PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing: 9.1.1 The anticipated time of commencement and completion of each of the various operations to be performed under this Contract; and 9.1.2 The sequence and interrelation of each of these operations with the others and with those of other related contracts; and 9.1.3 The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 10; and 9.1.4 The estimated amount in dollars the Contractor will claim on a monthly basis. 9.2 The proposed schedule shall be revised as directed by the Engineer, until finally approved by the Engineer, and after such approval, subject to the provisions of Article 11, shall be strictly adhered to by the Contractor. 9.3 If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 11, it shall promptly adopt such other or additional Means and Methods of Construction, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the City if the approved progress schedule is not met. 9.4 The Contractor will not receive any payments until the proposed progress schedule is submitted.
Appears in 9 contracts
Samples: Proposal for Bids, Proposal for Bids, Proposal for Bids
PROGRESS SCHEDULES. 9.1 9.1. To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:
9.1.1 9.1.1. The anticipated time of commencement and completion of each of the various operations to be performed under this Contract; and
9.1.2 9.1.2. The sequence and interrelation of each of these operations with the others and with those of other related contracts; and
9.1.3 9.1.3. The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 10; and
9.1.4 9.1.4. The estimated amount in dollars the Contractor will claim on a monthly basis.
9.2 9.2. The proposed schedule shall be revised as directed by the Engineer, until finally approved by the Engineer, and after such approval, subject to the provisions of Article 11, shall be strictly adhered to by the Contractor.
9.3 9.3. If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 11, it shall promptly adopt such other or additional Means and Methods of Construction, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the City if the approved progress schedule is not met.
9.4 9.4. The Contractor will not receive any payments until the proposed progress schedule is submitted.
Appears in 9 contracts
Samples: Construction Contract, Construction Contract, Standard Construction Contract
PROGRESS SCHEDULES. 9.1 42.1. To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, Resident Engineer or Project Manager, shall submit to the Engineer, Resident Engineer or Project Manager a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, Resident Engineer or Project Manager, and monthly cash flow requirements, showing:
9.1.1 42.1.1. The anticipated time of commencement and completion of each of the various operations to be performed under this Contract; and
9.1.2 42.1.2. The sequence and interrelation of each of these operations with the others and with those of other related contracts; and
9.1.3 42.1.3. The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 1043; and
9.1.4 42.1.4. The estimated amount in dollars the Contractor will claim on a monthly basis.
9.2 42.2. The proposed schedule shall be revised as directed by the EngineerEngineer or Project Manager, until finally approved by the EngineerEngineer or Project Manager, and after such approval, subject to the provisions of Article 1144, shall be strictly adhered to by the Contractor.
9.3 42.3. If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 1144, it shall promptly adopt such other or additional Means and Methods of Constructionthe Work, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the City if the approved progress schedule is not met.
9.4 42.4. The Contractor will not receive any payments until either the proposed progress schedule contemplated in this Article 42 or any other schedule required under Article 4 (if required) is submitted.
Appears in 5 contracts
Samples: Furnish and Install Agreement, Furnish and Install Agreement, Furnish and Install Agreement
PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to WorkWork or issuance of a Work Order, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:
9.1.1 The anticipated time of commencement and completion of each of the various operations to be performed under this Contractthe Work Order; and
9.1.2 The sequence and interrelation of each of these operations with the others and with those of other related contracts; and
9.1.3 The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 10; and
9.1.4 9.2 The estimated amount in dollars the Contractor will claim on a monthly basis.
9.2 9.3 The proposed schedule shall be revised as directed by the Engineer, until finally approved by the Engineer, and after such approval, subject to the provisions of Article 11, shall be strictly adhered to by the Contractor.
9.3 9.4 If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 11, it shall promptly adopt such other or additional Means and Methods of Construction, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the City if the approved progress schedule is not met.
9.4 9.5 The Contractor will not receive any payments until the proposed progress schedule is submitted.
Appears in 1 contract
Samples: Agreement for Boilers, Heaters, Repairs and Maintenance Services