PROGRESS SCHEDULES. A. Contractor shall develop a progress schedule and submit to the Engineer for review and comment before starting Work on the Site. The Contractor shall modify the schedule in accordance with the comments provided by the Engineer. B. The Contractor shall update and submit the progress schedule to the Engineer each month. The Owner may withhold payment if the Contractor fails to submit the schedule.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Demolition and Remediation Contract
PROGRESS SCHEDULES. A. Contractor shall develop a progress schedule and submit to the Engineer for review and comment before starting Work on the Site. The Contractor shall modify the schedule in accordance with the comments provided by the Engineer.
B. The Contractor shall update and submit the progress schedule to the Engineer each month. The Owner may withhold payment if the Contractor fails to submit the schedule.
Appears in 1 contract
Samples: Construction Contract
PROGRESS SCHEDULES. A. Contractor shall develop a progress schedule and submit to the Engineer Facilities Manager for review and comment before starting Work on at the SiteSites. The Contractor shall modify the schedule in accordance with the comments provided by the EngineerFacilities Manager.
B. The Contractor shall update and submit the progress schedule to the Engineer each month. The Owner may withhold payment Facilities Manager biweekly if the Contractor fails to submit the schedulebaseline schedule milestones are not met.
Appears in 1 contract
Samples: Construction Contract
PROGRESS SCHEDULES. A. Contractor shall develop a progress schedule and submit to the Engineer Project Manager for review and comment before starting Work on at the SiteSites. The Contractor shall modify the schedule in accordance with the comments provided by the EngineerProject Manager.
B. The Contractor shall update and submit the progress schedule to the Engineer each month. The Owner may withhold payment Project Manager biweekly if the Contractor fails to submit the schedulebaseline schedule milestones are not met.
Appears in 1 contract
Samples: Construction Contract
PROGRESS SCHEDULES. A. Contractor shall develop a progress schedule and submit to the Engineer Owner for review and comment before starting Work on the Site. The Contractor shall modify the schedule in accordance with the comments provided by the Engineer.
B. The Contractor shall update and submit the progress schedule to the Engineer each month. The Owner may withhold payment if the Contractor fails to submit the schedule.
Appears in 1 contract
Samples: Construction Contract