PERMITS TO USE. 16.1 [The Works shall be carried out in [♦] Phases which may be completed in any order.]
16.2 Project Co shall notify the Independent Tester and the Authority's Representative of the date when Project Co (acting reasonably) considers that [a Phase of] the Works will be complete in accordance with the PTU Criteria not less than [♦] Business Days prior to such anticipated completion ("Expected PTU Date"). Such notice shall be accompanied by Project Co's detailed programme of activities (including Works) that Project Co intends to complete to ensure that the PTU Criteria are satisfied by the Expected PTU Date.
16.3 The parties each undertake to co-operate with the Independent Tester to ensure that the Independent Tester is familiar with all necessary aspects of the Project for the purposes of its role as described in this Clause 16 (Permits to Use).
16.4 Following receipt of the notice specified in Clause 16.2 (Permits to Use) the Authority's Representative and the Independent Tester shall be entitled to inspect the Works [relating to the relevant Phase] on the date or dates reasonably specified by Project Co in accordance with Clause 16.2 (Permits to Use), and to attend any of the tests on completion. Project Co shall, if so requested, accompany the Authority's Representative and the Independent Tester on any such inspection.
16.5 Pursuant to the terms of the Independent Tester Contract and subject to Clauses 16.10 to 16.12 (Snagging Items), the parties shall procure that the Independent Tester:
PERMITS TO USE