PROJECT CLOSEOUT Services. 7.1. At the conclusion of design, Garver will assist the Owner with project closeout by providing a final project report per the FAA NWM Standard Handout for Final Reports 620-05 will include all necessary documents required for FAA grant closeout. Closeout documentation will be provided within 30 days after bids have been received.
Appears in 1 contract
Samples: Work Order
PROJECT CLOSEOUT Services. 7.1. At the conclusion of designconstruction, Garver will assist the Owner with project closeout by providing a final project report per the following documents in accordance with AIP Sponsor Guide 1600 Grant Closeout within 45 days of receipt of Contractor closeout documents.
1. Final Construction Report in accordance with FAA NWM Standard Handout for Final Reports 620-05 will include all necessary documents required for FAA grant closeout. Closeout documentation will be provided within 30 days after bids have been receivedrequirements.
a. Brief Narrative of Work Accomplished
Appears in 1 contract
Samples: Supplemental Agreement
PROJECT CLOSEOUT Services. 7.15.1. At the conclusion of design, Garver will assist the Owner with project closeout by providing a the additional elements required in final project construction report per the FAA NWM Standard Handout for Final Reports 620-05 which will include all necessary documents required for FAA grant closeout. Closeout documentation will be provided within 30 90 days after bids have been receivedof the final payment to the Contractor. Garver will also update the airport’s ALD to show the completed project as “existing” and coordinate the submission of the updated ALD through OE/AAA.
Appears in 1 contract
Samples: Work Order
PROJECT CLOSEOUT Services. 7.16.1. At the conclusion of designconstruction, Garver will assist the Owner with project closeout by providing a final project report per the FAA NWM Standard Handout for Final Reports 620-05 which will include all necessary documents required for FAA grant closeout. Closeout documentation will be provided within 30 days after bids have been receivedof the final payment to the Contractor. Garver will also update the airport’s ALD to show the completed project as “existing” and coordinate the submission of the updated ALD through OE/AAA and provide Record Drawings.
Appears in 1 contract
Samples: Work Order