Common use of OWNER NOTICE OF DELAYS Clause in Contracts

OWNER NOTICE OF DELAYS. The Owner may direct a delay in the Work for any reason by providing prompt written notice to the Construction Manager of the cause of such delays after the OWNER first recognizes the need for the delay. The Owner and the Construction Manager agree to take reasonable steps to mitigate the effect of such delays. If the Construction Manager incurs additional costs as a result of a delay that is caused by items (a) through (d) in subsection 6.3.1, the Construction Manager may be entitled to an equitable adjustment in the Contract Price. For the avoidance of doubt, the Construction Manager shall not be entitled to an adjustment in the Contract Price as a result of a delay that is caused by items (e) through (m) in subsection 6.3.1.

Appears in 4 contracts

Samples: Standard Agreement, Standard Agreement, Standard Agreement