Liability for delay costs. Where an EOT has been granted in accordance with clause 11.4 due to a Delay Event, the Contractor will be entitled to be paid the additional direct costs actually incurred by the Contractor as a result of the Delay Event (to the extent not already included in a variation priced under clause 16), as verified and substantiated by the Contractor by reason of the delay and up to the Delay Costs Cap, provided that the Contractor takes all reasonable steps to mitigate the effect of the Delay Event including through reallocation or redeployment of resources where reasonable to do so.
AutoNDA by SimpleDocs

Related to Liability for delay costs

  • Liability for Loss If Included Timber is destroyed or damaged by an unexpected event that significantly changes the nature of Included Timber, such as fire, wind, flood, insects, disease, or similar cause, the party holding title shall bear the timber value loss resulting from such destruction or damage; except that such losses after removal of timber from Sale Area, but before Scaling, shall be borne by Purchaser at Current Contract Rates and Required Deposits. Deterioration or loss of value of salvage timber is not an unexpected event, except for deterioration due to delay or interruption that qualifies for Contract Term Adjustment or under B8.33.

  • Compensation for Damages or Losses When investments by investors of either Contracting Party suffer damages or losses owing to war, armed conflict, a state of national emergency, revolt, insurrection, riot or other similar events in the territory of the other Contracting Party, they shall be accorded by the latter Contracting Party a treatment, as regards compensation or other settlement, not less favourable than that accorded to its own investors or to investors of any Third State.

  • Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Liability for Specific Obligations The Administrator will be liable only for its specific obligations under this Agreement. All other liability is expressly waived and released as a condition of, and consideration for, the execution of this Agreement by the Administrator. The Administrator will be liable for its willful misconduct, bad faith or negligence in performing its obligations under this Agreement.

  • Liability for Taxes (i) Seller shall be liable for and pay, and pursuant to ARTICLE XI shall indemnify and hold harmless each Buyer Group Member from and against any and all Losses and Expenses incurred by such Buyer Group Member in connection with or arising from (A) Taxes imposed on the Company or for which the Company may otherwise be liable as a result of having been a member of a Company Group (including Taxes for which the Company may be liable pursuant to Treasury Regulation § 1.1502-6 or similar provisions of state, local or foreign law as a result of having been a member of a Company Group and any Taxes resulting from the ceasing to be a member of any Company Group) and (B) Taxes imposed on the Company or for which the Company may otherwise be liable for any taxable year or period that ends on or before the Closing Date and the portion of any Straddle Period ending on and including the Closing Date (the “Pre-Closing Tax Period”), except, in each case, to the extent such Taxes were included on the Closing Date Balance Sheet and taken into account in determining the Adjusted Purchase Price. (ii) For purposes of paragraph (a)(i), whenever it is necessary to determine the liability for Taxes of the Company for a Straddle Period, the determination of the Taxes of the Company for the portion of the Straddle Period ending on and including the Closing Date shall be determined by assuming that the Straddle Period consisted of two taxable years or periods, one which ended at the close of the Closing Date and the other which began at the beginning of the day following the Closing Date and items of income, gain, deduction, loss or credit of the Company for the Straddle Period shall be allocated between such two taxable years or periods on a “closing of the books basis” by assuming that the books of the Company were closed at the close of the Closing Date, provided, however, that exemptions, allowances, deductions or Taxes that are calculated on an annual basis, such as property Taxes and depreciation deductions, shall be apportioned between such two taxable years or periods on a daily basis. (iii) Seller shall be entitled to the amount of any refund or credit of Taxes of the Company (including any interest relating thereto) with respect to a Pre-Closing Tax Period to the extent such Taxes were paid by the Company prior to the Closing or by a Seller after the Closing pursuant to Section 8.2(a) or ARTICLE XI which refund or credit is actually recognized by Buyer or its Affiliates (including the Company) after the Closing, net of any cost to Buyer and its Affiliates attributable to the obtaining and receipt of such refund or credit, except to the extent such refund or credit arises as the result of a carryback of a loss or other tax benefit from a Tax period (or portion thereof) beginning after the Closing Date or such refund or credit was included on the Closing Date Balance Sheet and taken into account in determining the Adjusted Purchase Price. Buyer shall pay, or cause to be paid, to Seller any amount to which Seller is entitled pursuant to the prior sentence within fifteen (15) days of the receipt or recognition of the applicable refund or credit by Buyer or its Subsidiaries. To the extent requested by Seller, Buyer will reasonably cooperate with Seller in obtaining such refund or credit, including through the filing of amended Tax Returns for periods ending before or on the Closing Date or refund claims. To the extent such refund or credit is subsequently disallowed or required to be returned to the applicable Governmental Body, Seller agrees promptly to repay the amount of such refund or credit to Buyer. Buyer shall be entitled to any refund or credit with respect to Taxes (including any interest relating thereto) that results from the carryback of losses, credits or similar items from a taxable year or period that begins after the Closing Date and is attributable to the Company and, to the extent such refund is actually received by Seller or its Affiliates, any such refund or credit shall be paid by Seller to Buyer within fifteen (15) days of the receipt of such refund by Seller. Buyer shall be entitled to any refund or credit included on the Closing Date Balance Sheet and taken into account in determining the Adjusted Purchase Price. Buyer and Seller shall take reasonable steps as may be requested by the other Party to obtain any refund or credit to which such Party is entitled under this subparagraph (iii). (iv) Buyer shall be liable for and pay, and pursuant to ARTICLE XI shall indemnify and hold harmless Seller from and against any and all Losses incurred by Seller in connection with or arising from any real property transfer Tax, sales Tax, use Tax, stamp Tax, stock transfer Tax, or other similar Tax imposed on the transactions contemplated by this Agreement.

  • Liability for Damages 1. The Purchaser shall be liable for any damages sustained by the State arising from Purchaser’s breach of the terms of this Contract and the State may cause all or part of the performance bond to be forfeited to recover such damages. 2. In the event that a portion of the timber sale under this Contract is resold as a result of the Purchaser’s forfeiture and the stumpage rate pursuant to the resold contract is lower than the stumpage rate provided herein, the difference between the original rate and the new rate shall be considered damages and the Purchaser shall be liable to the State for those damages. The State may cause all or part of the Purchaser’s performance bond to be forfeited to recover such damages.

  • Liability for Default 11.1 The Parties agree and acknowledge that if any Party (“Defaulting Party”) breaches any provision of this Agreement, or fails to perform any obligation under this Agreement, it shall constitute a default under this Agreement (“Default”) and the non-defaulting Party shall be entitled to request the Defaulting Party to cure such Default or take remedies within a reasonable time period. If the Defaulting Party fails to cure such Default or take remedies within such reasonable time period or within ten (10) days after the non-Defaulting Party notifies the Defaulting Party in writing and requests it to cure such Default, then the non-defaulting Party is entitled to decide at its discretion: 11.1.1 If Party B is the Defaulting Party, Party A shall be entitled to terminate this Agreement and request the Defaulting Party to indemnify it against all the damages, or to request the Defaulting Party to continue to perform its obligations under this Agreement and to request the Defaulting Party to indemnify it for all the damages; 11.1.2 If Party A is the Defaulting Party, Party B shall be entitled to request the Defaulting Party to indemnify it for all the damages, unless otherwise stipulated by the Laws, the non-defaulting Party shall not be entitled to terminate or cancel this Agreement under any circumstances. 11.2 Notwithstanding any other provisions of this Agreement, the validity of this Section 11 shall not be affected by any suspension or termination of this Agreement.

  • Liability for defects 5.1 The Customer is required to inspect the delivered Products without undue delay after delivery and to report any defects. 5.2 The delivered Products are deemed to have been approved if XXXX, with regard to obvious defects, obvious shortages or other defects which were or would have been identifiable in the course of an immediate, careful inspection, has not received notifi- cation of the defect within 7 days of delivery of the product, or otherwise – in the case of unclear or hidden defects – within 7 days of the discovery of the defect or the time at which the defect was identifiable to the Customer in the course of normal use of the Product without closer inspection. 5.3 In the event of a justified complaint, the Customer will be entitled to two attempts to rectify defects or make a replacement delivery at XXXX'x discretion free of charge within a reasonable period of time. Shortages will be delivered subsequently. If two attempts to rectify defects or make a replacement delivery within a reasonable period of time are unsuccessful, the Customer will be entitled to the statutory rights, subject to the provisions of clause 7. Subsequent performance will include neither removal of the defective item nor reassembly if XXXX was not originally required to carry out assembly. The expenses required for the purpose of inspection and subsequent performance, in particular transport, travel, labour and material costs (not: removal and assembly costs), insofar as these are not increased because the subject matter of the contract is located at a place other than our Customer's place of performance, will be borne by XXXX if there is actually a defect. Otherwise, XXXX may demand compensation from the Customer for the costs incurred by the unjustified request for rectification of the defect (in particular inspection and transport costs), unless the lack of defectiveness was not identifiable for the Customer. XXXX can refuse to rectify defects or make a replacement delivery if the Customer does not fulfil its payment obligations towards XXXX to an extent that corresponds to the defect-free part of the service provided. 5.4 No warranty will be assumed, in particular, in the following cases: Unsuitable or in- correct use by the Customer or by third parties instructed by the Customer, in particular through the use of insufficiently qualified personnel, faulty assembly or commission- ing, natural wear and tear (wearing parts), faulty or negligent handling, improper maintenance, unsuitable operating materials, defective construction work, unsuitable construction land, chemical, electrochemical or electrical influences, provided XXXX is not responsible for these circumstances. 5.5 XXXX is also not required to provide a warranty insofar as defects of Products are based on defective materials supplied by the Customer or insofar as defects of Products are based on the fact that the Customer has prescribed the execution of the order ac- cording to construction plans of third parties. 5.6 A delivery of used Products agreed with the Customer in the individual case is made to the exclusion of any warranty, unless XXXX has caused the defect intentionally or through gross negligence or has fraudulently concealed the defect. 5.7 The warranty period will be one year from delivery or, where acceptance was stipu- lated, from acceptance. Replaced parts will become our property and must be sent to us at our request. If shipping, assembly or commissioning is delayed through no fault of our own, our liability will expire no later than twelve months after the transfer of risk. 5.8 The right of recovery in accordance with sections 445a, 445b German Civil Code (BGB) is excluded, unless XXXX has caused the defect intentionally or by gross neg- ligence or has fraudulently concealed the defect.

  • INDEMNIFICATION FOR DAMAGES, TAXES AND CONTRIBUTIONS CONTRACTOR shall exonerate, indemnify, defend, and hold harmless COUNTY (which for the purpose of paragraphs 5 and 6 shall include, without limitation, its officers, agents, employees and volunteers) from and against: A. Any and all claims, demands, losses, damages, defense costs, or liability of any kind or nature which COUNTY may sustain or incur or which may be imposed upon it for injury to or death of persons, or damage to property as a result of, arising out of, or in any manner connected with the CONTRACTOR'S performance under the terms of this Agreement, excepting any liability arising out of the sole negligence of the COUNTY. Such indemnification includes any damage to the or of CONTRACTOR and third persons. B. Any and all Federal, State and Local taxes, charges, fees, or contributions required to be paid with respect to CONTRACTOR and CONTRACTOR'S officers, employees and agents engaged in the performance of this Agreement (including, without limitation, unemployment insurance, social security and payroll tax withholding).