Program. 27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Program including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecast

Appears in 30 contracts

Samples: Agreement, www.mpwrd.gov.in, Agreement

AutoNDA by SimpleDocs

Program. 27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Program including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecast.

Appears in 16 contracts

Samples: www.tniuscbe.org, www.tniuscbe.org, www.tniuscbe.org

Program. 27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Program including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works Works, along with monthly cash flow forecast.

Appears in 10 contracts

Samples: nahep.icar.gov.in, nahep.icar.gov.in, Guru Nanak

Program. 27.1 Within the time stated in the Contract Data after the date of the letter of acceptance, the Contractor shall submit to the Engineer for approval a revised Program including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecast.

Appears in 2 contracts

Samples: www.geerfoundation.gujarat.gov.in, geerfoundation.gujarat.gov.in

AutoNDA by SimpleDocs

Program. 27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Program including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecast.

Appears in 1 contract

Samples: ofbcipher.s3.amazonaws.com

Program. 27.1 24.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Program including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecast.