Notification of Early Interim Completion. (a) Unless Project Co obtains the prior written consent of WCH, in its sole discretion, Project Co shall not be entitled to the Interim Completion Certificate prior to, and the Interim Completion Date and Interim Payment Commencement Date shall not be earlier than, the Scheduled Interim Completion Date.
(b) If Project Co advises WCH that it expects to be able to achieve Interim Completion prior to the Scheduled Interim Completion Date, the WCH Representative shall be entitled to require Project Co to produce and submit to the WCH Representative a revised Works Schedule showing the manner and the periods in which the Works shall be performed and what the revised date for Interim Completion would be so as to enable WCH to consider at its sole discretion:
(i) whether to agree to an earlier Scheduled Interim Completion Date; and
(ii) what modifications, if any, shall be required to this Project Agreement in order to accommodate such earlier Scheduled Interim Completion Date.
Notification of Early Interim Completion. (a) Unless Project Co obtains the prior written consent of Contracting Authority, in Contracting Authority’s sole discretion,
(i) Project Co shall not be entitled to the First Interim Completion Certificate prior to, and the First Interim Completion Date shall not be earlier than, the Scheduled First Interim Completion Date; and
(ii) Project Co shall not be entitled to the Second Interim Completion Certificate prior to, and the Second Interim Completion Date shall not be earlier than, the Scheduled Second Interim Completion Date; and
(b) If Project Co advises Contracting Authority that it expects to be able to achieve an Interim Completion prior to the applicable Scheduled Interim Completion Date, the Contracting Authority Representative shall be entitled to require Project Co to produce and submit to the Contracting Authority Representative a revised Progress Works Schedule (or Recovery Schedule, as applicable), showing the manner and the periods in which the Works shall be performed and what the revised date for the First Interim Completion or the Second Interim Completion, as applicable, would be so as to enable Contracting Authority to consider at its sole discretion:
(i) whether to agree to an earlier Scheduled First Interim Completion Date or an earlier Scheduled Second Interim Completion Date, as applicable; and
(ii) what modifications, if any, shall be required to this Project Agreement in order to accommodate such earlier Scheduled First Interim Completion Date or Scheduled Second Interim Completion Date, as applicable. All costs associated with any such modifications to this Project Agreement shall be borne by Project Co.