PROGRESS SCHEDULES. 43.1. As may be required pursuant to Article 4 or as directed by the Project Manager, to enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen
Appears in 2 contracts
Samples: Furnish and Install Agreement, Furnish and Install Agreement
PROGRESS SCHEDULES. 43.142.1. As may be required pursuant to Article 4 or as directed by the Project Manager, to enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen
Appears in 1 contract
Samples: Furnish and Install Agreement
PROGRESS SCHEDULES. 43.1. As may be required pursuant to Article 4 or as directed by the Project Manager, to enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen
Appears in 1 contract
Samples: Furnish and Install Agreement