Project Change Orders Final Sample Clauses

Project Change Orders Final. The execution of a Project Change Order by EPC Contractor shall constitute conclusive evidence of EPC Contractor’s agreement to the ordered changes in the Work, the Contract Documents as thus amended, EPC Contractor’s compensation and the Guaranteed Substantial Completion Date. EPC Contractor, by executing the Project Change Order, waives and forever releases any claim against Client for additional time or compensation for matters relating to or arising out of or resulting from the executed Project Change Order, unless such request for additional time or compensation is based on labor disputes, fire, unusual delay in the deliveries, abnormal adverse weather conditions not reasonably anticipatable, unavoidable casualties or any causes beyond EPC Contractor’s control, unforeseen field conditions that cannot be reasonably anticipated or expected, or by other causes which Client determines justify additional time and or compensation.
AutoNDA by SimpleDocs

Related to Project Change Orders Final

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Project Changes 1.8.1. All changes shall be administered per the UGC.

  • Change Order (5) The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Contract Changes Changes may not be made in the terms and conditions of this contract without the agreement and written permission of the Director of Housing.

  • For Lump Sum Change Order The payment and extension of time (if any) provided by this Change Order constitutes compensation in full to the Contractor and its Subcontractors and Suppliers for all costs and markups directly and indirectly attributable to the Change Order herein, for all delays related thereto and for performance of changes within the time stated.

  • Change Orders and Contract Amendments 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:

  • Other Change Orders For Change Orders involving the following situations that would materially affect the completion of the Work by lengthening the critical path of the Construction Progress Schedule, the Design Professional shall determine the appropriate number of days and thereby extend the Material Completion and Occupancy Date. The Contractor expressly agrees that the Contractor’s sole monetary remedy for such extensions of Contract Time shall be calculated at the daily rate established for Time Dependent Overhead Costs in the Contract.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • CHANGE ORDERS AND AMENDMENTS A. Any alterations, additions, or deletions to the terms of this Agreement, which are required by changes in federal or state law or by regulations, are automatically incorporated without written amendment hereto, and shall become effective on the date designated by such law or by regulation.

  • Change Order Conditions All Change Orders are issued under the following conditions and shall contain the following language as appropriate: