OWNER'S RIGHT TO DO WORK Sample Clauses

OWNER'S RIGHT TO DO WORK. Owner reserves the right to perform other or additional work at or near the project site with other forces than those of the Contractor. If such work takes place within or next to the project site, Contractor will coordinate work with the other contractors or forces, cooperate with all other contractors or forces, carry out the Work in a way that will minimize interference and delay for all forces involved, place and dispose of materials being used so as not to interfere with the operations of another, and join the Work with the work of the others in an acceptable manner and perform it in proper sequence to that of the others. The Owner’s Authorized Representative will resolve any disagreements that may arise between or among Contractor and the other contractors over the method or order of doing all work (including the Work). In case of unavoidable interference, the Owner’s Authorized Representative will establish work priority (including the Work) which generally will be in the sequence that the contracts were awarded.
AutoNDA by SimpleDocs
OWNER'S RIGHT TO DO WORK. If Contractor neglects to prosecute work properly or fails to perform any provision of this Agreement, Owner, after three (3) days' written notice to Contractor, may, without prejudice to any other remedy he or she may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due the Contractor.
OWNER'S RIGHT TO DO WORK. Owner reserves the right to perform other or additional work at or near the project site with other forces than those of the Contractor. If such work takes place within or next to the project site, Contractor shall coordinate work with the other contractors or forces, cooperate with all other contractors or forces, carry out the Work in a way that will minimize interference and delay for all forces involved, place and dispose of materials being used so as not to interfere with the operations of another, and join the Work with the work of the others in an acceptable manner and perform it in proper sequence to that of the others. The Owner will resolve any disagreements that may arise between or among Contractor and the other contractors over the method or order of doing all work (including the Work). In case of unavoidable interference, the Owner will establish work priority (including the Work) which generally will be in the sequence that the contracts were awarded.
OWNER'S RIGHT TO DO WORK. If Contractor refuses or fails to prosecute any part of the Work with such diligence as will ensure completion within the time specified in this Agreement, as the same may be modified in writing from time to time, or otherwise fails to perform any of its obligations under this Agreement, Owner may, at any time after three (3) days written notice to Contractor, or in an emergency endangering life or property, after such notice, if any, as may be reasonable under the circumstances, without prejudice to any other rights or remedies, make good such deficiencies by such means as Owner may deem expedient and charge the cost thereof to Contractor.
OWNER'S RIGHT TO DO WORK. 2.M.1. Owner reserves the right to perform other or additional work at or near the project site with other forces than those of the Contractor.
OWNER'S RIGHT TO DO WORK. If, during the progress of the work or during the period of guarantee, the contractor fails to prosecute the work properly or to perform any provision of the contract, the owner, after seven (7) days' written notice sent by certified mail, return receipt requested, to the contractor from the designer, may perform or have performed that portion of the work. The cost of the work may be deducted from any amounts due or to become due to the contractor, such action and cost of same having been first approved by the designer. Should the cost of such action of the owner exceed the amount due or to become due the contractor, then the contractor or his surety, or both, shall be liable for and shall pay to the owner the amount of said excess.
OWNER'S RIGHT TO DO WORK. If CONTRACTOR should neglect to prosecute any ------------------------- substantive portion of the Work properly, OWNER, after five business (5) days' written notice to CONTRACTOR and CONTRACTOR fails to promptly initiate corrective action, may, without prejudice to any other remedy it may have, make good such deficiencies and may deduct the cost thereof from the payments then or thereafter due CONTRACTOR, and if such expenditures, together with said losses, damages and extra expenses, exceed the amount otherwise due to CONTRACTOR hereunder, CONTRACTOR agrees to pay to OWNER within thirty (30) Days the full amount of such excess, together with interest thereon at the prime rate of interest as published from time to time in the Wall Street Journal plus one percent (1%) until paid.
AutoNDA by SimpleDocs
OWNER'S RIGHT TO DO WORK. .1 The Owner, subject to the approval of the Engineer, may notify the Contractor and his surety, in writing, that the Contractor is in default of his contractual obligations and instruct him to correct the default within five (5) working days, if the Contractor should:
OWNER'S RIGHT TO DO WORK. If the Contractor should neglect to prosecute the Work properly or fail to perform any provision of the Contract, the Owner, after seven days' written notice to the Contractor, may, without prejudice to any other remedy he may have, make good such deficiencies and may deduct the cost thereof, including Architect's additional services and expenses made necessary by such default, neglect or failure, from the payment then or thereafter due the Contractor, provided however, that the Architect shall have approved both such action and the amount charged to the Contractor.
OWNER'S RIGHT TO DO WORK. Owner has the right to perform work ------------------------ relating to the Xxxxx Project with Owner's own work forces, and such work shall be performed to minimize any interference with or interruptions in Contractor's Work. Contractor will coordinate the sequence of such work and Owner will cooperate therewith.