Notification of Early Substantial Completion. (a) Unless Project Co obtains the prior written consent of Contracting Authority, in Contracting Authority’s sole discretion, Project Co shall not be entitled to the Substantial Completion Certificate prior to, and the Substantial Completion Date and Substantial Completion Payment Date shall not be earlier than, the Scheduled Substantial Completion Date.
(b) If Project Co advises Contracting Authority that Project Co expects to be able to achieve Substantial Completion prior to the Scheduled Substantial Completion Date, the Contracting Authority Representative shall be entitled to require Project Co to produce and submit to the Contracting Authority Representative a revised Progress Works Schedule or Recovery Schedule, as applicable, showing the manner and the periods in which the Works shall be performed and what the revised date for Substantial Completion would be so as to enable Contracting Authority to consider at its sole discretion:
(i) whether to agree to an earlier Scheduled Substantial Completion Date; and
(ii) what modifications, if any, shall be required to this Project Agreement in order to accommodate such earlier Scheduled Substantial Completion Date.
(c) All costs associated with any such modifications to this Project Agreement shall be borne by Project Co.
Notification of Early Substantial Completion. (a) Unless Project Co obtains the prior written consent of HMQ, in its sole discretion, Project Co shall not be entitled to the Substantial Completion Certificate prior to, and the Substantial Completion Date and Payment Commencement Date shall not be earlier than, the Scheduled Substantial Completion Date.
(b) If Project Co advises HMQ that it expects to be able to achieve Substantial Completion prior to the Scheduled Substantial Completion Date, the HMQ Representative shall be entitled to require Project Co to produce and submit to the HMQ Representative a revised Works Schedule showing the manner and the periods in which the Works shall be performed and what the revised date for Substantial Completion would be so as to enable HMQ to consider at its sole discretion:
(i) whether to agree to an earlier Scheduled Substantial Completion Date; and
(ii) what modifications, if any, shall be required to this Project Agreement in order to accommodate such earlier Scheduled Substantial Completion Date.
Notification of Early Substantial Completion. (a) Unless Project Co obtains the prior written consent of HRRH, in HRRH’s sole discretion, Project Co shall not be entitled to the Substantial Completion Certificate prior to, and the Substantial Completion Date and Payment Commencement Date shall not be earlier than, the Scheduled Substantial Completion Date.
Notification of Early Substantial Completion. (a) Unless Project Co obtains the prior written consent of CAMH, in its sole discretion, Project Co shall not be entitled to the Substantial Completion Certificate prior to, and the Substantial Completion Date and Payment Commencement Date shall not be earlier than, the Scheduled Substantial Completion Date.
Notification of Early Substantial Completion. (a) Unless Project Co obtains the prior written consent of WGH, in its sole discretion, Project Co shall not be entitled to the Substantial Completion Certificate prior to, and the Substantial Completion Date and Payment Commencement Date shall not be earlier than, the Scheduled Substantial Completion Date.
Notification of Early Substantial Completion. (a) Unless Project Co obtains the prior written consent of the Ministry, in its discretion, Project Co shall not be entitled to:
(i) the Phase One Substantial Completion Certificate prior to, and the Phase One Substantial Completion Date and a Phase One Milestone Payment Date shall not be earlier than, the Scheduled Phase One Substantial Completion Date; or
(ii) the Substantial Completion Certificate prior to, and the Substantial Completion Date and Substantial Completion Payment Commencement Date shall not be earlier than, the Scheduled Substantial Completion Date.
(b) If Project Co advises the Ministry that it expects to be able to achieve Phase One Substantial Completion or Substantial Completion prior to the Scheduled Phase One Substantial Completion Date or the Scheduled Substantial Completion Date, as applicable, the Ministry Representative shall be entitled to require Project Co to produce and submit to the Ministry Representative a revised Works Schedule showing the manner and the periods in which the Works shall be performed and what the revised date for Phase One Substantial Completion or Substantial Completion would be so as to enable the Ministry to consider at its discretion:
(i) whether to agree to an earlier Phase One Substantial Completion Date or Scheduled Substantial Completion Date; and
(ii) what modifications, if any, shall be required to this Project Agreement in order to accommodate such earlier Phase One Substantial Completion Date or Scheduled Substantial Completion Date.