“Guaranteed Train 2 Substantial Completion Date”),
Guaranteed Substantial Completion Dates. Subject to Section 5.2C, 1. Contractor shall achieve Substantial Completion of Train 1 on or before *** (***) Days after issuance of LNTP No. 1 (“Guaranteed Train 1 Substantial Completion Date”);
Guaranteed Substantial Completion Dates. Except as otherwise stated in this Contract, Contractor guarantees that:
(i) Phase 1 will achieve Substantial Completion on or before [ * * * ]*; and