Maintenance obligations of theContractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall bepaid(if not included in the Schedule - H):
Appears in 3 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Maintenance obligations of theContractor. (i) The Contractor shall maintain the Project Highway for a period of [5 (five) / 10 (ten)] years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall bepaid(if not included in the Schedule - H):bepaid:
Appears in 2 contracts
Samples: nhidcl.com, nhidcl.com
Maintenance obligations of theContractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (fiveFive) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”), paid as per the provisions below. The Defect Liability for the wearing coat laid on the structures shall be 10 Years, commencing from the date of Completion Certificate, which will not be paid.For the performance of its Maintenance obligations, the Contractor shall bepaid(if not included in the Schedule - H):
Appears in 1 contract
Samples: Draft Contract Agreement
Maintenance obligations of theContractor. (i) The Contractor shall maintain the Project Highway for a period of 5 10 (fiveten) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). The Defect Liability corresponds to the complete structure except the wearing coat.For the performance of its Maintenance obligations, the Contractor shall bepaid(if not included in the Schedule - H):
Appears in 1 contract
Samples: Draft Contract Agreement
Maintenance obligations of theContractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall bepaid(if not included in the Schedule - H):bepaid:
Appears in 1 contract
Samples: Draft Contract Agreement
Maintenance obligations of theContractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall bepaid(if be paid (if not included in the Schedule - H):
Appears in 1 contract
Samples: Draft Contract Agreement